415-415 1/2 E 84TH ST 90003
Certificate Information: 415-415 1/2 E 84TH ST 90003
- Application / Permit
- 25016-10000-24811
- Plan Check / Job No.
- B25LA34102
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- CONVERT EXISTING FIRST FLOOR UNIT DEN TO A.D.U. IN EXISTING APARTMENT BUILDING PER ENGINEER DESIGN (ADU PER ORDINANCE, Attached ADU, LAMC 12.22 A.33 (c) and (e))
- Permit Issued
- Issued on 11/3/2025
- Issuing Office
- Metro
- Current Status
- Issued on 11/3/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 8/15/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 8/20/2025 | LAWRENCE QUIRANTE |
| Corrections Issued | 8/21/2025 | LAWRENCE QUIRANTE |
| Building Plans Picked Up | 8/25/2025 | APPLICANT |
| Applicant returned to address corrections | 10/17/2025 | SUNMIN LEE |
| Plan Check Approved | 10/30/2025 | AUNG SOE |
| Issued | 11/3/2025 | APPLICANT |
Permit Application Clearance Information
| Sewer availability | Cleared | 9/5/2025 | ABEL CASILLAS |
| Address approval | Cleared | 9/12/2025 | MICHAEL BROWN |
| Eng Process Fee Ord 176,300 | Cleared | 9/12/2025 | MICHAEL BROWN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Moser,, Bradley Charles; Lic. No.: C68803 | 116 OAKSIDE LN BUELLTON, CA 93427 |
Inspector Information
| PAUL BAZERKANIAN, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
| LUIS CCAMACHO, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
| ALAN MORELOS, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Special/Order Compliance | 11/6/2025 | Not Ready for Inspection | ALFREDO LOPEZ |
| Final | 3/31/2026 | Not Ready for Inspection | ALFREDO LOPEZ |
| Order to Comply | 3/31/2026 | Not Required | ALFREDO LOPEZ |
| Smoke Detectors | 3/31/2026 | Not Ready for Inspection | ALFREDO LOPEZ |
| Wood Frame | 3/31/2026 | Not Ready for Inspection | ALFREDO LOPEZ |
| Drywall Nailing | 5/22/2026 | Not Ready for Inspection | ALFREDO LOPEZ |
| Insulation | 5/22/2026 | Partial Approval | ALFREDO LOPEZ |
| Smoke Detectors | 5/22/2026 | Not Ready for Inspection | ALFREDO LOPEZ |
| Drywall Nailing | 5/26/2026 | Approved | DARRYL ARNOLD |