3012 N GLENMANOR PL 90039

Certificate Information: 3012 N GLENMANOR PL 90039

Application / Permit
25016-10000-25889
Plan Check / Job No.
B25LA35765
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
eplan Convert (E) detached Garage into State ADU per GCS 66323(a)(1)
Permit Issued
Issued on 10/20/2025
Issuing Office
Current Status
CofO Issued on 4/7/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/26/2025 APPLICANT
Assigned to Plan Check Engineer 8/29/2025 ZAW HAN
Corrections Issued 8/29/2025 ZAW HAN
Applicant returned to address corrections 9/20/2025 ZAW HAN
Plan Check Approved 10/2/2025 MINA HABILI
Issued 10/20/2025 APPLICANT
CofO in Progress 4/3/2026 NICHOLAS LOPEZ
Permit Finaled 4/7/2026 DEROLD HAUFF
CofO Issued 4/7/2026 DEROLD HAUFF
Permit Finaled 4/7/2026 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 9/10/2025 LEE GUILBEAUX
Roof/Waste drainage to street Cleared 9/10/2025 LEE GUILBEAUX
Sewer availability Cleared 9/10/2025 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 9/10/2025 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 9/12/2025 LEE GUILBEAUX
ZI Cleared 9/24/2025 DAVID URITA

Contact Information

Contractor Cahla Construction Group Corp; Lic. No.: 1122701-B       ,
Engineer Wu,, Shu; Lic. No.: C90391 136 LOST HILLS      IRVINE, CA 92618

Inspector Information

NICHOLAS LOPEZ, (213) 202-3224 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 11/4/2025 Conditional Approval NICHOLAS LOPEZ
PLUMBING-Rough 12/1/2025 Partial Approval NICHOLAS LOPEZ
Footing/Foundation/Slab 12/8/2025 Approved NICHOLAS LOPEZ
Sewer 12/16/2025 Approved NICHOLAS LOPEZ
ELECTRICAL-Rough 12/19/2025 Corrections Issued NICHOLAS LOPEZ
HVAC-Rough 12/19/2025 Corrections Issued NICHOLAS LOPEZ
PLUMBING-Rough 12/19/2025 Not Ready for Inspection NICHOLAS LOPEZ
Underground Mechanical 12/19/2025 Corrections Issued NICHOLAS LOPEZ
Rough-Elec/Plmb/HVAC 12/29/2025 Approved NICHOLAS LOPEZ
Underground Mechanical 12/29/2025 Approved NICHOLAS LOPEZ
BUILDING-Rough-Frame 1/5/2026 Corrections Issued NICHOLAS LOPEZ
Green Building Rough 1/5/2026 Approved NICHOLAS LOPEZ
Interior/Exterior Lathing 1/5/2026 Partial Approval NICHOLAS LOPEZ
Insulation 1/6/2026 Not Ready for Inspection NICHOLAS LOPEZ
BUILDING-Rough-Frame 1/7/2026 Approved NICHOLAS LOPEZ
Insulation 1/7/2026 Conditional Approval NICHOLAS LOPEZ
Drywall Nailing 1/8/2026 Not Ready for Inspection NICHOLAS LOPEZ
Floor/Roof Diaphrgm/Shear Wall 1/8/2026 Corrections Issued NICHOLAS LOPEZ
Interior/Exterior Lathing 1/8/2026 Approved NICHOLAS LOPEZ
Shower Pan 1/8/2026 Approved NICHOLAS LOPEZ
Deputy Wood Construction 1/9/2026 Conditional Approval NICHOLAS LOPEZ
Drywall Nailing 1/13/2026 Approved ALIZAH MAYAGOITIA
Final 3/23/2026 Corrections Issued NICHOLAS LOPEZ
Green Building Final 3/23/2026 Not Ready for Inspection NICHOLAS LOPEZ
SGSOV-Seismic Gas S/O Valve 3/23/2026 SGSOV Not Ready NICHOLAS LOPEZ
Smoke Detectors 3/23/2026 Approved NICHOLAS LOPEZ
Final 3/31/2026 Corrections Issued NICHOLAS LOPEZ
Green Building Final 3/31/2026 Not Ready for Inspection NICHOLAS LOPEZ
SGSOV-Seismic Gas S/O Valve 3/31/2026 SGSOV Approved NICHOLAS LOPEZ
Final 4/3/2026 OK to Issue CofO NICHOLAS LOPEZ
Green Building Final 4/3/2026 Approved NICHOLAS LOPEZ