3204 W WELDON AVE 90065

Certificate Information: 3204 W WELDON AVE 90065

Application / Permit
25016-10000-22868
Plan Check / Job No.
B25LA30762
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
EPLAN CONVERSION OF EXISITING UNPERMITTED DETACHED GARAGE ( PRIOR TO JANUARY 1, 2020) TO ADU. See Comment.
Permit Issued
Issued on 9/10/2025
Issuing Office
Current Status
CofO in Progress on 6/5/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 7/24/2025 APPLICANT
Assigned to Plan Check Engineer 7/29/2025 TSE MING HUANG
Corrections Issued 7/29/2025 TSE MING HUANG
Applicant returned to address corrections 8/26/2025 TSE MING HUANG
Plan Check Approved 9/9/2025 TSE MING HUANG
Issued 9/10/2025 APPLICANT
CofO in Progress 6/5/2026 NICHOLAS LOPEZ

Permit Application Clearance Information

Address approval Cleared 8/12/2025 CELINA MORENO
Sewer availability Cleared 8/12/2025 CELINA MORENO
Eng Process Fee Ord 176,300 Cleared 8/13/2025 CELINA MORENO
Supp. Use District POD/CDO/TDO Cleared 8/14/2025 ANDREA MAGANA-WITHERS

Contact Information

Contractor Owner-Builder       ,
Engineer Sandoval,, Martin; Lic. No.: C56905 12761 DAIRY ST      EASTVALE, CA 92880

Inspector Information

NICHOLAS LOPEZ, (213) 202-3224 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 12/22/2025 Partial Approval DAVID WILLIAMS
Underground Mechanical 12/22/2025 Partial Approval DAVID WILLIAMS
Footing/Foundation/Slab 1/5/2026 Approved NICHOLAS LOPEZ
BUILDING-Rough-Frame 2/12/2026 Not Ready for Inspection NICHOLAS LOPEZ
Floor/Roof Diaphrgm/Shear Wall 2/12/2026 Corrections Issued NICHOLAS LOPEZ
Green Building Rough 2/12/2026 Not Ready for Inspection NICHOLAS LOPEZ
Floor/Roof Diaphrgm/Shear Wall 2/17/2026 Approved NICHOLAS LOPEZ
Interior/Exterior Lathing 2/17/2026 Approved NICHOLAS LOPEZ
BUILDING-Rough-Frame 2/18/2026 Approved NICHOLAS LOPEZ
Green Building Rough 2/18/2026 Approved NICHOLAS LOPEZ
Rough-Elec/Plmb/HVAC 2/18/2026 Approved NICHOLAS LOPEZ
Insulation 2/20/2026 Approved NICHOLAS LOPEZ
ELECTRICAL-Rough 2/25/2026 Approved NICHOLAS LOPEZ
PLUMBING-Rough 2/25/2026 Approved NICHOLAS LOPEZ
Drywall Nailing 3/16/2026 Approved RONNIE MEDINA
Interior/Exterior Lathing 3/16/2026 Approved RONNIE MEDINA
ELECTRICAL-Final 6/3/2026 Corrections Issued NICHOLAS LOPEZ
Final 6/3/2026 Corrections Issued NICHOLAS LOPEZ
Green Building Final 6/3/2026 Corrections Issued NICHOLAS LOPEZ
HVAC-Final 6/3/2026 Corrections Issued NICHOLAS LOPEZ
PLUMBING-Final 6/3/2026 Corrections Issued NICHOLAS LOPEZ
SGSOV-Seismic Gas S/O Valve 6/3/2026 SGSOV No Gas NICHOLAS LOPEZ
Service/Power Release 6/3/2026 Not Ready for Inspection NICHOLAS LOPEZ
Smoke Detectors 6/3/2026 Approved NICHOLAS LOPEZ
ELECTRICAL-Final 6/5/2026 Approved NICHOLAS LOPEZ
Final 6/5/2026 OK to Issue CofO NICHOLAS LOPEZ
Green Building Final 6/5/2026 Approved NICHOLAS LOPEZ
HVAC-Final 6/5/2026 Approved NICHOLAS LOPEZ
PLUMBING-Final 6/5/2026 Approved NICHOLAS LOPEZ
Service/Power Release 6/5/2026 Approved NICHOLAS LOPEZ