800 W 6TH ST Suite 320 90017
Certificate Information: 800 W 6TH ST Suite 320 90017
- Application / Permit
- 25016-10000-25127
- Plan Check / Job No.
- B25LA34604
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (13) Office
- Work Description
- eplan: TI on (E) Office, New non bearing metal stud and gypsum board partitions, new flooring, new door, frame, and hardware assemblies.
- Permit Issued
- Issued on 10/31/2025
- Issuing Office
- Current Status
- Issued on 10/31/2025
Permit Application Status History
| Submitted | 8/26/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 8/29/2025 | TSE MING HUANG |
| Corrections Issued | 8/29/2025 | TSE MING HUANG |
| Plan Check Approved | 9/25/2025 | ZAW HAN |
| Issued | 10/31/2025 | APPLICANT |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Little Foot Construction Inc; Lic. No.: 800241-B | , |
| Engineer | Youngblood,, Charles St Denny; Lic. No.: NA45031 | , |
Inspector Information
| JEROME BLACKWOOD, (213) 213-5353 | Office Hours: 7:00-8:00 AM MON-FRI |
| REGINA MENDEZ, (213) 213-5353 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Light Gage Steel Frame | 11/12/2025 | Partial Approval | PAUL BAZERKANIAN |
| Insulation | 11/14/2025 | Partial Approval | PAUL BAZERKANIAN |
| Pre-Inspection | 11/14/2025 | Partial Approval | PAUL BAZERKANIAN |
| Drywall Nailing | 11/18/2025 | Partial Approval | PAUL BAZERKANIAN |
| SGSOV-Seismic Gas S/O Valve | 1/20/2026 | SGSOV Not Ready | PAUL BAZERKANIAN |
| Final | 1/21/2026 | Partial Inspection | PAUL BAZERKANIAN |