1813 S CRESCENT HEIGHTS BLVD 90035

Certificate Information: 1813 S CRESCENT HEIGHTS BLVD 90035

Application / Permit
25016-10000-24295
Plan Check / Job No.
B25LA33219
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
EPLAN: CONVERT (E) DETACHED GARAGE INTO ACCESSORY DWELLING UNIT PER GCS 66323(a)(1)
Permit Issued
Issued on 9/1/2025
Issuing Office
Current Status
Issued on 9/1/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 8/11/2025 APPLICANT
Assigned to Plan Check Engineer 8/13/2025 GURUNATH NESARAJAH
Corrections Issued 8/14/2025 GURUNATH NESARAJAH
Plan Check Approved 8/31/2025 GURUNATH NESARAJAH
Issued 9/1/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 8/15/2025 DERRICK MAGEE
Eng Process Fee Ord 176,300 Cleared 8/15/2025 DERRICK MAGEE
Sewer availability Cleared 8/15/2025 DERRICK MAGEE
ZI Cleared 8/27/2025 FIPE LEILUA

Contact Information

Architect Dembsky,, Amit; Lic. No.: NA30383       ,
Contractor Oasis Builders Inc; Lic. No.: 1055132-B       ,

Inspector Information

DAVID WILLIAMS, (213) 202-3126 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 12/12/2025 Partial Approval BRENDAN MORELLI
Sewer 12/12/2025 Approved BRENDAN MORELLI
Underground Mechanical 12/12/2025 Partial Approval BRENDAN MORELLI
Footing/Foundation/Slab 12/22/2025 Approved BRENDAN MORELLI
BUILDING-Rough-Frame 1/29/2026 Partial Approval BRENDAN MORELLI
ELECTRICAL-Rough 1/29/2026 Approved BRENDAN MORELLI
Green Building Rough 1/29/2026 Not Ready for Inspection BRENDAN MORELLI
HVAC-Rough 1/29/2026 Approved BRENDAN MORELLI
METHANE-Rough 1/29/2026 Approved BRENDAN MORELLI
PLUMBING-Rough 1/29/2026 Corrections Issued BRENDAN MORELLI
BUILDING-Rough-Frame 2/2/2026 Not Ready for Inspection JOSH MEISTER
Green Building Rough 2/2/2026 Not Ready for Inspection JOSH MEISTER
PLUMBING-Rough 2/2/2026 Approved JOSH MEISTER
BUILDING-Rough-Frame 2/5/2026 Approved JOSH MEISTER
Green Building Rough 2/5/2026 Approved JOSH MEISTER
Shower Pan 2/5/2026 Approved JOSH MEISTER
Insulation 2/17/2026 Corrections Issued BRENDAN MORELLI
Interior/Exterior Lathing 2/17/2026 Approved BRENDAN MORELLI
Insulation 2/18/2026 Approved BRENDAN MORELLI
Drywall Nailing 2/23/2026 Approved ALEX COLIN
ELECTRICAL-Final 6/4/2026 Approved DAVID WILLIAMS
Final 6/4/2026 Corrections Issued DAVID WILLIAMS
Green Building Final 6/4/2026 Approved DAVID WILLIAMS
HVAC-Final 6/4/2026 Approved DAVID WILLIAMS
PLUMBING-Final 6/4/2026 Approved DAVID WILLIAMS
SGSOV-Seismic Gas S/O Valve 6/4/2026 SGSOV Approved DAVID WILLIAMS
Smoke Detectors 6/4/2026 Approved DAVID WILLIAMS