1333 S 2ND AVE 90019
Certificate Information: 1333 S 2ND AVE 90019
- Application / Permit
- 25016-10000-23783
- Plan Check / Job No.
- B25LA32315
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- Eplan: Soft-Story seismic retrofit per LABC Chapter 93: Install Special Steel cantilevered column.
- Permit Issued
- Issued on 12/4/2025
- Issuing Office
- Current Status
- OK for CofC on 2/20/2026
Permit Application Status History
| Submitted | 8/5/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 8/7/2025 | VARAND SARKISIAN |
| Corrections Issued | 8/20/2025 | VARAND SARKISIAN |
| Quality Review Completed | 8/26/2025 | HANS SANTIAGO |
| Applicant returned to address corrections | 9/17/2025 | VARAND SARKISIAN |
| Applicant returned to address corrections | 10/17/2025 | VARAND SARKISIAN |
| Plan Check Approved | 11/4/2025 | VARAND SARKISIAN |
| Issued | 12/4/2025 | APPLICANT |
| OK for CofC | 2/20/2026 | MARTIN TAVITIAN |
Permit Application Clearance Information
| Address approval | Cleared | 10/14/2025 | XOCHITL ARQUIETA |
| Eng Process Fee Ord 176,300 | Cleared | 10/23/2025 | XOCHITL ARQUIETA |
| Tenant Habitability Plan | Cleared | 12/3/2025 | ARIC DEFUSCO |
Contact Information
| Contractor | Core General Contractors Corporation; Lic. No.: 1094631-B | , |
| Engineer | Deihimi,, Amir; Lic. No.: C78194 | 201 E SANDPOINTE AVE STE 400 SANTA ANA, CA 92707 |
Inspector Information
| DARRYL ARNOLD, (213) 482-0341 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Floor/Roof Diaphrgm/Shear Wall | 12/16/2025 | Approved | MARTIN TAVITIAN |
| Pre-Inspection | 12/16/2025 | Approved | MARTIN TAVITIAN |
| Wood Frame | 12/16/2025 | Approved | MARTIN TAVITIAN |
| Excavation/Setback/Form/Re-Bar | 1/2/2026 | Approved | DARRYL ARNOLD |
| Structural Steel Frame | 1/2/2026 | Approved | DARRYL ARNOLD |
| Deputy Reinf. Concrete | 1/5/2026 | Conditional Approval | DARRYL ARNOLD |
| Drywall Nailing | 1/13/2026 | Approved | ALFREDO LOPEZ |
| Final | 1/21/2026 | Not Ready for Inspection | DARRYL ARNOLD |
| SGSOV-Seismic Gas S/O Valve | 1/21/2026 | SGSOV Not Ready | DARRYL ARNOLD |
| Smoke Detectors | 1/21/2026 | Corrections Issued | DARRYL ARNOLD |
| Final | 2/20/2026 | OK for CofC | MARTIN TAVITIAN |
| SGSOV-Seismic Gas S/O Valve | 2/20/2026 | SGSOV Approved | MARTIN TAVITIAN |
| Smoke Detectors | 2/20/2026 | Approved | MARTIN TAVITIAN |