1558 W 214TH ST 90501
Certificate Information: 1558 W 214TH ST 90501
- Application / Permit
- 25016-10000-23029
- Plan Check / Job No.
- B25LA30999
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Remodel of existing SFD. consisting of 4 bedroom, 3 bath, kitchen, laundry.
- Permit Issued
- Issued on 8/27/2025
- Issuing Office
- Metro
- Current Status
- Issued on 8/27/2025
Permit Application Status History
| Submitted | 7/26/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 7/30/2025 | ROSENDO MEDINA |
| Corrections Issued | 7/30/2025 | ROSENDO MEDINA |
| Applicant returned to address corrections | 8/5/2025 | ROSENDO MEDINA |
| Plan Check Approved | 8/7/2025 | NAREG ATARIAN |
| Issued | 8/27/2025 | APPLICANT |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 8/6/2025 | MICHAEL BROWN |
| Sewer availability | Cleared | 8/6/2025 | MICHAEL BROWN |
Contact Information
| Contractor | Paramount Construction Inc; Lic. No.: 1080565-B | 11801 GARFIELD AVE SOUTH GATE, CA 90280 |
| Engineer | Ramirez, Cid, Jose Carlos; Lic. No.: C91046 | 5164 N RATON CIR LONG BEACH, CA 90807 |
Inspector Information
| EUGENE CASSIDY, (310) 548-2508 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 9/22/2025 | Partial Approval | EUGENE CASSIDY |
| Deputy Other (see comments) | 9/22/2025 | Partial Approval | EUGENE CASSIDY |
| Footing/Foundation/Slab | 9/23/2025 | Approved | EUGENE CASSIDY |
| PLUMBING-Rough | 11/7/2025 | Approved | EUGENE CASSIDY |
| Floor/Roof Diaphrgm/Shear Wall | 11/12/2025 | Not Ready for Inspection | EUGENE CASSIDY |
| Floor/Roof Diaphrgm/Shear Wall | 11/19/2025 | Not Ready for Inspection | BEN MOLSTAD |
| Floor/Roof Diaphrgm/Shear Wall | 11/26/2025 | Partial Approval | BEN MOLSTAD |
| Rough-Elec/Plmb/HVAC | 12/16/2025 | Corrections Issued | EUGENE CASSIDY |
| Wood Frame | 12/16/2025 | Not Ready for Inspection | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 12/18/2025 | Partial Approval | EUGENE CASSIDY |
| ELECTRICAL-Rough | 12/18/2025 | Approved | EUGENE CASSIDY |
| HVAC-Rough | 12/18/2025 | Approved | EUGENE CASSIDY |
| Interior/Exterior Lathing | 1/5/2026 | Partial Approval | EUGENE CASSIDY |
| Insulation | 1/21/2026 | Approved | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 1/22/2026 | Approved | EUGENE CASSIDY |
| Floor/Roof Diaphrgm/Shear Wall | 1/22/2026 | Approved | EUGENE CASSIDY |
| Interior/Exterior Lathing | 1/27/2026 | Approved | EUGENE CASSIDY |
| Shower Pan | 1/27/2026 | Not Ready for Inspection | EUGENE CASSIDY |
| Drywall Nailing | 1/28/2026 | Approved | EUGENE CASSIDY |
| Shower Pan | 1/28/2026 | Approved | EUGENE CASSIDY |