902 S BARRINGTON AVE 90049
Certificate Information: 902 S BARRINGTON AVE 90049
- Application / Permit
- 25016-10000-29469
- Plan Check / Job No.
- B25LA41294
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (17) Restaurant
- Work Description
- TI to existing restaurant.
- Permit Issued
- Issued on 12/2/2025
- Issuing Office
- Metro
- Current Status
- Issued on 12/2/2025
Permit Application Status History
| Submitted | 10/1/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 10/1/2025 | SALVADOR QUINTANILLA |
| Corrections Issued | 10/15/2025 | SALVADOR QUINTANILLA |
| Applicant returned to address corrections | 11/24/2025 | SALVADOR QUINTANILLA |
| Plan Check Approved | 12/2/2025 | SALVADOR QUINTANILLA |
| Issued | 12/2/2025 | APPLICANT |
Permit Application Clearance Information
| Food establishment approval | Cleared | 10/6/2025 | LACDHS APPROVED |
| Food Service Establishment | Cleared | 11/24/2025 | LEONARDO GONZALES |
Contact Information
| Contractor | H W Holmes Inc; Lic. No.: 945923-B | P O BOX 2302 CAMARILLO, CA 930112302 |
| Contractor | Owner-Builder | , |
| Engineer | Daoud,, Richard A; Lic. No.: S6585 | 714 W OLYMPIC BLVD STE 617 LOS ANGELES, CA 90015 |
Inspector Information
| CASIMIR BRITTON, (310) 914-3913 | Office Hours: 7:00-8:00 AM MON-FRI |
| SHAVONNE ESPINOZA, (310) 914-3913 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 12/18/2025 | Partial Approval | PAUL DAVIDSON |
| Light Gage Steel Frame | 2/25/2026 | Corrections Issued | CASIMIR BRITTON |
| Deputy Drilled-In Anchors | 2/27/2026 | Conditional Approval | CASIMIR BRITTON |
| Light Gage Steel Frame | 3/2/2026 | Partial Approval | CASIMIR BRITTON |
| Special/Order Compliance | 3/2/2026 | Corrections Issued | CASIMIR BRITTON |
| Light Gage Steel Frame | 3/9/2026 | Not Ready for Inspection | CASIMIR BRITTON |
| Deputy Drilled-In Anchors | 3/11/2026 | Conditional Approval | CASIMIR BRITTON |
| Footing/Foundation/Slab | 3/11/2026 | Conditional Approval | CASIMIR BRITTON |
| Deputy Reinf. Concrete | 3/13/2026 | Conditional Approval | CASIMIR BRITTON |
| Footing/Foundation/Slab | 3/16/2026 | Corrections Issued | CASIMIR BRITTON |
| Light Gage Steel Frame | 3/16/2026 | Corrections Issued | CASIMIR BRITTON |
| Drywall Nailing | 3/23/2026 | Partial Approval | CASIMIR BRITTON |
| T-Bar Ceiling | 4/23/2026 | Not Ready for Inspection | DANIEL VARNUM |
| Final | 5/1/2026 | Not Ready for Inspection | CASIMIR BRITTON |
| Light Gage Steel Frame | 5/5/2026 | Approved | CASIMIR BRITTON |
| Final | 5/28/2026 | Not Ready for Inspection | CASIMIR BRITTON |
| SGSOV-Seismic Gas S/O Valve | 5/28/2026 | SGSOV Not Ready | CASIMIR BRITTON |
| Smoke Detectors | 5/28/2026 | Not Ready for Inspection | CASIMIR BRITTON |
| Special/Order Compliance | 5/29/2026 | Corrections Issued | CASIMIR BRITTON |