830 S MANNING AVE 90024
Certificate Information: 830 S MANNING AVE 90024
- Application / Permit
- 25016-10000-26664
- Plan Check / Job No.
- B25LA37010
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ePlan: MAJOR REMODEL AND ADDITION TO EXISTING 2-STORY SINGLE FAMILY RESIDENCE WITH ATTACHED CARPORT FIRE SPRINKLER THROUGHOUT
- Permit Issued
- Issued on 10/31/2025
- Issuing Office
- Current Status
- Issued on 10/31/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 9/3/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 9/4/2025 | KHEDER ALRAZAA |
| Corrections Issued | 9/6/2025 | KHEDER ALRAZAA |
| Quality Review Completed | 9/10/2025 | GARO TELMI |
| Assigned to Zoning Architect | 9/11/2025 | CAMERON JONES |
| Applicant returned to address corrections | 10/15/2025 | KHEDER ALRAZAA |
| Plan Check Approved | 10/31/2025 | KHEDER ALRAZAA |
| Issued | 10/31/2025 | APPLICANT |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 9/16/2025 | LANNY MERRICK |
| Roof/Waste drainage to street | Cleared | 9/20/2025 | JESUS CISNEROS |
| Eng Process Fee Ord 176,300 | Cleared | 9/23/2025 | JESUS CISNEROS |
| Sewer availability | Cleared | 9/23/2025 | JESUS CISNEROS |
| ZA Case | Cleared | 10/17/2025 | RUBEN VASQUEZ |
| ZA Case | Cleared | 10/17/2025 | RUBEN VASQUEZ |
| Zoning Plan Check | Cleared | 10/21/2025 | CAMERON JONES |
Contact Information
| Architect | Grant,, Thurman; Lic. No.: NA30285 | , |
| Contractor | David Diaz; Lic. No.: 467015-B | , |
| Contractor | Lcd Developement; Lic. No.: 467015-B | , |
| Engineer | Kim,, Taewon; Lic. No.: C80632 | 28531 PALOS VERDES DR EAST RANCHO PALOS VERDES, CA 90275 |
Inspector Information
| DAVID SCANTLIN, (310) 914-3863 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 11/17/2025 | Not Ready for Inspection | CARLOS MATAMOROS |
| Deputy Drilled-In Anchors | 11/18/2025 | Conditional Approval | ANDREW NAVE |
| Footing/Foundation/Slab | 11/19/2025 | Not Ready for Inspection | DANIEL VERA |
| Footing/Foundation/Slab | 11/20/2025 | Approved | DANIEL VERA |
| Deputy Drilled-In Anchors | 12/17/2025 | Conditional Approval | ANDREW NAVE |
| Deputy Wood Construction | 4/7/2026 | Conditional Approval | ANDREW NAVE |
| Footing/Foundation/Slab | 4/14/2026 | Approved | RYAN SALAZAR |