4427 W AVENUE 42 90065

Certificate Information: 4427 W AVENUE 42 90065

Application / Permit
25016-10000-24587
Plan Check / Job No.
B25LA33689
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Eplan GARAGE CONVERSION TO 432 SQ.FT. ADU PER STATE LAW
Permit Issued
Issued on 11/12/2025
Issuing Office
Current Status
CofO Issued on 6/15/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/14/2025 APPLICANT
Assigned to Plan Check Engineer 8/19/2025 NEHEMIAS RAMOS
Corrections Issued 8/19/2025 NEHEMIAS RAMOS
Applicant returned to address corrections 9/26/2025 JOSE VELAZQUEZ
Applicant returned to address corrections 10/24/2025 NEHEMIAS RAMOS
Applicant returned to address corrections 11/1/2025 NEHEMIAS RAMOS
Plan Check Approved 11/10/2025 JOSE VELAZQUEZ
Issued 11/12/2025 APPLICANT
CofO in Progress 6/11/2026 RONNIE MEDINA
Permit Finaled 6/15/2026 DEROLD HAUFF
CofO Issued 6/15/2026 DEROLD HAUFF
Permit Finaled 6/15/2026 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 8/23/2025 COLIN LOREDO
Sewer availability Cleared 8/23/2025 COLIN LOREDO
Grading Pre-Inspection Cleared 8/27/2025 RUSSELL BONVOULOIR
Eng Process Fee Ord 176,300 Cleared 8/28/2025 COLIN LOREDO
Construction near power lines Cleared 10/22/2025 RIDWAN HARDY

Contact Information

Contractor Pacific Point Builders Inc; Lic. No.: 768984-B       ,

Inspector Information

RONNIE MEDINA, (213) 469-5852 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 12/3/2025 Not Ready for Inspection RONNIE MEDINA
Floor/Roof Diaphrgm/Shear Wall 12/10/2025 Corrections Issued RONNIE MEDINA
Footing/Foundation/Slab 12/10/2025 Approved RONNIE MEDINA
Sewer 12/10/2025 Partial Approval RONNIE MEDINA
Deputy Reinf. Concrete 12/16/2025 Conditional Approval RONNIE MEDINA
BUILDING-Rough-Frame 2/26/2026 Not Ready for Inspection LILIANA PORTILLO
ELECTRICAL-Rough 2/26/2026 Corrections Issued LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 2/26/2026 Approved LILIANA PORTILLO
HVAC-Rough 2/26/2026 Approved LILIANA PORTILLO
MERV13>=Rough 2/26/2026 Approved LILIANA PORTILLO
PLUMBING-Rough 2/26/2026 Corrections Issued LILIANA PORTILLO
Verify Sprinkler Sign Off 2/26/2026 Approved LILIANA PORTILLO
Rough-Elec/Plmb/HVAC 3/10/2026 Approved RONNIE MEDINA
BUILDING-Rough-Frame 3/13/2026 Conditional Approval RONNIE MEDINA
Green Building Rough 3/13/2026 Approved RONNIE MEDINA
Interior/Exterior Lathing 3/13/2026 Partial Approval RONNIE MEDINA
Insulation 3/23/2026 Approved GEM DE OCAMPO
Drywall Nailing 3/27/2026 Approved RONNIE MEDINA
Sewer 4/6/2026 Approved RONNIE MEDINA
Shower Pan 4/16/2026 Approved GEM DE OCAMPO
Interior/Exterior Lathing 4/20/2026 Approved GEM DE OCAMPO
BUILDING-Rough-Frame 5/18/2026 Not Ready for Inspection RONNIE MEDINA
ELECTRICAL-Final 5/18/2026 Not Ready for Inspection RONNIE MEDINA
Final 5/18/2026 Not Ready for Inspection RONNIE MEDINA
Green Building Final 5/18/2026 Not Ready for Inspection RONNIE MEDINA
HVAC-Final 5/18/2026 Not Ready for Inspection RONNIE MEDINA
MERV13>=Final 5/18/2026 Not Ready for Inspection RONNIE MEDINA
PLUMBING-Final 5/18/2026 Not Ready for Inspection RONNIE MEDINA
SGSOV-Seismic Gas S/O Valve 5/18/2026 SGSOV Not Ready RONNIE MEDINA
Service/Power Release 5/18/2026 Not Ready for Inspection RONNIE MEDINA
Smoke Detectors 5/18/2026 Not Ready for Inspection RONNIE MEDINA
BUILDING-Rough-Frame 5/26/2026 Not Ready for Inspection RONNIE MEDINA
ELECTRICAL-Final 5/26/2026 Not Ready for Inspection RONNIE MEDINA
Final 5/26/2026 Not Ready for Inspection RONNIE MEDINA
Green Building Final 5/26/2026 Not Ready for Inspection RONNIE MEDINA
HVAC-Final 5/26/2026 Not Ready for Inspection RONNIE MEDINA
MERV13>=Final 5/26/2026 Not Ready for Inspection RONNIE MEDINA
PLUMBING-Final 5/26/2026 Not Ready for Inspection RONNIE MEDINA
SGSOV-Seismic Gas S/O Valve 5/26/2026 SGSOV Not Ready RONNIE MEDINA
Smoke Detectors 5/26/2026 Not Ready for Inspection RONNIE MEDINA
Service/Power Release 6/8/2026 Not Ready for Inspection RONNIE MEDINA
BUILDING-Rough-Frame 6/10/2026 Approved RONNIE MEDINA
ELECTRICAL-Final 6/10/2026 Approved RONNIE MEDINA
Final 6/10/2026 OK to Issue CofO RONNIE MEDINA
Green Building Final 6/10/2026 Approved RONNIE MEDINA
HVAC-Final 6/10/2026 Approved RONNIE MEDINA
MERV13>=Final 6/10/2026 Approved RONNIE MEDINA
PLUMBING-Final 6/10/2026 Approved RONNIE MEDINA
SGSOV-Seismic Gas S/O Valve 6/10/2026 SGSOV No Gas RONNIE MEDINA
Service/Power Release 6/10/2026 Approved RONNIE MEDINA
Smoke Detectors 6/10/2026 Approved RONNIE MEDINA