6336 W 77TH ST 90045

Certificate Information: 6336 W 77TH ST 90045

Application / Permit
25016-10000-23987
Plan Check / Job No.
B25LA32687
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan. CONVERT EXISTING DETACHED GARAGE TO NEW ADU PER STATE LAW
Permit Issued
Issued on 9/18/2025
Issuing Office
Current Status
CofO in Progress on 5/27/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 8/6/2025 APPLICANT
Assigned to Plan Check Engineer 8/12/2025 ZAW HAN
Corrections Issued 8/13/2025 ZAW HAN
Plan Check Approved 9/17/2025 FERNANDO FLORES
Issued 9/18/2025 APPLICANT
CofO in Progress 5/27/2026 MORRIS JACKSON

Permit Application Clearance Information

CPC Cleared 8/21/2025 DANIEL CORONADO
CPC Cleared 8/21/2025 DANIEL CORONADO
CPC Cleared 8/21/2025 DANIEL CORONADO
Specific Plan Cleared 8/21/2025 RICHARD WOO
Grading Pre-Inspection Cleared 8/22/2025 LANNY MERRICK
Address approval Cleared 8/23/2025 CHRISTINE REUSCH
Roof/Waste drainage to street Cleared 8/27/2025 CHRISTINE REUSCH
Miscellaneous Cleared 9/10/2025 CHRISTINE REUSCH
Eng Process Fee Ord 176,300 Cleared 9/11/2025 CHRISTINE REUSCH
Sewer availability Cleared 9/11/2025 CHRISTINE REUSCH

Contact Information

Architect Noteware,, Brian Arthur; Lic. No.: C21514 845 20TH STREET, #106      SANTA MONICA, CA 90403
Contractor Owner-Builder       ,

Inspector Information

MORRIS JACKSON, (310) 914-3885 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 9/23/2025 Corrections Issued RUBEN RIVAS
Footing/Foundation/Slab 9/30/2025 Approved RUBEN RIVAS
Sewer 10/28/2025 Approved RUBEN RIVAS
Underground Mechanical 10/28/2025 Partial Approval RUBEN RIVAS
Floor/Roof Diaphrgm/Shear Wall 12/4/2025 Partial Approval ANTHONY EGSON
Interior/Exterior Lathing 12/8/2025 Approved ANTHONY EGSON
BUILDING-Rough-Frame 12/12/2025 Not Ready for Inspection ANTHONY EGSON
ELECTRICAL-Rough 12/12/2025 Not Ready for Inspection ANTHONY EGSON
Green Building Rough 12/12/2025 Not Ready for Inspection ANTHONY EGSON
HVAC-Rough 12/12/2025 Not Ready for Inspection ANTHONY EGSON
METHANE-Rough 12/12/2025 Not Ready for Inspection ANTHONY EGSON
PLUMBING-Rough 12/12/2025 Not Ready for Inspection ANTHONY EGSON
Wood Frame 12/12/2025 Not Ready for Inspection ANTHONY EGSON
ELECTRICAL-Rough 12/16/2025 Partial Approval ANTHONY EGSON
PLUMBING-Rough 12/16/2025 Approved ANTHONY EGSON
ELECTRICAL-Rough 12/19/2025 Approved ANTHONY EGSON
PLUMBING-Rough 12/19/2025 Approved ANTHONY EGSON
Insulation 12/30/2025 Approved ANTHONY EGSON
Drywall Nailing 1/12/2026 Approved ANTHONY EGSON
Interior/Exterior Lathing 1/12/2026 Partial Approval ANTHONY EGSON
BUILDING-Rough-Frame 5/7/2026 Conditional Approval ANTHONY EGSON
ELECTRICAL-Final 5/7/2026 Corrections Issued ANTHONY EGSON
Final 5/7/2026 Not Ready for Inspection ANTHONY EGSON
Green Building Final 5/7/2026 Not Ready for Inspection ANTHONY EGSON
Green Building Rough 5/7/2026 Approved ANTHONY EGSON
PLUMBING-Final 5/7/2026 Not Ready for Inspection ANTHONY EGSON
SGSOV-Seismic Gas S/O Valve 5/7/2026 SGSOV Approved ANTHONY EGSON
Smoke Detectors 5/7/2026 Approved ANTHONY EGSON
ELECTRICAL-Final 5/12/2026 Approved MORRIS JACKSON
HVAC-Final 5/12/2026 Approved MORRIS JACKSON
PLUMBING-Final 5/12/2026 Approved MORRIS JACKSON
BUILDING-Rough-Frame 5/26/2026 Approved MORRIS JACKSON
Final 5/26/2026 OK to Issue CofO MORRIS JACKSON
Green Building Final 5/26/2026 Approved MORRIS JACKSON
METHANE-Final 5/26/2026 Approved MORRIS JACKSON
METHANE-Rough 5/26/2026 Approved MORRIS JACKSON