2342 S CLEMENT AVE 90291
Certificate Information: 2342 S CLEMENT AVE 90291
- Application / Permit
- 25016-10000-27696
- Plan Check / Job No.
- B25LA38611
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- EPLAN: INTERIOR REMODEL TO 1ST FLOOR OF (E) SFD & REPLACE (1) WINDOW. ALL WORK DONE PER ENGINEERING
- Permit Issued
- Issued on 1/19/2026
- Issuing Office
- Current Status
- Issued on 1/19/2026
Permit Application Status History
| Submitted | 9/25/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 9/29/2025 | GURUNATH NESARAJAH |
| Corrections Issued | 9/30/2025 | GURUNATH NESARAJAH |
| Applicant returned to address corrections | 12/23/2025 | GURUNATH NESARAJAH |
| Plan Check Approved | 1/15/2026 | GURUNATH NESARAJAH |
| Issued | 1/19/2026 | APPLICANT |
Permit Application Clearance Information
| Sewer availability | Cleared | 10/2/2025 | JEFF LOREDO |
| Miscellaneous | Cleared | 10/3/2025 | RUBEN VASQUEZ |
| Miscellaneous | Cleared | 10/3/2025 | RUBEN VASQUEZ |
| Miscellaneous | Cleared | 10/3/2025 | RUBEN VASQUEZ |
| Miscellaneous | Cleared | 10/3/2025 | RUBEN VASQUEZ |
| Miscellaneous | Cleared | 10/3/2025 | RUBEN VASQUEZ |
| Miscellaneous | Cleared | 10/3/2025 | RUBEN VASQUEZ |
| Miscellaneous | Cleared | 10/3/2025 | RUBEN VASQUEZ |
| ZA Case | Cleared | 10/3/2025 | RUBEN VASQUEZ |
| ZA Case | Cleared | 10/3/2025 | RUBEN VASQUEZ |
| Eng Process Fee Ord 176,300 | Cleared | 10/6/2025 | JEFF LOREDO |
| Specific Plan | Cleared | 12/1/2025 | LUIS LOPEZ |
| Coastal Zone | Cleared | 1/13/2026 | DORIAN AGUILAR |
Contact Information
| Contractor | Sb Construction & Remodeling Inc; Lic. No.: 1061509-B | , |
Inspector Information
| RUBEN RIVAS, (310) 914-3981 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 2/5/2026 | Corrections Issued | RUBEN RIVAS |
| Footing/Foundation/Slab | 2/12/2026 | Corrections Issued | RUBEN RIVAS |
| Footing/Foundation/Slab | 2/18/2026 | Approved | RUBEN RIVAS |
| BUILDING-Rough-Frame | 3/3/2026 | Not Ready for Inspection | RUBEN RIVAS |
| Floor/Roof Diaphrgm/Shear Wall | 3/10/2026 | Partial Approval | RUBEN RIVAS |
| Shower Pan | 3/10/2026 | Approved | RUBEN RIVAS |
| Drywall Nailing | 3/12/2026 | Approved | TEMISTOCLES CAAL |
| Special/Order Compliance | 3/12/2026 | Partial Inspection | HERBERT GIRON |
| Interior/Exterior Lathing | 3/16/2026 | Partial Approval | MICHAEL ALLEN |
| Interior/Exterior Lathing | 3/24/2026 | Approved | RUBEN RIVAS |