2410 S 8TH AVE 90018
Certificate Information: 2410 S 8TH AVE 90018
- Application / Permit
- 25016-10000-28818
- Plan Check / Job No.
- B25LA40343
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ePlan: Convert portion of (E) storage at second floor to bathroom (87 sq. ft) in (e) 2-story SFD COMPLY WITH DEPARTMENT ORDER effective date 07/05/2025. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE
- Permit Issued
- Issued on 4/17/2026
- Issuing Office
- Current Status
- Permit Finaled on 6/1/2026
Permit Application Status History
| Submitted | 10/8/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 10/10/2025 | DANIEL SMILEY |
| Corrections Issued | 10/12/2025 | DANIEL SMILEY |
| Applicant returned to address corrections | 11/13/2025 | KELVIN CHUONG |
| Applicant returned to address corrections | 12/2/2025 | KELVIN CHUONG |
| Applicant returned to address corrections | 12/11/2025 | KELVIN CHUONG |
| Applicant returned to address corrections | 12/31/2025 | KELVIN CHUONG |
| Applicant returned to address corrections | 1/6/2026 | KELVIN CHUONG |
| Plan Check Approved | 4/2/2026 | KELVIN CHUONG |
| Issued | 4/17/2026 | APPLICANT |
| Permit Finaled | 5/29/2026 | LUIS CORRAL |
Permit Application Clearance Information
| Sewer availability | Cleared | 11/6/2025 | DAVID LOPEZ |
| Eng Process Fee Ord 176,300 | Cleared | 11/12/2025 | DAVID LOPEZ |
| HPOZ | Cleared | 3/30/2026 | DEBORAH MCGILL |
Contact Information
| Contractor | Dreamers General Construction Inc; Lic. No.: 1025578-B | , |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| ELECTRICAL-Rough | 4/23/2026 | Approved | LUIS CORRAL |
| PLUMBING-Rough | 4/23/2026 | Approved | LUIS CORRAL |
| HVAC-Final | 5/4/2026 | Approved | LUIS CORRAL |
| PLUMBING-Final | 5/4/2026 | Approved | LUIS CORRAL |
| ELECTRICAL-Final | 5/21/2026 | No Access for Inspection | LUIS CORRAL |
| Final | 5/21/2026 | No Access for Inspection | LUIS CORRAL |
| Green Building Final | 5/21/2026 | No Access for Inspection | LUIS CORRAL |
| BUILDING-Rough-Frame | 5/22/2026 | Approved | LUIS CORRAL |
| ELECTRICAL-Final | 5/22/2026 | Approved | LUIS CORRAL |
| HVAC-Final | 5/22/2026 | Approved | LUIS CORRAL |
| Smoke Detectors | 5/22/2026 | Approved | LUIS CORRAL |
| Final | 5/29/2026 | Permit Finaled | LUIS CORRAL |
| Green Building Final | 5/29/2026 | Approved | LUIS CORRAL |