1004 N BUNDY DR 90049

Certificate Information: 1004 N BUNDY DR 90049

Application / Permit
25016-10000-25601
Plan Check / Job No.
B25LA35323
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
eplan Interior remodel of an existing 2-story single-family dwelling. Replacement of select doors and (1) window. No change in square footage.
Permit Issued
Issued on 9/26/2025
Issuing Office
Current Status
Issued on 9/26/2025

Permit Application Status History

Submitted 8/25/2025 APPLICANT
Assigned to Plan Check Engineer 8/27/2025 NEHEMIAS RAMOS
Corrections Issued 8/28/2025 NEHEMIAS RAMOS
Applicant returned to address corrections 9/13/2025 NEHEMIAS RAMOS
Applicant returned to address corrections 9/23/2025 NEHEMIAS RAMOS
Plan Check Approved 9/24/2025 NEHEMIAS RAMOS
Issued 9/26/2025 APPLICANT

Permit Application Clearance Information

Grading Pre-Inspection Cleared 9/9/2025 LANNY MERRICK

Contact Information

Contractor Mod Design Build; Lic. No.: 1031321-B       ,
Engineer Basso,, Alexandre; Lic. No.: NA77670       ,

Inspector Information

EVAN COOPER, (310) 914-3861 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 9/30/2025 Corrections Issued CARLOS MATAMOROS
Footing/Foundation/Slab 9/30/2025 Not Ready for Inspection CARLOS MATAMOROS
Excavation/Setback/Form/Re-Bar 10/1/2025 Approved CARLOS MATAMOROS
Footing/Foundation/Slab 10/1/2025 Approved CARLOS MATAMOROS
PLUMBING-Rough 10/14/2025 Corrections Issued CARLOS MATAMOROS
Gas Test 10/17/2025 Approved CARLOS MATAMOROS
PLUMBING-Rough 10/17/2025 Approved CARLOS MATAMOROS
Shower Pan 10/22/2025 Approved CARLOS MATAMOROS
BUILDING-Rough-Frame 11/21/2025 Not Ready for Inspection DANIEL VERA
HVAC-Rough 11/21/2025 Not Ready for Inspection DANIEL VERA
Interior/Exterior Lathing 11/21/2025 Partial Approval DANIEL VERA
ELECTRICAL-Rough 11/24/2025 No Access for Inspection CARLOS MATAMOROS
HVAC-Rough 11/24/2025 No Access for Inspection CARLOS MATAMOROS
Wood Frame 11/24/2025 No Access for Inspection CARLOS MATAMOROS
BUILDING-Rough-Frame 11/25/2025 Not Ready for Inspection CARLOS MATAMOROS
BUILDING-Rough-Frame 11/26/2025 Partial Approval CARLOS MATAMOROS
Deputy Wood Construction 11/26/2025 Conditional Approval ANDREW NAVE
Excavation/Setback/Form/Re-Bar 11/26/2025 Approved CARLOS MATAMOROS
BUILDING-Rough-Frame 12/8/2025 Approved CARLOS MATAMOROS
ELECTRICAL-Rough 12/8/2025 Approved CARLOS MATAMOROS
HVAC-Rough 12/8/2025 Approved CARLOS MATAMOROS
Insulation 12/8/2025 Approved CARLOS MATAMOROS
PLUMBING-Rough 12/8/2025 Approved CARLOS MATAMOROS
Drywall Nailing 12/26/2025 Not Ready for Inspection EVAN COOPER
Interior/Exterior Lathing 12/26/2025 Partial Approval EVAN COOPER
Drywall Nailing 12/30/2025 Approved CHRISTOPHER WILSON
Interior/Exterior Lathing 12/30/2025 Partial Approval CHRISTOPHER WILSON