Pre-Inspection
|
2/4/2026
|
Partial Inspection
|
ROGELIO REYNA
|
|
Special/Order Compliance
|
2/4/2026
|
Corrections Issued
|
CASIMIR BRITTON
|
|
Excavation/Setback/Form/Re-Bar
|
2/10/2026
|
Not Ready for Inspection
|
ROGELIO REYNA
|
|
Footing/Foundation/Slab
|
2/10/2026
|
Not Ready for Inspection
|
CASIMIR BRITTON
|
|
Footing/Foundation/Slab
|
2/10/2026
|
Not Ready for Inspection
|
ROGELIO REYNA
|
|
Excavation/Setback/Form/Re-Bar
|
2/11/2026
|
Not Ready for Inspection
|
ROGELIO REYNA
|
|
Footing/Foundation/Slab
|
2/11/2026
|
Not Ready for Inspection
|
ROGELIO REYNA
|
|
Green Building Rough
|
2/12/2026
|
Not Ready for Inspection
|
ROGELIO REYNA
|
|
Reinforced Concrete Frame
|
2/12/2026
|
Not Ready for Inspection
|
ROGELIO REYNA
|
|
Verify Sprinkler Sign Off
|
2/12/2026
|
Not Ready for Inspection
|
ROGELIO REYNA
|
|
Deputy Shotcrete
|
2/19/2026
|
Conditional Approval
|
ROGELIO REYNA
|
|
Light Gage Steel Frame
|
2/24/2026
|
Not Ready for Inspection
|
ROGELIO REYNA
|
|
Light Gage Steel Frame
|
2/24/2026
|
Partial Inspection
|
CASIMIR BRITTON
|
|
Masonry Wall/Backfill
|
2/24/2026
|
Not Ready for Inspection
|
ROGELIO REYNA
|
|
Excavation/Setback/Form/Re-Bar
|
2/26/2026
|
Not Ready for Inspection
|
ROGELIO REYNA
|
|
Light Gage Steel Frame
|
2/26/2026
|
Partial Approval
|
ROGELIO REYNA
|
|
Footing/Foundation/Slab
|
3/12/2026
|
Partial Approval
|
DANIEL VARNUM
|
|
Structural Steel Frame
|
3/12/2026
|
Partial Approval
|
DANIEL VARNUM
|
|
Insulation
|
3/16/2026
|
Partial Approval
|
DANIEL VARNUM
|
|
Light Gage Steel Frame
|
3/18/2026
|
Off-Hour Fees Due
|
|
|
Light Gage Steel Frame
|
3/18/2026
|
Partial Approval
|
DANIEL VARNUM
|
|
Masonry Wall/Backfill
|
3/18/2026
|
Off-Hour Fees Due
|
|
|
Masonry Wall/Backfill
|
3/18/2026
|
Partial Inspection
|
DANIEL VARNUM
|
|
Drywall Nailing
|
3/20/2026
|
Off-Hour Fees Due
|
|
|
Drywall Nailing
|
3/20/2026
|
Partial Approval
|
DANIEL VARNUM
|
|
Final
|
3/20/2026
|
Off-Hour Fees Due
|
|
|
Green Building Final
|
3/20/2026
|
Off-Hour Fees Due
|
|
|
Green Building Rough
|
3/20/2026
|
Off-Hour Fees Due
|
|
|
Masonry Wall/Backfill
|
3/20/2026
|
Not Ready for Inspection
|
DANIEL VARNUM
|
|
Masonry Wall/Backfill
|
3/20/2026
|
Off-Hour Fees Due
|
|
|
Reinforced Concrete Frame
|
3/20/2026
|
Off-Hour Fees Due
|
|
|
SGSOV-Seismic Gas S/O Valve
|
3/20/2026
|
Off-Hour Fees Due
|
|
|
Smoke Detectors
|
3/20/2026
|
Off-Hour Fees Due
|
|
|
Verify Sprinkler Sign Off
|
3/20/2026
|
Off-Hour Fees Due
|
|
|
Light Gage Steel Frame
|
3/27/2026
|
Partial Approval
|
PAUL DAVIDSON
|
|
Light Gage Steel Frame
|
4/2/2026
|
Partial Approval
|
DANIEL VARNUM
|
|
Masonry Wall/Backfill
|
4/2/2026
|
Partial Approval
|
DANIEL VARNUM
|
|
Light Gage Steel Frame
|
4/13/2026
|
Partial Approval
|
PAUL DAVIDSON
|
|
Light Gage Steel Frame
|
5/15/2026
|
Partial Approval
|
DANIEL ARMENTA
|
|
Green Building Rough
|
5/18/2026
|
Not Ready for Inspection
|
ROGELIO REYNA
|
|
Reinforced Concrete Frame
|
5/18/2026
|
Corrections Issued
|
ROGELIO REYNA
|
|
Verify Sprinkler Sign Off
|
5/18/2026
|
Not Ready for Inspection
|
ROGELIO REYNA
|
|
Green Building Rough
|
5/20/2026
|
Not Ready for Inspection
|
ROGELIO REYNA
|
|
Reinforced Concrete Frame
|
5/20/2026
|
