1330 W 35TH PL 90007
Certificate Information: 1330 W 35TH PL 90007
- Application / Permit
- 25016-10000-21801
- Plan Check / Job No.
- B25LA26972
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- ePlan: CONVERT (E) ADDTACHED GARAGE TO ATTACHED ADU PER STATE LAW BUILDING B 2 OF 4
- Permit Issued
- Issued on 8/11/2025
- Issuing Office
- Current Status
- Issued on 8/11/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 6/30/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 7/10/2025 | KHUONG TRUONG |
| Corrections Issued | 7/16/2025 | KHUONG TRUONG |
| Quality Review Completed | 7/23/2025 | PRANITA SHAH |
| Plan Check Approved | 8/7/2025 | KHUONG TRUONG |
| Issued | 8/11/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 7/28/2025 | MICHAEL BROWN |
| Eng Process Fee Ord 176,300 | Cleared | 7/28/2025 | MICHAEL BROWN |
| Sewer availability | Cleared | 7/28/2025 | MICHAEL BROWN |
Contact Information
| Contractor | Emerald Builders And Developers; Lic. No.: 1068007-B | , |
| Engineer | Salto,, Alvaro; Lic. No.: C83859 | 2543 E NORMAN AVE WEST COVINA, CA 91791 |
Inspector Information
| SABAS ALONSO, (213) 202-3468 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 9/19/2025 | Approved | SABAS ALONSO |
| Underground Mechanical | 9/19/2025 | Approved | SABAS ALONSO |
| ELECTRICAL-Rough | 10/16/2025 | Approved | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 10/16/2025 | Approved | SABAS ALONSO |
| HVAC-Rough | 10/16/2025 | Approved | SABAS ALONSO |
| PLUMBING-Rough | 10/16/2025 | Approved | SABAS ALONSO |
| BUILDING-Rough-Frame | 10/30/2025 | Approved | SABAS ALONSO |
| Green Building Rough | 10/30/2025 | Approved | SABAS ALONSO |
| Insulation | 10/30/2025 | Approved | SABAS ALONSO |
| Interior/Exterior Lathing | 10/30/2025 | Partial Approval | SABAS ALONSO |
| Insulation | 11/5/2025 | Approved | SABAS ALONSO |
| Drywall Nailing | 3/6/2026 | Approved | SABAS ALONSO |
| Final | 3/13/2026 | Corrections Issued | SABAS ALONSO |
| Green Building Final | 3/13/2026 | Approved | SABAS ALONSO |
| SGSOV-Seismic Gas S/O Valve | 3/13/2026 | SGSOV Approved | SABAS ALONSO |
| Smoke Detectors | 3/13/2026 | Approved | SABAS ALONSO |
| Final | 3/24/2026 | Not Ready for Inspection | SABAS ALONSO |