369 N KILKEA DR 90048
Certificate Information: 369 N KILKEA DR 90048
- Application / Permit
- 25016-10000-28935
- Plan Check / Job No.
- B25LA40486
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan. Convert (E) Detached Garage to an Accessory Dwelling Unit per GC 66323(a)(1). All work per WFPP
- Permit Issued
- Issued on 6/12/2026
- Issuing Office
- Current Status
- Issued on 6/12/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 10/10/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 10/16/2025 | AMY GUEVARRA |
| Corrections Issued | 10/19/2025 | AMY GUEVARRA |
| Applicant returned to address corrections | 12/2/2025 | AMY GUEVARRA |
| Applicant returned to address corrections | 1/26/2026 | AMY GUEVARRA |
| Applicant returned to address corrections | 3/9/2026 | AMY GUEVARRA |
| Applicant returned to address corrections | 3/17/2026 | AMY GUEVARRA |
| Applicant returned to address corrections | 4/23/2026 | DAVID CASTILLO |
| Plan Check Approved | 5/1/2026 | DAVID CASTILLO |
| Issued | 6/12/2026 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 12/19/2025 | ROSE STEIN-WENDT |
| Roof/Waste drainage to street | Cleared | 12/19/2025 | ROSE STEIN-WENDT |
| Sewer availability | Cleared | 12/19/2025 | ROSE STEIN-WENDT |
| Eng Process Fee Ord 176,300 | Cleared | 12/23/2025 | ROSE STEIN-WENDT |
| Construction within easement | Cleared | 4/28/2026 | RIDWAN HARDY |
Contact Information
| Architect | Benjamin,, James Antony; Lic. No.: NA28983 | , |
| Contractor | Zumwalt Development Inc; Lic. No.: 1097342-B | , |
Inspector Information
| JOSE MACIAS, (213) 202-3125 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 6/25/2026 | Partial Approval | JOSH MEISTER |
| Wood Frame | 6/26/2026 | Approved | JOSH MEISTER |
| Floor/Roof Diaphrgm/Shear Wall | 6/30/2026 | Partial Approval | JOSH MEISTER |
| Green Building Rough | 6/30/2026 | Not Ready for Inspection | JOSH MEISTER |
| METHANE-Rough | 6/30/2026 | Approved | JOSH MEISTER |