5029 W MELROSE AVE 90038
Certificate Information: 5029 W MELROSE AVE 90038
- Application / Permit
- 25016-10000-22995
- Plan Check / Job No.
- B25LA30969
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (16) Retail
- Work Description
- INTERIOR T.I. OF (E) RETAIL SPACE TO A CLOTHING RETAIL SHOP (URM BUILDING).
- Permit Issued
- Issued on 10/14/2025
- Issuing Office
- Valley
- Current Status
- Permit Finaled on 4/10/2026
Permit Application Status History
| Submitted | 7/25/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 7/29/2025 | LUKE GONZALES |
| Corrections Issued | 7/29/2025 | LUKE GONZALES |
| Building Plans Picked Up | 8/5/2025 | APPLICANT |
| Plan Check Approved | 8/28/2025 | MINA HABILI |
| Issued | 10/14/2025 | APPLICANT |
| Permit Finaled | 4/10/2026 | LUIS CCAMACHO |
Permit Application Clearance Information
| Historic Resource Verification | Cleared | 8/28/2025 | DAVID URITA |
| Redevelopment Project Area | Cleared | 8/28/2025 | DAVID URITA |
Contact Information
| Contractor | Saran Group Development; Lic. No.: 1105674-B | 4825 ARCOLA AVE NORTH HOLLYWOOD, CA 91601 |
| Engineer | Kwei,, Peter; Lic. No.: C72100 | 1306 N HAWTHORN WY AZUSA, CA 91702 |
Inspector Information
| TIMOTHY POWELL, (213) 482-0360 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 10/17/2025 | Approved | TIMOTHY POWELL |
| Final | 3/26/2026 | Not Ready for Inspection | REGINA MENDEZ |
| SGSOV-Seismic Gas S/O Valve | 3/26/2026 | SGSOV Not Ready | REGINA MENDEZ |
| Smoke Detectors | 3/26/2026 | Not Ready for Inspection | REGINA MENDEZ |
| Final | 4/10/2026 | Permit Finaled | LUIS CCAMACHO |
| SGSOV-Seismic Gas S/O Valve | 4/10/2026 | SGSOV Approved | LUIS CCAMACHO |
| Smoke Detectors | 4/10/2026 | Approved | LUIS CCAMACHO |