4427 W AVENUE 42 90065
Certificate Information: 4427 W AVENUE 42 90065
- Application / Permit
- 25016-10000-24587
- Plan Check / Job No.
- B25LA33689
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Eplan GARAGE CONVERSION TO 432 SQ.FT. ADU PER STATE LAW
- Permit Issued
- Issued on 11/12/2025
- Issuing Office
- Current Status
- CofO Issued on 6/15/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/14/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 8/19/2025 | NEHEMIAS RAMOS |
| Corrections Issued | 8/19/2025 | NEHEMIAS RAMOS |
| Applicant returned to address corrections | 9/26/2025 | JOSE VELAZQUEZ |
| Applicant returned to address corrections | 10/24/2025 | NEHEMIAS RAMOS |
| Applicant returned to address corrections | 11/1/2025 | NEHEMIAS RAMOS |
| Plan Check Approved | 11/10/2025 | JOSE VELAZQUEZ |
| Issued | 11/12/2025 | APPLICANT |
| CofO in Progress | 6/11/2026 | RONNIE MEDINA |
| Permit Finaled | 6/15/2026 | DEROLD HAUFF |
| CofO Issued | 6/15/2026 | DEROLD HAUFF |
| Permit Finaled | 6/15/2026 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 8/23/2025 | COLIN LOREDO |
| Sewer availability | Cleared | 8/23/2025 | COLIN LOREDO |
| Grading Pre-Inspection | Cleared | 8/27/2025 | RUSSELL BONVOULOIR |
| Eng Process Fee Ord 176,300 | Cleared | 8/28/2025 | COLIN LOREDO |
| Construction near power lines | Cleared | 10/22/2025 | RIDWAN HARDY |
Contact Information
| Contractor | Pacific Point Builders Inc; Lic. No.: 768984-B | , |
Inspector Information
| RONNIE MEDINA, (213) 469-5852 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 12/3/2025 | Not Ready for Inspection | RONNIE MEDINA |
| Floor/Roof Diaphrgm/Shear Wall | 12/10/2025 | Corrections Issued | RONNIE MEDINA |
| Footing/Foundation/Slab | 12/10/2025 | Approved | RONNIE MEDINA |
| Sewer | 12/10/2025 | Partial Approval | RONNIE MEDINA |
| Deputy Reinf. Concrete | 12/16/2025 | Conditional Approval | RONNIE MEDINA |
| BUILDING-Rough-Frame | 2/26/2026 | Not Ready for Inspection | LILIANA PORTILLO |
| ELECTRICAL-Rough | 2/26/2026 | Corrections Issued | LILIANA PORTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 2/26/2026 | Approved | LILIANA PORTILLO |
| HVAC-Rough | 2/26/2026 | Approved | LILIANA PORTILLO |
| MERV13>=Rough | 2/26/2026 | Approved | LILIANA PORTILLO |
| PLUMBING-Rough | 2/26/2026 | Corrections Issued | LILIANA PORTILLO |
| Verify Sprinkler Sign Off | 2/26/2026 | Approved | LILIANA PORTILLO |
| Rough-Elec/Plmb/HVAC | 3/10/2026 | Approved | RONNIE MEDINA |
| BUILDING-Rough-Frame | 3/13/2026 | Conditional Approval | RONNIE MEDINA |
| Green Building Rough | 3/13/2026 | Approved | RONNIE MEDINA |
| Interior/Exterior Lathing | 3/13/2026 | Partial Approval | RONNIE MEDINA |
| Insulation | 3/23/2026 | Approved | GEM DE OCAMPO |
| Drywall Nailing | 3/27/2026 | Approved | RONNIE MEDINA |
| Sewer | 4/6/2026 | Approved | RONNIE MEDINA |
| Shower Pan | 4/16/2026 | Approved | GEM DE OCAMPO |
| Interior/Exterior Lathing | 4/20/2026 | Approved | GEM DE OCAMPO |
| BUILDING-Rough-Frame | 5/18/2026 | Not Ready for Inspection | RONNIE MEDINA |
| ELECTRICAL-Final | 5/18/2026 | Not Ready for Inspection | RONNIE MEDINA |
| Final | 5/18/2026 | Not Ready for Inspection | RONNIE MEDINA |
| Green Building Final | 5/18/2026 | Not Ready for Inspection | RONNIE MEDINA |
| HVAC-Final | 5/18/2026 | Not Ready for Inspection | RONNIE MEDINA |
| MERV13>=Final | 5/18/2026 | Not Ready for Inspection | RONNIE MEDINA |
| PLUMBING-Final | 5/18/2026 | Not Ready for Inspection | RONNIE MEDINA |
| SGSOV-Seismic Gas S/O Valve | 5/18/2026 | SGSOV Not Ready | RONNIE MEDINA |
| Service/Power Release | 5/18/2026 | Not Ready for Inspection | RONNIE MEDINA |
| Smoke Detectors | 5/18/2026 | Not Ready for Inspection | RONNIE MEDINA |
| BUILDING-Rough-Frame | 5/26/2026 | Not Ready for Inspection | RONNIE MEDINA |
| ELECTRICAL-Final | 5/26/2026 | Not Ready for Inspection | RONNIE MEDINA |
| Final | 5/26/2026 | Not Ready for Inspection | RONNIE MEDINA |
| Green Building Final | 5/26/2026 | Not Ready for Inspection | RONNIE MEDINA |
| HVAC-Final | 5/26/2026 | Not Ready for Inspection | RONNIE MEDINA |
| MERV13>=Final | 5/26/2026 | Not Ready for Inspection | RONNIE MEDINA |
| PLUMBING-Final | 5/26/2026 | Not Ready for Inspection | RONNIE MEDINA |
| SGSOV-Seismic Gas S/O Valve | 5/26/2026 | SGSOV Not Ready | RONNIE MEDINA |
| Smoke Detectors | 5/26/2026 | Not Ready for Inspection | RONNIE MEDINA |
| Service/Power Release | 6/8/2026 | Not Ready for Inspection | RONNIE MEDINA |
| BUILDING-Rough-Frame | 6/10/2026 | Approved | RONNIE MEDINA |
| ELECTRICAL-Final | 6/10/2026 | Approved | RONNIE MEDINA |
| Final | 6/10/2026 | OK to Issue CofO | RONNIE MEDINA |
| Green Building Final | 6/10/2026 | Approved | RONNIE MEDINA |
| HVAC-Final | 6/10/2026 | Approved | RONNIE MEDINA |
| MERV13>=Final | 6/10/2026 | Approved | RONNIE MEDINA |
| PLUMBING-Final | 6/10/2026 | Approved | RONNIE MEDINA |
| SGSOV-Seismic Gas S/O Valve | 6/10/2026 | SGSOV No Gas | RONNIE MEDINA |
| Service/Power Release | 6/10/2026 | Approved | RONNIE MEDINA |
| Smoke Detectors | 6/10/2026 | Approved | RONNIE MEDINA |