13068 W GARBER ST 91331

Certificate Information: 13068 W GARBER ST 91331

Application / Permit
25016-10000-28789
Plan Check / Job No.
B25VN27278
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
EPLAN CONVERT (E) DETACHED GARAGE TO ADU PER LAMC 12.22 A.33 (c) and (e). ALL WORK PER WFPP.
Permit Issued
Issued on 11/19/2025
Issuing Office
Current Status
CofO Issued on 4/22/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/19/2025 APPLICANT
Assigned to Plan Check Engineer 9/24/2025 SAMUEL GONZALEZ
Corrections Issued 9/25/2025 SAMUEL GONZALEZ
Plan Check Approved 11/11/2025 SAMUEL GONZALEZ
Issued 11/19/2025 APPLICANT
CofO in Progress 3/3/2026 MICHEL ABAJAN
Permit Finaled 4/22/2026 RUBEN SALAS
CofO Issued 4/22/2026 RUBEN SALAS
Permit Finaled 4/22/2026 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 10/14/2025 BIAINA HARITUNIAN
Sewer availability Cleared 10/14/2025 BIAINA HARITUNIAN
Eng Process Fee Ord 176,300 Cleared 10/15/2025 BIAINA HARITUNIAN

Contact Information

Contractor Ultimate Green Construction Inc; Lic. No.: 1023605-B       ,

Inspector Information

MICHEL ABAJAN, (818) 374-9932 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 12/3/2025 Conditional Approval JOAQUIN GREENOUGH
Footing/Foundation/Slab 12/3/2025 Approved MICHEL ABAJAN
PLUMBING-Rough 12/3/2025 Partial Approval MICHEL ABAJAN
BUILDING-Rough-Frame 12/22/2025 Approved MICHEL ABAJAN
ELECTRICAL-Rough 12/22/2025 Approved MICHEL ABAJAN
Green Building Rough 12/22/2025 Approved MICHEL ABAJAN
HVAC-Rough 12/22/2025 Approved MICHEL ABAJAN
METHANE-Rough 12/22/2025 Approved MICHEL ABAJAN
PLUMBING-Rough 12/22/2025 Approved MICHEL ABAJAN
Underground Mechanical 12/22/2025 Approved MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 12/23/2025 Partial Approval MICHEL ABAJAN
Insulation 1/8/2026 Approved MICHEL ABAJAN
Drywall Nailing 1/12/2026 Approved MICHEL ABAJAN
Interior/Exterior Lathing 1/12/2026 Approved MICHEL ABAJAN
Shower Pan 1/12/2026 Approved MICHEL ABAJAN
ELECTRICAL-Final 3/2/2026 Approved MICHEL ABAJAN
Final 3/2/2026 OK to Issue CofO MICHEL ABAJAN
Green Building Final 3/2/2026 Approved MICHEL ABAJAN
HVAC-Final 3/2/2026 Approved MICHEL ABAJAN
PLUMBING-Final 3/2/2026 Approved MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 3/2/2026 SGSOV Approved MICHEL ABAJAN
Smoke Detectors 3/2/2026 Approved MICHEL ABAJAN