3010 N GLENMANOR PL 90039

Certificate Information: 3010 N GLENMANOR PL 90039

Application / Permit
25016-10000-28257
Plan Check / Job No.
B25LA39435
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
EPLAN ENCLOSE FRONT COVERED PORCH TO BE PART OF SFD. LEGALIZE REAR ADDITION AND NEW LANDING
Permit Issued
Issued on 12/2/2025
Issuing Office
Current Status
CofO Issued on 4/7/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/29/2025 APPLICANT
Assigned to Plan Check Engineer 10/1/2025 JOHNPAUL ISIP
Corrections Issued 10/2/2025 JOHNPAUL ISIP
Applicant returned to address corrections 10/30/2025 JOHNPAUL ISIP
Plan Check Approved 11/25/2025 JOHNPAUL ISIP
Issued 12/2/2025 APPLICANT
CofO in Progress 4/1/2026 NICHOLAS LOPEZ
Permit Finaled 4/7/2026 DEROLD HAUFF
CofO Issued 4/7/2026 DEROLD HAUFF
Permit Finaled 4/7/2026 DEROLD HAUFF

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 10/20/2025 WALLIE JONG
Roof/Waste drainage to street Cleared 10/20/2025 WALLIE JONG

Contact Information

Architect White,, Ellesse Akie; Lic. No.: C40162 942 W PASEO DEL MAR      SAN PEDRO, CA 90731
Contractor Owner-Builder       ,
Engineer Wu,, Shu; Lic. No.: C90391 136 LOST HILLS      IRVINE, CA 92618

Inspector Information

NICHOLAS LOPEZ, (213) 202-3224 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 12/8/2025 Partial Inspection NICHOLAS LOPEZ
Footing/Foundation/Slab 12/18/2025 Approved NICHOLAS LOPEZ
BUILDING-Rough-Frame 1/5/2026 Approved NICHOLAS LOPEZ
ELECTRICAL-Rough 1/5/2026 Approved NICHOLAS LOPEZ
Floor/Roof Diaphrgm/Shear Wall 1/5/2026 Approved NICHOLAS LOPEZ
Green Building Rough 1/5/2026 Approved NICHOLAS LOPEZ
Interior/Exterior Lathing 1/5/2026 Approved NICHOLAS LOPEZ
Insulation 1/7/2026 Approved NICHOLAS LOPEZ
Drywall Nailing 1/8/2026 Approved NICHOLAS LOPEZ
Final 3/23/2026 Corrections Issued NICHOLAS LOPEZ
Green Building Final 3/23/2026 Approved NICHOLAS LOPEZ
SGSOV-Seismic Gas S/O Valve 3/23/2026 SGSOV Not Ready NICHOLAS LOPEZ
Smoke Detectors 3/23/2026 Corrections Issued NICHOLAS LOPEZ
Final 3/31/2026 OK to Issue CofO NICHOLAS LOPEZ
SGSOV-Seismic Gas S/O Valve 3/31/2026 SGSOV Approved NICHOLAS LOPEZ
Smoke Detectors 3/31/2026 Approved NICHOLAS LOPEZ