743 W 106TH ST 90044

Certificate Information: 743 W 106TH ST 90044

Application / Permit
25016-10000-23066
Plan Check / Job No.
B25LA31093
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
eplan. Convert existing detached garage to ADU per GC 66323(a)(1)
Permit Issued
Issued on 10/14/2025
Issuing Office
Current Status
Issued on 10/14/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 7/31/2025 APPLICANT
Assigned to Plan Check Engineer 8/4/2025 AUNG SOE
Corrections Issued 8/21/2025 AUNG SOE
Applicant returned to address corrections 8/29/2025 ADAM HEGAZI
Applicant returned to address corrections 10/9/2025 ZAW HAN
Plan Check Approved 10/10/2025 ZAW HAN
Issued 10/14/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 8/19/2025 DAVID LOPEZ
Sewer availability Cleared 8/19/2025 DAVID LOPEZ
Eng Process Fee Ord 176,300 Cleared 8/22/2025 DAVID LOPEZ
Construction near power lines Cleared 10/2/2025 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,
Engineer Espino,, Manuel A; Lic. No.: C55526 12109 WOODRUFF AVE      DOWNEY, CA 90241

Inspector Information

BEN MOLSTAD, (310) 732-4557 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 10/23/2025 Conditional Approval BEN MOLSTAD
PLUMBING-Rough 10/27/2025 Corrections Issued BEN MOLSTAD
PLUMBING-Rough 10/29/2025 Partial Approval BEN MOLSTAD
Footing/Foundation/Slab 10/31/2025 Conditional Approval JOSEPH MCGARRY
BUILDING-Rough-Frame 12/17/2025 Partial Inspection ARTHUR NEGRETE
Green Building Rough 12/17/2025 Not Ready for Inspection ARTHUR NEGRETE
ELECTRICAL-Rough 12/26/2025 No Access for Inspection ARTHUR NEGRETE
ELECTRICAL-Rough 12/29/2025 Corrections Issued BEN MOLSTAD
HVAC-Rough 12/29/2025 Corrections Issued BEN MOLSTAD
PLUMBING-Rough 12/29/2025 Corrections Issued BEN MOLSTAD
ELECTRICAL-Rough 12/31/2025 Corrections Issued BEN MOLSTAD
ELECTRICAL-Rough 3/31/2026 Corrections Issued BEN MOLSTAD
PLUMBING-Rough 3/31/2026 Corrections Issued BEN MOLSTAD
ELECTRICAL-Rough 4/6/2026 Not Ready for Inspection BEN MOLSTAD
HVAC-Rough 4/6/2026 Corrections Issued BEN MOLSTAD
BUILDING-Rough-Frame 4/10/2026 Approved JOSEPH MCGARRY
Green Building Rough 4/10/2026 Approved JOSEPH MCGARRY
Interior/Exterior Lathing 4/10/2026 Partial Approval JOSEPH MCGARRY
Rough-Elec/Plmb/HVAC 4/10/2026 Approved JOSEPH MCGARRY
BUILDING-Rough-Frame 4/17/2026 Corrections Issued BEN MOLSTAD
Insulation 4/17/2026 Corrections Issued BEN MOLSTAD
Drywall Nailing 4/20/2026 Corrections Issued BEN MOLSTAD
Insulation 4/20/2026 Approved BEN MOLSTAD
Drywall Nailing 4/27/2026 Approved BEN MOLSTAD
ELECTRICAL-Rough 4/27/2026 Partial Approval BEN MOLSTAD
BUILDING-Rough-Frame 6/11/2026 Approved BEN MOLSTAD
Final 6/11/2026 Corrections Issued BEN MOLSTAD
Green Building Final 6/11/2026 Not Ready for Inspection BEN MOLSTAD
SGSOV-Seismic Gas S/O Valve 6/11/2026 SGSOV Approved BEN MOLSTAD
Smoke Detectors 6/11/2026 Approved BEN MOLSTAD
Final 6/18/2026 Corrections Issued BEN MOLSTAD
Green Building Final 6/18/2026 Not Ready for Inspection BEN MOLSTAD
Final 6/23/2026 Corrections Issued BEN MOLSTAD
Green Building Final 6/23/2026 Approved BEN MOLSTAD