20512 W SATICOY ST 91306
Certificate Information: 20512 W SATICOY ST 91306
- Application / Permit
- 25016-10000-22308
- Plan Check / Job No.
- B25VN19204
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN: Existing detached garage converted into an Accessory Dwelling Unit per GCS 66323(a)(1).
- Permit Issued
- Issued on 10/7/2025
- Issuing Office
- Current Status
- CofO in Progress on 3/17/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 7/10/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 7/17/2025 | ALEXANDER JOO |
| Assigned to Zoning Architect | 7/17/2025 | MELISSA QUINONES |
| Corrections Issued | 7/19/2025 | ALEXANDER JOO |
| Quality Review Completed | 7/21/2025 | GARO TELMI |
| Applicant returned to address corrections | 8/26/2025 | ALEXANDER JOO |
| Applicant returned to address corrections | 9/9/2025 | ALEXANDER JOO |
| Applicant returned to address corrections | 10/2/2025 | ALEXANDER JOO |
| Applicant returned to address corrections | 10/6/2025 | ALEXANDER JOO |
| Plan Check Approved | 10/7/2025 | ALEXANDER JOO |
| Issued | 10/7/2025 | APPLICANT |
| CofO in Progress | 3/17/2026 | ALEXANDER HANDY |
Permit Application Clearance Information
| Address approval | Cleared | 7/29/2025 | DAVID LOPEZ |
| Sewer availability | Cleared | 7/29/2025 | DAVID LOPEZ |
| Eng Process Fee Ord 176,300 | Cleared | 7/30/2025 | DAVID LOPEZ |
| Zoning Plan Check | Cleared | 10/6/2025 | MELISSA QUINONES |
Contact Information
| Architect | Bertha, Olmos; Lic. No.: C35995 | , |
| Contractor | Owner-Builder | , |
| Engineer | Lambert,, Will A; Lic. No.: S5430 | 223 E THOUSAND OAKS BLVD304 THOUSAND OAKS, CA 91360 |
Inspector Information
| ALEXANDER HANDY, (818) 774-4317 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 10/16/2025 | Corrections Issued | ALEXANDER HANDY |
| PLUMBING-Rough | 10/16/2025 | Partial Approval | ALEXANDER HANDY |
| Footing/Foundation/Slab | 10/20/2025 | Approved | ALEXANDER HANDY |
| BUILDING-Rough-Frame | 11/18/2025 | Not Ready for Inspection | ARUTYUN MADATYAN |
| ELECTRICAL-Rough | 11/18/2025 | Approved | ARUTYUN MADATYAN |
| Green Building Rough | 11/18/2025 | Not Ready for Inspection | ARUTYUN MADATYAN |
| HVAC-Rough | 11/18/2025 | Approved | ARUTYUN MADATYAN |
| PLUMBING-Rough | 11/18/2025 | Approved | ARUTYUN MADATYAN |
| BUILDING-Rough-Frame | 12/8/2025 | Approved | ALEXANDER HANDY |
| Green Building Rough | 12/8/2025 | Approved | ALEXANDER HANDY |
| Interior/Exterior Lathing | 12/8/2025 | Partial Approval | ALEXANDER HANDY |
| Wood Frame | 12/8/2025 | Approved | ALEXANDER HANDY |
| Deputy Wood Construction | 12/9/2025 | Conditional Approval | ROBERT GOLD |
| Insulation | 12/11/2025 | Approved | DAVID SCANTLIN |
| Interior/Exterior Lathing | 12/11/2025 | Approved | DAVID SCANTLIN |
| Drywall Nailing | 12/16/2025 | Approved | TROY SANDERS |
| ELECTRICAL-Final | 3/10/2026 | Not Ready for Inspection | ALEXANDER HANDY |
| Final | 3/10/2026 | Corrections Issued | ALEXANDER HANDY |
| Green Building Final | 3/10/2026 | Not Ready for Inspection | ALEXANDER HANDY |
| HVAC-Final | 3/10/2026 | Not Ready for Inspection | ALEXANDER HANDY |
| PLUMBING-Final | 3/10/2026 | Not Ready for Inspection | ALEXANDER HANDY |
| SGSOV-Seismic Gas S/O Valve | 3/10/2026 | SGSOV No Gas | ALEXANDER HANDY |
| Service/Power Release | 3/10/2026 | Not Required | ALEXANDER HANDY |
| Smoke Detectors | 3/10/2026 | Approved | ALEXANDER HANDY |
| ELECTRICAL-Final | 3/16/2026 | Approved | ALEXANDER HANDY |
| Final | 3/16/2026 | OK to Issue CofO | ALEXANDER HANDY |
| Green Building Final | 3/16/2026 | Approved | ALEXANDER HANDY |
| HVAC-Final | 3/16/2026 | Approved | ALEXANDER HANDY |
| PLUMBING-Final | 3/16/2026 | Approved | ALEXANDER HANDY |
| Service/Power Release | 3/16/2026 | Not Required | ALEXANDER HANDY |