9212 S VAN NESS AVE 90047
Certificate Information: 9212 S VAN NESS AVE 90047
- Application / Permit
- 25016-10000-25995
- Plan Check / Job No.
- B25LA35984
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) DETACHED GARAGE TO NEW DETACHED ACCESSORY DWELLING UNIT PER GC 66323(a)(1).
- Permit Issued
- Issued on 1/27/2026
- Issuing Office
- Current Status
- Issued on 1/27/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 8/27/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 9/2/2025 | MIROOSH KHACHATOORIAN |
| Corrections Issued | 9/3/2025 | MIROOSH KHACHATOORIAN |
| Applicant returned to address corrections | 10/7/2025 | SARKIS HARABEDIAN |
| Applicant returned to address corrections | 10/20/2025 | SARKIS HARABEDIAN |
| Applicant returned to address corrections | 11/7/2025 | SARKIS HARABEDIAN |
| Applicant returned to address corrections | 11/10/2025 | GIOVANNY CHAVEZ |
| Plan Check Approved | 1/14/2026 | GIOVANNY CHAVEZ |
| Issued | 1/27/2026 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 9/18/2025 | SAFA JAVANMARDI |
| Sewer availability | Cleared | 9/18/2025 | SAFA JAVANMARDI |
| Eng Process Fee Ord 176,300 | Cleared | 9/23/2025 | SAFA JAVANMARDI |
| Miscellaneous | Cleared | 12/23/2025 | ALBERT TAM |
Contact Information
| Architect | Treiber,, Joshua; Lic. No.: C39017 | 4130 BERENICE AVE LOS ANGELES, CA 90031 |
| Contractor | Owner-Builder | , |
| Engineer | Melchor,, Oscar Elias; Lic. No.: C76828 | 21731 VENTURA BLVD SUITE 110 WOODLAND HILLS, CA 91364 |
Inspector Information
| SALVADOR MARTINEZ, (213) 202-3479 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 2/9/2026 | Corrections Issued | SALVADOR MARTINEZ |
| PLUMBING-Rough | 2/9/2026 | Corrections Issued | SALVADOR MARTINEZ |
| Sewer | 2/11/2026 | Approved | ALEX COLIN |
| Underground Mechanical | 2/11/2026 | Partial Approval | ALEX COLIN |
| Footing/Foundation/Slab | 2/19/2026 | Corrections Issued | SALVADOR MARTINEZ |
| Footing/Foundation/Slab | 2/24/2026 | Corrections Issued | SALVADOR MARTINEZ |
| Deputy Drilled-In Anchors | 3/25/2026 | Partial Approval | SALVADOR MARTINEZ |
| Footing/Foundation/Slab | 3/26/2026 | Conditional Approval | SALVADOR MARTINEZ |
| Floor/Roof Diaphrgm/Shear Wall | 4/3/2026 | Approved | MICHAEL LEWIS |
| Insulation | 4/3/2026 | Partial Approval | MICHAEL LEWIS |
| PLUMBING-Rough | 4/3/2026 | Approved | MICHAEL LEWIS |
| HVAC-Rough | 4/7/2026 | Corrections Issued | SALVADOR MARTINEZ |
| Interior/Exterior Lathing | 4/7/2026 | Corrections Issued | SALVADOR MARTINEZ |
| Shower Pan | 4/7/2026 | Approved | SALVADOR MARTINEZ |
| HVAC-Rough | 4/10/2026 | Approved | SALVADOR MARTINEZ |
| Interior/Exterior Lathing | 4/10/2026 | Approved | SALVADOR MARTINEZ |
| BUILDING-Rough-Frame | 4/14/2026 | Corrections Issued | SALVADOR MARTINEZ |
| ELECTRICAL-Rough | 4/14/2026 | Corrections Issued | SALVADOR MARTINEZ |
| Green Building Rough | 4/14/2026 | Approved | SALVADOR MARTINEZ |
| METHANE-Rough | 4/14/2026 | Approved | SALVADOR MARTINEZ |
| BUILDING-Rough-Frame | 4/17/2026 | Corrections Issued | SALVADOR MARTINEZ |
| ELECTRICAL-Rough | 4/17/2026 | Corrections Issued | SALVADOR MARTINEZ |
| BUILDING-Rough-Frame | 5/11/2026 | Corrections Issued | WILLIAM SIERRA |
| BUILDING-Rough-Frame | 5/13/2026 | Conditional Approval | SALVADOR MARTINEZ |
| ELECTRICAL-Rough | 5/13/2026 | Conditional Approval | SALVADOR MARTINEZ |
| Insulation | 5/13/2026 | Approved | SALVADOR MARTINEZ |
| Drywall Nailing | 5/18/2026 | Approved | STUART CHAPMAN |