649 N LILLIAN WAY 90004
Certificate Information: 649 N LILLIAN WAY 90004
- Application / Permit
- 25016-10000-23851
- Plan Check / Job No.
- B25LA32434
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan: Convert existing detached garage to ADU PER GC 66323(a)(1).
- Permit Issued
- Issued on 10/8/2025
- Issuing Office
- Current Status
- Issued on 10/8/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 8/5/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 8/8/2025 | ALEC MOUSAKHANIAN |
| Corrections Issued | 8/11/2025 | ALEC MOUSAKHANIAN |
| Plan Check Approved | 9/1/2025 | ALEC MOUSAKHANIAN |
| Issued | 10/8/2025 | APPLICANT |
Permit Application Clearance Information
| HPOZ | Cleared | 8/12/2025 | SUKI GERSHENHORN |
| Address approval | Cleared | 8/16/2025 | DAVID LOPEZ |
| Roof/Waste drainage to street | Cleared | 8/16/2025 | DAVID LOPEZ |
| Sewer availability | Cleared | 8/16/2025 | DAVID LOPEZ |
| Eng Process Fee Ord 176,300 | Cleared | 8/18/2025 | DAVID LOPEZ |
| Flood clearance | Cleared | 8/18/2025 | SAMSON WONG |
Contact Information
| Contractor | Rivera'S Construction; Lic. No.: 1060375-B | , |
| Engineer | Yenjai,, Seree; Lic. No.: C73151 | 3249 SHADYLAWN DRIVE DUARTE, CA 91010 |
Inspector Information
| JEFFREY MEAD, (213) 202-3240 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 10/23/2025 | Corrections Issued | JEFFREY MEAD |
| Underground Mechanical | 11/6/2025 | Approved | JEFFREY MEAD |
| Footing/Foundation/Slab | 11/12/2025 | Approved | JEFFREY MEAD |
| BUILDING-Rough-Frame | 1/7/2026 | Not Ready for Inspection | JEFFREY MEAD |
| ELECTRICAL-Rough | 1/7/2026 | Corrections Issued | JEFFREY MEAD |
| Floor/Roof Diaphrgm/Shear Wall | 1/7/2026 | Approved | JEFFREY MEAD |
| Green Building Rough | 1/7/2026 | Approved | JEFFREY MEAD |
| METHANE-Rough | 1/7/2026 | Approved | JEFFREY MEAD |
| PLUMBING-Rough | 1/7/2026 | Corrections Issued | JEFFREY MEAD |
| BUILDING-Rough-Frame | 1/13/2026 | Approved | RAUL BARAJAS |
| ELECTRICAL-Rough | 1/13/2026 | Partial Approval | RAUL BARAJAS |
| HVAC-Rough | 1/13/2026 | Partial Approval | RAUL BARAJAS |
| PLUMBING-Rough | 1/13/2026 | Partial Approval | RAUL BARAJAS |
| Insulation | 1/15/2026 | Approved | JOSH MEISTER |
| Interior/Exterior Lathing | 1/15/2026 | Partial Approval | JOSH MEISTER |
| Drywall Nailing | 1/28/2026 | Approved | JEFFREY MEAD |
| Interior/Exterior Lathing | 1/28/2026 | Approved | JEFFREY MEAD |
| Shower Pan | 1/28/2026 | Approved | JEFFREY MEAD |
| Final | 4/30/2026 | Corrections Issued | JEFFREY MEAD |
| Green Building Final | 4/30/2026 | Approved | JEFFREY MEAD |
| SGSOV-Seismic Gas S/O Valve | 4/30/2026 | SGSOV Approved | JEFFREY MEAD |
| Smoke Detectors | 4/30/2026 | Approved | JEFFREY MEAD |
| Final | 5/8/2026 | Partial Inspection | JEFFREY MEAD |