13319 1/4 W JUDD ST 91331
Certificate Information: 13319 1/4 W JUDD ST 91331
- Application / Permit
- 25016-10000-24853
- Plan Check / Job No.
- B25LA34177
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT ATTACHED CARPORT AND PORTION OF (E) SFD (13319) WITH A.D.U. (13319 1/2) INTO 236 sf J.A.D.U. (13319 1/4) PER GCS 66323(a)(1) AND 66333.
- Permit Issued
- Issued on 9/2/2025
- Issuing Office
- Current Status
- CofO Issued on 2/20/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/15/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 8/20/2025 | LAWRENCE QUIRANTE |
| Corrections Issued | 8/22/2025 | LAWRENCE QUIRANTE |
| Building Plans Picked Up | 8/25/2025 | APPLICANT |
| Applicant returned to address corrections | 9/2/2025 | CARLOS MONTES |
| Plan Check Approved | 9/2/2025 | SHANGQIN XIE |
| Issued | 9/2/2025 | APPLICANT |
| CofO in Progress | 1/30/2026 | MICHEL ABAJAN |
| Permit Finaled | 2/20/2026 | RUBEN SALAS |
| CofO Issued | 2/20/2026 | RUBEN SALAS |
| Permit Finaled | 2/20/2026 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 8/29/2025 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 8/29/2025 | LEE GUILBEAUX |
| Public Works-Highway Ded. | Cleared | 8/29/2025 | LEE GUILBEAUX |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MICHEL ABAJAN, (818) 374-9932 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 9/4/2025 | Approved | JENNIFER RABUCHIN |
| Excavation/Setback/Form/Re-Bar | 9/26/2025 | Approved | NICHOLAS TROWBRIDGE |
| Footing/Foundation/Slab | 9/26/2025 | Approved | NICHOLAS TROWBRIDGE |
| PLUMBING-Rough | 10/6/2025 | Partial Approval | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 10/15/2025 | Not Ready for Inspection | MICHEL ABAJAN |
| ELECTRICAL-Rough | 10/15/2025 | Not Ready for Inspection | MICHEL ABAJAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/15/2025 | Partial Approval | MICHEL ABAJAN |
| Green Building Rough | 10/15/2025 | Not Ready for Inspection | MICHEL ABAJAN |
| HVAC-Rough | 10/15/2025 | Not Ready for Inspection | MICHEL ABAJAN |
| METHANE-Rough | 10/15/2025 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 10/15/2025 | Approved | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 10/30/2025 | Approved | KEVIN BERBERYAN |
| ELECTRICAL-Rough | 10/30/2025 | Corrections Issued | KEVIN BERBERYAN |
| Green Building Rough | 10/30/2025 | Not Ready for Inspection | KEVIN BERBERYAN |
| HVAC-Rough | 10/30/2025 | Approved | KEVIN BERBERYAN |
| Interior/Exterior Lathing | 11/6/2025 | Partial Approval | MICHAEL CORTEZ |
| Shower Pan | 11/6/2025 | Approved | MICHAEL CORTEZ |
| Insulation | 11/14/2025 | Approved | MICHAEL CORTEZ |
| ELECTRICAL-Rough | 11/20/2025 | Approved | MICHEL ABAJAN |
| Drywall Nailing | 12/8/2025 | Approved | CHRISTOPHER MORFIN |
| SGSOV-Seismic Gas S/O Valve | 12/30/2025 | SGSOV Not Ready | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 1/9/2026 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Final | 1/9/2026 | Approved | MICHEL ABAJAN |
| Final | 1/9/2026 | Corrections Issued | MICHEL ABAJAN |
| Green Building Final | 1/9/2026 | Approved | MICHEL ABAJAN |
| Green Building Rough | 1/9/2026 | Approved | MICHEL ABAJAN |
| HVAC-Final | 1/9/2026 | Approved | MICHEL ABAJAN |
| PLUMBING-Final | 1/9/2026 | Approved | MICHEL ABAJAN |
| SGSOV-Seismic Gas S/O Valve | 1/9/2026 | SGSOV Approved | MICHEL ABAJAN |
| Service/Power Release | 1/9/2026 | Not Ready for Inspection | MICHEL ABAJAN |
| Smoke Detectors | 1/9/2026 | Approved | MICHEL ABAJAN |
| Final | 1/30/2026 | OK to Issue CofO | MICHEL ABAJAN |
| Service/Power Release | 1/30/2026 | Approved | MICHEL ABAJAN |