3242 S CASTLE HEIGHTS AVE 90034

Certificate Information: 3242 S CASTLE HEIGHTS AVE 90034

Application / Permit
25016-10000-26541
Plan Check / Job No.
B25LA36834
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePlan: INTERIOR REMODEL TO (E) SFD WHICH INCLUDES CONVERTING BATHROOM INTO LAUNDRY ROOM, REMODELING EXISTING MAIN BATH, AND CREATING ADDITIONAL BATH.
Permit Issued
Issued on 11/4/2025
Issuing Office
Current Status
Permit Finaled on 3/2/2026

Permit Application Status History

Submitted 9/2/2025 APPLICANT
Assigned to Plan Check Engineer 9/5/2025 ISIS ARGUETA
Corrections Issued 9/8/2025 ISIS ARGUETA
Plan Check Approved 9/24/2025 ISIS ARGUETA
Issued 11/4/2025 APPLICANT
Permit Finaled 2/27/2026 ASHLEY THOMPSON

Permit Application Clearance Information

No Data Available.

Contact Information

Contractor Qastic Inc; Lic. No.: 1086753-B 9889 SANTA MONICA BLVD STE 205      BEVERLY HILLS, CA 90212
Engineer Esmaili,, Omid; Lic. No.: NA87027       ,

Inspector Information

ASHLEY THOMPSON, (310) 914-3897 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 11/26/2025 Corrections Issued ASHLEY THOMPSON
Footing/Foundation/Slab 12/8/2025 Approved DANIEL VERA
ELECTRICAL-Rough 12/22/2025 Not Ready for Inspection ASHLEY THOMPSON
Floor/Roof Diaphrgm/Shear Wall 12/22/2025 Corrections Issued ASHLEY THOMPSON
PLUMBING-Rough 12/22/2025 Corrections Issued ASHLEY THOMPSON
ELECTRICAL-Rough 12/30/2025 Not Ready for Inspection ASHLEY THOMPSON
PLUMBING-Rough 12/30/2025 Not Ready for Inspection ASHLEY THOMPSON
Wood Frame 12/30/2025 Partial Approval ASHLEY THOMPSON
ELECTRICAL-Rough 1/9/2026 Not Ready for Inspection ASHLEY THOMPSON
HVAC-Rough 1/9/2026 Corrections Issued ASHLEY THOMPSON
PLUMBING-Rough 1/9/2026 Approved ASHLEY THOMPSON
Special/Order Compliance 1/9/2026 Partial Inspection DAKOTA LOW
Wood Frame 1/9/2026 Not Ready for Inspection ASHLEY THOMPSON
BUILDING-Rough-Frame 1/14/2026 Partial Approval ARAM AVEDISIAN
ELECTRICAL-Rough 1/14/2026 Approved ARAM AVEDISIAN
HVAC-Rough 1/14/2026 Corrections Issued ARAM AVEDISIAN
HVAC-Rough 1/16/2026 Approved ASHLEY THOMPSON
Insulation 1/16/2026 Approved ASHLEY THOMPSON
Wood Frame 1/16/2026 Approved ASHLEY THOMPSON
Drywall Nailing 1/26/2026 Approved ARAM AVEDISIAN
Shower Pan 1/26/2026 Corrections Issued ARAM AVEDISIAN
Shower Pan 1/30/2026 Corrections Issued ASHLEY THOMPSON
Interior/Exterior Lathing 2/4/2026 Approved DANIEL VERA
Shower Pan 2/9/2026 Approved RYAN SALAZAR
ELECTRICAL-Final 2/20/2026 Corrections Issued ASHLEY THOMPSON
Final 2/20/2026 Corrections Issued ASHLEY THOMPSON
HVAC-Final 2/20/2026 Corrections Issued ASHLEY THOMPSON
PLUMBING-Final 2/20/2026 Corrections Issued ASHLEY THOMPSON
SGSOV-Seismic Gas S/O Valve 2/20/2026 SGSOV Not Ready ASHLEY THOMPSON
Smoke Detectors 2/20/2026 Corrections Issued ASHLEY THOMPSON
Final 2/27/2026 Permit Finaled ASHLEY THOMPSON
SGSOV-Seismic Gas S/O Valve 2/27/2026 SGSOV Approved ASHLEY THOMPSON
Smoke Detectors 2/27/2026 Approved ASHLEY THOMPSON