Partial Approval
|
ROGELIO REYNA
|
|
Verify Sprinkler Sign Off
|
5/20/2026
|
Not Ready for Inspection
|
ROGELIO REYNA
|
|
Green Building Rough
|
5/29/2026
|
Not Ready for Inspection
|
ROGELIO REYNA
|
|
Light Gage Steel Frame
|
5/29/2026
|
Partial Approval
|
ROGELIO REYNA
|
|
Reinforced Concrete Frame
|
5/29/2026
|
Partial Approval
|
ROGELIO REYNA
|
|
Verify Sprinkler Sign Off
|
5/29/2026
|
Not Ready for Inspection
|
ROGELIO REYNA
|
|
Green Building Rough
|
6/5/2026
|
Not Ready for Inspection
|
DANIEL ARMENTA
|
|
Light Gage Steel Frame
|
6/5/2026
|
Partial Approval
|
DANIEL ARMENTA
|
|
Reinforced Concrete Frame
|
6/5/2026
|
Not Ready for Inspection
|
DANIEL ARMENTA
|
|
Verify Sprinkler Sign Off
|
6/5/2026
|
Not Ready for Inspection
|
DANIEL ARMENTA
|
|
Green Building Rough
|
6/9/2026
|
Not Ready for Inspection
|
ROGELIO REYNA
|
|
Reinforced Concrete Frame
|
6/9/2026
|
Not Ready for Inspection
|
ROGELIO REYNA
|
|
Verify Sprinkler Sign Off
|
6/9/2026
|
Not Ready for Inspection
|
ROGELIO REYNA
|
|
Excavation/Setback/Form/Re-Bar
|
6/11/2026
|
Not Ready for Inspection
|
DANIEL ARMENTA
|
|
Green Building Rough
|
6/12/2026
|
Not Ready for Inspection
|
DERRICK SPENCER
|
|
Reinforced Concrete Frame
|
6/12/2026
|
Not Ready for Inspection
|
DERRICK SPENCER
|
|
Verify Sprinkler Sign Off
|
6/12/2026
|
Not Ready for Inspection
|
DERRICK SPENCER
|
|
Green Building Rough
|
6/16/2026
|
Not Ready for Inspection
|
ROGELIO REYNA
|
|
Reinforced Concrete Frame
|
6/16/2026
|
Partial Approval
|
ROGELIO REYNA
|
|
Verify Sprinkler Sign Off
|
6/16/2026
|
Not Ready for Inspection
|
ROGELIO REYNA
|
|
Drywall Nailing
|
6/17/2026
|
Partial Approval
|
ROGELIO REYNA
|
|
Light Gage Steel Frame
|
6/18/2026
|
Partial Approval
|
ROGELIO REYNA
|
|
Drywall Nailing
|
6/25/2026
|
Not Ready for Inspection
|
ROGELIO REYNA
|
|
Light Gage Steel Frame
|
6/25/2026
|
Partial Approval
|
ROGELIO REYNA
|
|
Light Gage Steel Frame
|
6/26/2026
|
Approved
|
VASIL MIHALEV
|
|
T-Bar Ceiling
|
6/26/2026
|
Approved
|
VASIL MIHALEV
|
|
Drywall Nailing
|
7/1/2026
|
Not Ready for Inspection
|
ROGELIO REYNA
|
|
Insulation
|
7/1/2026
|
Not Ready for Inspection
|
ROGELIO REYNA
|
|
Light Gage Steel Frame
|
7/1/2026
|
Partial Approval
|
ROGELIO REYNA
|
|
T-Bar Ceiling
|
7/1/2026
|
Not Ready for Inspection
|
ROGELIO REYNA
|
|
Drywall Nailing
|
7/2/2026
|
Not Ready for Inspection
|
ROGELIO REYNA
|
|
Insulation
|
7/2/2026
|
Not Ready for Inspection
|
ROGELIO REYNA
|
|
Light Gage Steel Frame
|
7/2/2026
|
Partial Approval
|
ROGELIO REYNA
|
|
T-Bar Ceiling
|
7/2/2026
|
Partial Approval
|
ROGELIO REYNA
|
|
Drywall Nailing
|
7/6/2026
|
Not Ready for Inspection
|
ROGELIO REYNA
|
|
Insulation
|
7/6/2026
|
Not Ready for Inspection
|
ROGELIO REYNA
|
|
Light Gage Steel Frame
|
7/6/2026
|
Partial Approval
|
ROGELIO REYNA
|
|
T-Bar Ceiling
|
7/6/2026
|
Partial Approval
|
ROGELIO REYNA
|
|
T-Bar Ceiling
|
7/7/2026
|
Partial Approval
|
ROGELIO REYNA
|
|
Light Gage Steel Frame
|
7/14/2026
|
Partial Approval
|
ROGELIO REYNA
|
|
T-Bar Ceiling
|
7/14/2026
|
Partial Approval
|
ROGELIO REYNA
|
|
Drywall Nailing
|
7/17/2026
|
Partial Approval
|
ROGELIO REYNA
|
|
Light Gage Steel Frame
|
7/17/2026
|
Partial Approval
|
ROGELIO REYNA
|