380 WORLD WAY 90045
Certificate Information: 380 WORLD WAY 90045
- Application / Permit
- 25016-10000-25395
- Plan Check / Job No.
- B25LA35045
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (3) Airport Building
- Work Description
- **ePlan**LAX** Tenant Improvements: Relocate Office, no change of use
- Permit Issued
- Issued on 11/3/2025
- Issuing Office
- Current Status
- Permit Finaled on 6/2/2026
Permit Application Status History
| Submitted | 8/21/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 8/28/2025 | FARSHAD ALIMOHAMADI |
| Corrections Issued | 9/3/2025 | FARSHAD ALIMOHAMADI |
| Quality Review Completed | 9/4/2025 | LIPING TENG |
| Applicant returned to address corrections | 10/28/2025 | FARSHAD ALIMOHAMADI |
| Plan Check Approved | 10/29/2025 | FARSHAD ALIMOHAMADI |
| Issued | 11/3/2025 | APPLICANT |
| Permit Finaled | 6/2/2026 | NICK LAROCCA |
Permit Application Clearance Information
| City owned building/parcel | Cleared | 9/24/2025 | MASON NG |
| Project Permit | Cleared | 9/30/2025 | CHRISTOPHER MARTINEZ |
| Green Code | Cleared | 10/3/2025 | Lily Teng |
| Airport buildings | Cleared | 10/21/2025 | ANDREW KO |
| DAS Clearance | Cleared | 10/28/2025 | Lily Teng |
Contact Information
| Architect | Gerod,, Debra A; Lic. No.: C23665 | GRUEN ASSOCIATES 6330 SAN VICENTE BLVD. STE. 200 LOS ANGELES, CA 90048 |
| Contractor | Clark Construction Group California Lp; Lic. No.: 839892-B | , |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Drywall Nailing | 11/5/2025 | Approved | NICK LAROCCA |
| Light Gage Steel Frame | 11/5/2025 | Corrections Issued | NICK LAROCCA |
| Deputy Fireproofing | 11/10/2025 | Approved | NICK LAROCCA |
| Deputy Fireproofing | 11/13/2025 | Conditional Approval | RICARDO ROBLES |
| Deputy Fireproofing | 11/14/2025 | Conditional Approval | RICARDO ROBLES |
| Deputy Fireproofing | 11/17/2025 | Conditional Approval | RICARDO ROBLES |
| Pre-Inspection | 11/17/2025 | Not Ready for Inspection | RICARDO ROBLES |
| Deputy Fireproofing | 11/18/2025 | Conditional Approval | RICARDO ROBLES |
| Deputy Drilled-In Anchors | 12/3/2025 | Approved | NICK LAROCCA |
| Deputy Drilled-In Anchors | 12/4/2025 | Approved | NICK LAROCCA |
| Deputy Drilled-In Anchors | 12/5/2025 | Approved | NICK LAROCCA |
| Deputy Drilled-In Anchors | 12/8/2025 | Approved | NICK LAROCCA |
| Non Compliance | 12/9/2025 | Not Required | NICK LAROCCA |
| T-Bar Ceiling | 12/9/2025 | Approved | NICK LAROCCA |
| Final | 12/19/2025 | Partial Approval | NICK LAROCCA |
| Green Building Final | 12/19/2025 | Approved | NICK LAROCCA |
| SGSOV-Seismic Gas S/O Valve | 12/19/2025 | SGSOV Approved | NICK LAROCCA |
| Smoke Detectors | 12/19/2025 | Approved | NICK LAROCCA |
| Deputy Drilled-In Anchors | 1/16/2026 | Conditional Approval | RICARDO ROBLES |
| Deputy Reinf. Concrete | 1/16/2026 | Conditional Approval | RICARDO ROBLES |
| Insulation | 3/24/2026 | Approved | NICK LAROCCA |
| Light Gage Steel Frame | 3/24/2026 | Approved | NICK LAROCCA |
| T-Bar Ceiling | 4/20/2026 | Not Ready for Inspection | NICK LAROCCA |
| T-Bar Ceiling | 4/23/2026 | Approved | NICK LAROCCA |
| Final | 6/2/2026 | Permit Finaled | NICK LAROCCA |