637-639 W 4TH ST 90731
Certificate Information: 637-639 W 4TH ST 90731
- Application / Permit
- 25016-10000-28564
- Plan Check / Job No.
- B25LA39948
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN. CONVERT PORTION OF GARAGE AND STORAGE TO ATTACHED ADU FOR EXISTING DUPLEX PER GC 66323(a)(3)
- Permit Issued
- Issued on 3/1/2026
- Issuing Office
- Current Status
- Issued on 3/1/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 9/23/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 9/26/2025 | ADAM HEGAZI |
| Corrections Issued | 9/29/2025 | ADAM HEGAZI |
| Applicant returned to address corrections | 2/5/2026 | ADAM HEGAZI |
| Applicant returned to address corrections | 2/24/2026 | ADAM HEGAZI |
| Plan Check Approved | 3/1/2026 | ADAM HEGAZI |
| Issued | 3/1/2026 | APPLICANT |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 10/23/2025 | LANNY MERRICK |
| Sewer availability | Cleared | 10/30/2025 | DERRICK MAGEE |
| Community Plan Implem. Overlay | Cleared | 1/5/2026 | NORALI MARTINEZ |
| Tenant Habitability Plan | Cleared | 1/12/2026 | ARIC DEFUSCO |
| Eng Process Fee Ord 176,300 | Cleared | 2/11/2026 | DERRICK MAGEE |
| Historic Resource Verification | Cleared | 2/17/2026 | LAMBERT GIESSINGER |
| Redevelopment Project Area | Cleared | 2/17/2026 | YASMINE BASHIRI |
| Address approval | Cleared | 2/26/2026 | DERRICK MAGEE |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Xi,, Wang; Lic. No.: NA85148 | , |
Inspector Information
| JOSEPH MCGARRY, (310) 732-4559 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 4/20/2026 | Partial Approval | JOSEPH MCGARRY |
| Excavation/Setback/Form/Re-Bar | 4/21/2026 | Conditional Approval | JOSEPH MCGARRY |
| Pre-Inspection | 4/21/2026 | Approved | JOSEPH MCGARRY |
| Deputy Drilled-In Anchors | 4/28/2026 | Conditional Approval | JOSEPH MCGARRY |
| Excavation/Setback/Form/Re-Bar | 5/1/2026 | Partial Approval | JOSEPH MCGARRY |
| PLUMBING-Rough | 5/12/2026 | Partial Approval | JOSEPH MCGARRY |
| Sewer | 5/12/2026 | Approved | JOSEPH MCGARRY |
| Deputy Steel/Welding | 5/13/2026 | Approved | JOSEPH MCGARRY |
| Excavation/Setback/Form/Re-Bar | 5/18/2026 | Approved | JOSEPH MCGARRY |
| Deputy Reinf. Concrete | 5/21/2026 | Approved | JOSEPH MCGARRY |
| Wood Frame | 6/9/2026 | Not Ready for Inspection | JOSEPH MCGARRY |
| ELECTRICAL-Rough | 6/29/2026 | Approved | JOSEPH MCGARRY |
| HVAC-Rough | 6/29/2026 | Partial Approval | JOSEPH MCGARRY |
| PLUMBING-Rough | 6/29/2026 | Corrections Issued | JOSEPH MCGARRY |
| Wood Frame | 6/29/2026 | Partial Approval | JOSEPH MCGARRY |
| Insulation | 7/24/2026 | Approved | ANSON MAGLASANG |
| PLUMBING-Rough | 7/24/2026 | Approved | ANSON MAGLASANG |