743 W 106TH ST 90044
Certificate Information: 743 W 106TH ST 90044
- Application / Permit
- 25016-10000-23066
- Plan Check / Job No.
- B25LA31093
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- eplan. Convert existing detached garage to ADU per GC 66323(a)(1)
- Permit Issued
- Issued on 10/14/2025
- Issuing Office
- Current Status
- Issued on 10/14/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 7/31/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 8/4/2025 | AUNG SOE |
| Corrections Issued | 8/21/2025 | AUNG SOE |
| Applicant returned to address corrections | 8/29/2025 | ADAM HEGAZI |
| Applicant returned to address corrections | 10/9/2025 | ZAW HAN |
| Plan Check Approved | 10/10/2025 | ZAW HAN |
| Issued | 10/14/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 8/19/2025 | DAVID LOPEZ |
| Sewer availability | Cleared | 8/19/2025 | DAVID LOPEZ |
| Eng Process Fee Ord 176,300 | Cleared | 8/22/2025 | DAVID LOPEZ |
| Construction near power lines | Cleared | 10/2/2025 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Espino,, Manuel A; Lic. No.: C55526 | 12109 WOODRUFF AVE DOWNEY, CA 90241 |
Inspector Information
| BEN MOLSTAD, (310) 732-4557 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 10/23/2025 | Conditional Approval | BEN MOLSTAD |
| PLUMBING-Rough | 10/27/2025 | Corrections Issued | BEN MOLSTAD |
| PLUMBING-Rough | 10/29/2025 | Partial Approval | BEN MOLSTAD |
| Footing/Foundation/Slab | 10/31/2025 | Conditional Approval | JOSEPH MCGARRY |
| BUILDING-Rough-Frame | 12/17/2025 | Partial Inspection | ARTHUR NEGRETE |
| Green Building Rough | 12/17/2025 | Not Ready for Inspection | ARTHUR NEGRETE |
| ELECTRICAL-Rough | 12/26/2025 | No Access for Inspection | ARTHUR NEGRETE |
| ELECTRICAL-Rough | 12/29/2025 | Corrections Issued | BEN MOLSTAD |
| HVAC-Rough | 12/29/2025 | Corrections Issued | BEN MOLSTAD |
| PLUMBING-Rough | 12/29/2025 | Corrections Issued | BEN MOLSTAD |
| ELECTRICAL-Rough | 12/31/2025 | Corrections Issued | BEN MOLSTAD |
| ELECTRICAL-Rough | 3/31/2026 | Corrections Issued | BEN MOLSTAD |
| PLUMBING-Rough | 3/31/2026 | Corrections Issued | BEN MOLSTAD |
| ELECTRICAL-Rough | 4/6/2026 | Not Ready for Inspection | BEN MOLSTAD |
| HVAC-Rough | 4/6/2026 | Corrections Issued | BEN MOLSTAD |
| BUILDING-Rough-Frame | 4/10/2026 | Approved | JOSEPH MCGARRY |
| Green Building Rough | 4/10/2026 | Approved | JOSEPH MCGARRY |
| Interior/Exterior Lathing | 4/10/2026 | Partial Approval | JOSEPH MCGARRY |
| Rough-Elec/Plmb/HVAC | 4/10/2026 | Approved | JOSEPH MCGARRY |
| BUILDING-Rough-Frame | 4/17/2026 | Corrections Issued | BEN MOLSTAD |
| Insulation | 4/17/2026 | Corrections Issued | BEN MOLSTAD |
| Drywall Nailing | 4/20/2026 | Corrections Issued | BEN MOLSTAD |
| Insulation | 4/20/2026 | Approved | BEN MOLSTAD |
| Drywall Nailing | 4/27/2026 | Approved | BEN MOLSTAD |
| ELECTRICAL-Rough | 4/27/2026 | Partial Approval | BEN MOLSTAD |
| BUILDING-Rough-Frame | 6/11/2026 | Approved | BEN MOLSTAD |
| Final | 6/11/2026 | Corrections Issued | BEN MOLSTAD |
| Green Building Final | 6/11/2026 | Not Ready for Inspection | BEN MOLSTAD |
| SGSOV-Seismic Gas S/O Valve | 6/11/2026 | SGSOV Approved | BEN MOLSTAD |
| Smoke Detectors | 6/11/2026 | Approved | BEN MOLSTAD |
| Final | 6/18/2026 | Corrections Issued | BEN MOLSTAD |
| Green Building Final | 6/18/2026 | Not Ready for Inspection | BEN MOLSTAD |
| Final | 6/23/2026 | Corrections Issued | BEN MOLSTAD |
| Green Building Final | 6/23/2026 | Approved | BEN MOLSTAD |