3103 S OAKHURST AVE 90034
Certificate Information: 3103 S OAKHURST AVE 90034
- Application / Permit
- 25016-10000-23814
- Plan Check / Job No.
- B25LA32382
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Interior remodel per engineer design
- Permit Issued
- Issued on 9/7/2025
- Issuing Office
- Current Status
- Permit Finaled on 12/1/2025
Permit Application Status History
| Submitted | 8/6/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 8/11/2025 | DANIEL SANJUAN |
| Corrections Issued | 8/12/2025 | DANIEL SANJUAN |
| Applicant returned to address corrections | 8/29/2025 | NGHI SU |
| Plan Check Approved | 9/4/2025 | NGHI SU |
| Issued | 9/7/2025 | APPLICANT |
| Permit Finaled | 12/1/2025 | EVAN COOPER |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 8/17/2025 | LANNY MERRICK |
| Address approval | Cleared | 9/3/2025 | ADRIAN SANCHEZ |
| Eng Process Fee Ord 176,300 | Cleared | 9/3/2025 | ADRIAN SANCHEZ |
Contact Information
| Contractor | Precision General Construction Inc; Lic. No.: 1030555-B | , |
| Engineer | Yang,, Di; Lic. No.: C92766 | 4005 CLIPPER CT FREMONT, CA 94538 |
Inspector Information
| ASHLEY THOMPSON, (310) 914-3897 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 9/9/2025 | Corrections Issued | ASHLEY THOMPSON |
| Footing/Foundation/Slab | 9/11/2025 | Approved | EVAN COOPER |
| ELECTRICAL-Rough | 9/19/2025 | Corrections Issued | ASHLEY THOMPSON |
| Floor/Roof Diaphrgm/Shear Wall | 9/19/2025 | Partial Approval | ASHLEY THOMPSON |
| PLUMBING-Rough | 9/19/2025 | Corrections Issued | ASHLEY THOMPSON |
| Shower Pan | 9/19/2025 | Not Ready for Inspection | ASHLEY THOMPSON |
| ELECTRICAL-Rough | 9/24/2025 | Approved | ASHLEY THOMPSON |
| HVAC-Rough | 9/24/2025 | Approved | ASHLEY THOMPSON |
| PLUMBING-Rough | 9/24/2025 | Approved | ASHLEY THOMPSON |
| Footing/Foundation/Slab | 9/30/2025 | Approved | EVAN COOPER |
| Insulation | 9/30/2025 | Corrections Issued | EVAN COOPER |
| Shower Pan | 9/30/2025 | Approved | EVAN COOPER |
| BUILDING-Rough-Frame | 10/14/2025 | Approved | ASHLEY THOMPSON |
| Drywall Nailing | 10/14/2025 | Approved | ASHLEY THOMPSON |
| Insulation | 10/14/2025 | Approved | ASHLEY THOMPSON |
| Interior/Exterior Lathing | 10/14/2025 | Approved | ASHLEY THOMPSON |
| ELECTRICAL-Final | 12/1/2025 | Approved | EVAN COOPER |
| Final | 12/1/2025 | Permit Finaled | EVAN COOPER |
| HVAC-Final | 12/1/2025 | Approved | EVAN COOPER |
| PLUMBING-Final | 12/1/2025 | Approved | EVAN COOPER |
| SGSOV-Seismic Gas S/O Valve | 12/1/2025 | SGSOV Approved | EVAN COOPER |
| Smoke Detectors | 12/1/2025 | Approved | EVAN COOPER |