583 N RADCLIFFE AVE 90272
Certificate Information: 583 N RADCLIFFE AVE 90272
- Application / Permit
- 25016-10000-27327
- Plan Check / Job No.
- B25LA38008
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 2025 WILDFIRE REBUILD, SINGLE FAMILY DWELLING WITH 1 LEVEL BASEMENT, AND ATTACHED 2-CAR GARAGE, 2-STORY. NFPA 13D SPRINKLERS THROUGHOUT EO1. SOLAR INSTALLATION EXEMPT PER GOVERNOR'S ORDER N-29-25.
- Permit Issued
- Issued on 4/16/2026
- Issuing Office
- Current Status
- Issued on 4/16/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 9/15/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 9/18/2025 | VIVIAN LAO |
| Corrections Issued | 9/24/2025 | VIVIAN LAO |
| Quality Review Completed | 9/24/2025 | JOHN FRANCIA |
| Applicant returned to address corrections | 11/18/2025 | VIVIAN LAO |
| Applicant returned to address corrections | 12/19/2025 | VIVIAN LAO |
| Applicant returned to address corrections | 3/10/2026 | VIVIAN LAO |
| Plan Check Approved | 3/31/2026 | VIVIAN LAO |
| Issued | 4/16/2026 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 9/29/2025 | MICHAEL BROWN |
| Eng Process Fee Ord 176,300 | Cleared | 9/29/2025 | MICHAEL BROWN |
| Hydrant and Access approval | Cleared | 9/29/2025 | PATRICK PEREZ |
| Roof/Waste drainage to street | Cleared | 9/29/2025 | MICHAEL BROWN |
| Sewer availability | Cleared | 9/29/2025 | MICHAEL BROWN |
Contact Information
| Contractor | Rocon Sunset Development Inc; Lic. No.: 1050364-B | , |
| Engineer | Shubeck,, Christopher Robert; Lic. No.: C66775 | 23705 VANOWEN ST 101 WEST HILLS, CA 91307 |
| Engineer | Vasquez,, Luis Fernando; Lic. No.: NA56232 | , |
Inspector Information
| STEPHANIE SWANSON, (213) 469-1255 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 4/17/2026 | Corrections Issued | STEPHANIE SWANSON |
| Excavation/Setback/Form/Re-Bar | 4/21/2026 | Partial Approval | STEPHANIE SWANSON |
| Deputy Shotcrete | 4/22/2026 | Conditional Approval | JUAN VALENZUELA |
| Underground Mechanical | 5/8/2026 | Partial Inspection | STEPHANIE SWANSON |