10590 W VERONA AVE 90025

Certificate Information: 10590 W VERONA AVE 90025

Application / Permit
25016-10000-21613
Plan Check / Job No.
B25LA28887
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERSION OF EXISTING REC ROOM OVER 2 CAR GARAGE INTO ADU.
Permit Issued
Issued on 10/9/2025
Issuing Office
Metro
Current Status
CofO Issued on 12/30/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/14/2025 APPLICANT
Assigned to Plan Check Engineer 7/17/2025 FERNANDO FLORES
Corrections Issued 7/19/2025 FERNANDO FLORES
Building Plans Picked Up 7/22/2025 APPLICANT
Applicant returned to address corrections 9/16/2025 DANIEL YIP
Plan Check Approved 10/9/2025 CRISTINA SALAZAR
Issued 10/9/2025 APPLICANT
CofO in Progress 12/25/2025 CARLOS MATAMOROS
Permit Finaled 12/30/2025 RICHARD STEINBACH
CofO Issued 12/30/2025 RICHARD STEINBACH
Permit Finaled 12/30/2025 RICHARD STEINBACH

Permit Application Clearance Information

Sewer availability Cleared 7/26/2025 JESUS CISNEROS
Eng Process Fee Ord 176,300 Cleared 8/12/2025 JESUS CISNEROS
Address approval Cleared 8/15/2025 JESUS CISNEROS
Construction near power lines Cleared 10/6/2025 RIDWAN HARDY

Contact Information

Architect Abramson,, Trevor David; Lic. No.: C17597 5171 W JEFFERSON BLVD.      LOS ANGELES, CA 90016
Contractor Owner-Builder       ,

Inspector Information

DAVID SCANTLIN, (310) 914-3863 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

ELECTRICAL-Rough 10/16/2025 Not Ready for Inspection DANIEL VERA
Interior/Exterior Lathing 10/16/2025 Partial Approval DANIEL VERA
PLUMBING-Rough 10/16/2025 Corrections Issued DANIEL VERA
PLUMBING-Rough 10/17/2025 Approved DANIEL VERA
Shower Pan 10/17/2025 Approved DANIEL VERA
HVAC-Rough 10/20/2025 Approved DANIEL VERA
Interior/Exterior Lathing 10/20/2025 Approved DANIEL VERA
Drywall Nailing 10/21/2025 Approved DANIEL VERA
BUILDING-Rough-Frame 12/12/2025 Approved CARLOS MATAMOROS
Final 12/12/2025 Corrections Issued CARLOS MATAMOROS
METHANE-Final 12/12/2025 Approved CARLOS MATAMOROS
METHANE-Rough 12/12/2025 Approved CARLOS MATAMOROS
Smoke Detectors 12/12/2025 Approved CARLOS MATAMOROS
ELECTRICAL-Final 12/24/2025 Approved CARLOS MATAMOROS
Final 12/24/2025 OK to Issue CofO CARLOS MATAMOROS
HVAC-Rough 12/24/2025 Approved CARLOS MATAMOROS
PLUMBING-Final 12/24/2025 Approved CARLOS MATAMOROS