16057-16059 W KNAPP ST 91343
Certificate Information: 16057-16059 W KNAPP ST 91343
- Application / Permit
- 25016-10000-29062
- Plan Check / Job No.
- B25VN25213
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- convert garage and portion of single family dwelling into JADU
- Permit Issued
- Issued on 12/18/2025
- Issuing Office
- Current Status
- CofO in Progress on 6/1/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 8/29/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 9/11/2025 | ARSALAN SHABESTARI |
| Assigned to Zoning Architect | 9/11/2025 | NICOLE SALEEBA |
| Corrections Issued | 9/18/2025 | ARSALAN SHABESTARI |
| Quality Review Completed | 9/30/2025 | PRANITA SHAH |
| Applicant returned to address corrections | 11/29/2025 | ARSALAN SHABESTARI |
| Plan Check Approved | 12/17/2025 | ARSALAN SHABESTARI |
| Issued | 12/18/2025 | APPLICANT |
| CofO in Progress | 6/1/2026 | MICHAEL CORTEZ |
Permit Application Clearance Information
| Address approval | Cleared | 10/24/2025 | DERRICK MAGEE |
| Eng Process Fee Ord 176,300 | Cleared | 10/24/2025 | DERRICK MAGEE |
| Sewer availability | Cleared | 10/24/2025 | DERRICK MAGEE |
| Grading Pre-Inspection | Cleared | 10/30/2025 | MICHAEL TEMPLE |
| Zoning Plan Check | Cleared | 11/7/2025 | NICOLE SALEEBA |
Contact Information
| Contractor | Arka Builders Inc; Lic. No.: 998231-B | , |
| Engineer | Shahbaz,, Shant Pierre; Lic. No.: NA93079 | , |
Inspector Information
| MICHAEL CORTEZ, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 1/26/2026 | Approved | GAREN HAYRAPETYAN |
| PLUMBING-Rough | 1/26/2026 | Approved | GAREN HAYRAPETYAN |
| ELECTRICAL-Rough | 2/10/2026 | Approved | GAREN HAYRAPETYAN |
| HVAC-Rough | 2/10/2026 | Conditional Approval | GAREN HAYRAPETYAN |
| PLUMBING-Rough | 2/10/2026 | Corrections Issued | GAREN HAYRAPETYAN |
| HVAC-Rough | 2/12/2026 | Approved | MICHAEL CORTEZ |
| PLUMBING-Rough | 2/12/2026 | Approved | MICHAEL CORTEZ |
| Insulation | 2/20/2026 | Partial Approval | GAREN HAYRAPETYAN |
| Wood Frame | 2/20/2026 | Partial Approval | GAREN HAYRAPETYAN |
| Deputy Wood Construction | 2/25/2026 | Conditional Approval | RAUL OLAGI |
| BUILDING-Rough-Frame | 3/2/2026 | Corrections Issued | JOSE AVILA |
| Insulation | 3/2/2026 | Partial Approval | JOSE AVILA |
| Interior/Exterior Lathing | 3/2/2026 | Approved | JOSE AVILA |
| Shower Pan | 3/2/2026 | Approved | JOSE AVILA |
| Drywall Nailing | 3/5/2026 | Approved | MICHEL ABAJAN |
| Interior/Exterior Lathing | 3/5/2026 | Approved | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 4/17/2026 | Approved | JOSE AVILA |
| ELECTRICAL-Final | 4/17/2026 | Approved | JOSE AVILA |
| Green Building Final | 4/17/2026 | Approved | JOSE AVILA |
| Green Building Rough | 4/17/2026 | Approved | JOSE AVILA |
| HVAC-Final | 4/17/2026 | Approved | JOSE AVILA |
| PLUMBING-Final | 4/17/2026 | Approved | JOSE AVILA |
| SGSOV-Seismic Gas S/O Valve | 4/17/2026 | SGSOV Approved | JOSE AVILA |
| Smoke Detectors | 4/17/2026 | Approved | JOSE AVILA |
| Final | 5/29/2026 | OK to Issue CofO | MICHAEL CORTEZ |