8382 S CHASE AVE 90045

Certificate Information: 8382 S CHASE AVE 90045

Application / Permit
25016-10000-23534
Plan Check / Job No.
B25LA31905
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
EPLAN: CONVERT (E) DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER GCS65852.2(e)(1)(A)
Permit Issued
Issued on 9/5/2025
Issuing Office
Current Status
CofO Issued on 1/17/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/1/2025 APPLICANT
Assigned to Plan Check Engineer 8/6/2025 GURUNATH NESARAJAH
Corrections Issued 8/7/2025 GURUNATH NESARAJAH
Plan Check Approved 9/3/2025 GURUNATH NESARAJAH
Issued 9/5/2025 APPLICANT
CofO in Progress 1/14/2026 JESUS PINEDA
Permit Finaled 1/17/2026 RICHARD STEINBACH
CofO Issued 1/17/2026 RICHARD STEINBACH
Permit Finaled 1/17/2026 RICHARD STEINBACH

Permit Application Clearance Information

Address approval Cleared 8/9/2025 COLIN LOREDO
Sewer availability Cleared 8/9/2025 COLIN LOREDO
Eng Process Fee Ord 176,300 Cleared 8/10/2025 DARIN LAM
Construction near power lines Cleared 8/11/2025 OSCAR CASTRO
ZI Cleared 8/22/2025 DAVID URITA

Contact Information

Architect Noteware,, Brian Arthur; Lic. No.: NA21514       ,
Contractor Unique Build Iskandar Construction Llc; Lic. No.: 1111731-B       ,

Inspector Information

MICHAEL LEWIS, (310) 914-3979 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 9/10/2025 Approved JESUS PINEDA
Special/Order Compliance 9/10/2025 Corrections Issued JESUS PINEDA
Footing/Foundation/Slab 9/22/2025 Approved JESUS PINEDA
PLUMBING-Rough 9/22/2025 Partial Approval JESUS PINEDA
ELECTRICAL-Rough 10/14/2025 Corrections Issued JESUS PINEDA
HVAC-Rough 10/14/2025 Approved JESUS PINEDA
PLUMBING-Rough 10/14/2025 Corrections Issued JESUS PINEDA
BUILDING-Rough-Frame 10/17/2025 Partial Approval JESUS PINEDA
ELECTRICAL-Rough 10/17/2025 Approved JESUS PINEDA
Insulation 10/17/2025 Partial Approval JESUS PINEDA
Interior/Exterior Lathing 10/17/2025 Partial Approval JESUS PINEDA
PLUMBING-Rough 10/17/2025 Approved JESUS PINEDA
BUILDING-Rough-Frame 10/22/2025 Approved JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 10/22/2025 Approved JESUS RODRIGUEZ
Green Building Rough 10/22/2025 Approved JESUS RODRIGUEZ
Insulation 10/22/2025 Approved JESUS RODRIGUEZ
Shower Pan 10/22/2025 Corrections Issued JESUS RODRIGUEZ
Drywall Nailing 10/27/2025 Corrections Issued TEMISTOCLES CAAL
Shower Pan 10/27/2025 Approved TEMISTOCLES CAAL
Drywall Nailing 12/3/2025 Approved JESUS PINEDA
ELECTRICAL-Final 12/3/2025 Corrections Issued JESUS PINEDA
Sewer 12/3/2025 Corrections Issued JESUS PINEDA
Sewer 12/5/2025 Approved JESUS PINEDA
Final 12/22/2025 Corrections Issued ANTHONY EGSON
Green Building Final 12/22/2025 Approved ANTHONY EGSON
SGSOV-Seismic Gas S/O Valve 12/22/2025 SGSOV Not Required ANTHONY EGSON
Smoke Detectors 12/22/2025 Not Ready for Inspection ANTHONY EGSON
Final 12/30/2025 Corrections Issued JESUS PINEDA
Smoke Detectors 12/30/2025 Approved JESUS PINEDA
Final 1/8/2026 Corrections Issued ANTHONY EGSON
HVAC-Final 1/8/2026 Approved ANTHONY EGSON
PLUMBING-Final 1/8/2026 Approved ANTHONY EGSON
ELECTRICAL-Final 1/14/2026 Approved JESUS PINEDA
Final 1/14/2026 OK to Issue CofO JESUS PINEDA