1813 S CRESCENT HEIGHTS BLVD 90035
Certificate Information: 1813 S CRESCENT HEIGHTS BLVD 90035
- Application / Permit
- 25016-10000-24295
- Plan Check / Job No.
- B25LA33219
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN: CONVERT (E) DETACHED GARAGE INTO ACCESSORY DWELLING UNIT PER GCS 66323(a)(1)
- Permit Issued
- Issued on 9/1/2025
- Issuing Office
- Current Status
- Issued on 9/1/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 8/11/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 8/13/2025 | GURUNATH NESARAJAH |
| Corrections Issued | 8/14/2025 | GURUNATH NESARAJAH |
| Plan Check Approved | 8/31/2025 | GURUNATH NESARAJAH |
| Issued | 9/1/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 8/15/2025 | DERRICK MAGEE |
| Eng Process Fee Ord 176,300 | Cleared | 8/15/2025 | DERRICK MAGEE |
| Sewer availability | Cleared | 8/15/2025 | DERRICK MAGEE |
| ZI | Cleared | 8/27/2025 | FIPE LEILUA |
Contact Information
| Architect | Dembsky,, Amit; Lic. No.: NA30383 | , |
| Contractor | Oasis Builders Inc; Lic. No.: 1055132-B | , |
Inspector Information
| DAVID WILLIAMS, (213) 202-3126 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 12/12/2025 | Partial Approval | BRENDAN MORELLI |
| Sewer | 12/12/2025 | Approved | BRENDAN MORELLI |
| Underground Mechanical | 12/12/2025 | Partial Approval | BRENDAN MORELLI |
| Footing/Foundation/Slab | 12/22/2025 | Approved | BRENDAN MORELLI |
| BUILDING-Rough-Frame | 1/29/2026 | Partial Approval | BRENDAN MORELLI |
| ELECTRICAL-Rough | 1/29/2026 | Approved | BRENDAN MORELLI |
| Green Building Rough | 1/29/2026 | Not Ready for Inspection | BRENDAN MORELLI |
| HVAC-Rough | 1/29/2026 | Approved | BRENDAN MORELLI |
| METHANE-Rough | 1/29/2026 | Approved | BRENDAN MORELLI |
| PLUMBING-Rough | 1/29/2026 | Corrections Issued | BRENDAN MORELLI |
| BUILDING-Rough-Frame | 2/2/2026 | Not Ready for Inspection | JOSH MEISTER |
| Green Building Rough | 2/2/2026 | Not Ready for Inspection | JOSH MEISTER |
| PLUMBING-Rough | 2/2/2026 | Approved | JOSH MEISTER |
| BUILDING-Rough-Frame | 2/5/2026 | Approved | JOSH MEISTER |
| Green Building Rough | 2/5/2026 | Approved | JOSH MEISTER |
| Shower Pan | 2/5/2026 | Approved | JOSH MEISTER |
| Insulation | 2/17/2026 | Corrections Issued | BRENDAN MORELLI |
| Interior/Exterior Lathing | 2/17/2026 | Approved | BRENDAN MORELLI |
| Insulation | 2/18/2026 | Approved | BRENDAN MORELLI |
| Drywall Nailing | 2/23/2026 | Approved | ALEX COLIN |
| ELECTRICAL-Final | 6/4/2026 | Approved | DAVID WILLIAMS |
| Final | 6/4/2026 | Corrections Issued | DAVID WILLIAMS |
| Green Building Final | 6/4/2026 | Approved | DAVID WILLIAMS |
| HVAC-Final | 6/4/2026 | Approved | DAVID WILLIAMS |
| PLUMBING-Final | 6/4/2026 | Approved | DAVID WILLIAMS |
| SGSOV-Seismic Gas S/O Valve | 6/4/2026 | SGSOV Approved | DAVID WILLIAMS |
| Smoke Detectors | 6/4/2026 | Approved | DAVID WILLIAMS |