8750-8752 N QUARTZ AVE 91324
Certificate Information: 8750-8752 N QUARTZ AVE 91324
- Application / Permit
- 25016-10000-22815
- Plan Check / Job No.
- B25LA30675
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ePlan CONVERT (E) ATTACHED GARAGE AND PORTION OF SFD TO (N) ACCESSORY DWELLING UNIT PER GC 66323(a)(1).
- Permit Issued
- Issued on 10/7/2025
- Issuing Office
- Current Status
- Issued on 10/7/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 7/24/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 7/29/2025 | ISIS ARGUETA |
| Corrections Issued | 7/30/2025 | ISIS ARGUETA |
| Applicant returned to address corrections | 8/5/2025 | ISIS ARGUETA |
| Applicant returned to address corrections | 8/12/2025 | LUISANGEL VALENZUELA |
| Plan Check Approved | 8/13/2025 | ISIS ARGUETA |
| Issued | 10/7/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 8/6/2025 | SAFA JAVANMARDI |
| Eng Process Fee Ord 176,300 | Cleared | 8/6/2025 | SAFA JAVANMARDI |
| Sewer availability | Cleared | 8/6/2025 | SAFA JAVANMARDI |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JEFFREY HARTLINE, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRIS CHRISTENSEN, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 1/29/2026 | Partial Approval | JEFFREY HARTLINE |
| Footing/Foundation/Slab | 2/4/2026 | Approved | CHRIS CHRISTENSEN |
| PLUMBING-Rough | 2/4/2026 | Partial Approval | CHRIS CHRISTENSEN |
| BUILDING-Rough-Frame | 2/11/2026 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Green Building Rough | 2/11/2026 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| BUILDING-Rough-Frame | 2/24/2026 | Corrections Issued | CHRIS CHRISTENSEN |
| Green Building Rough | 2/24/2026 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Deputy Wood Construction | 2/26/2026 | Conditional Approval | CHRIS CHRISTENSEN |
| BUILDING-Rough-Frame | 3/3/2026 | Partial Approval | CHRIS CHRISTENSEN |
| Green Building Rough | 3/3/2026 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| ELECTRICAL-Rough | 3/31/2026 | Approved | CHRIS CHRISTENSEN |
| HVAC-Rough | 3/31/2026 | Approved | CHRIS CHRISTENSEN |
| PLUMBING-Rough | 3/31/2026 | Approved | CHRIS CHRISTENSEN |