2806-2808 S BARRINGTON AVE 90064
Certificate Information: 2806-2808 S BARRINGTON AVE 90064
- Application / Permit
- 25016-10000-21579
- Plan Check / Job No.
- B25LA28815
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- ePlan: Attached garage conversion to ADU per GC 66323(a)(3) in an (E) 2-story duplex.
- Permit Issued
- Issued on 10/6/2025
- Issuing Office
- Current Status
- CofO Issued on 5/6/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/14/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 7/16/2025 | DAVID CASTILLO |
| Corrections Issued | 7/17/2025 | DAVID CASTILLO |
| Applicant returned to address corrections | 8/25/2025 | DAVID CASTILLO |
| Applicant returned to address corrections | 9/2/2025 | ALFREDO JARA |
| Applicant returned to address corrections | 9/17/2025 | DAVID CASTILLO |
| Applicant returned to address corrections | 9/23/2025 | DAVID CASTILLO |
| Applicant returned to address corrections | 10/1/2025 | HOOMAN HAJIZADEH |
| Plan Check Approved | 10/6/2025 | HOOMAN HAJIZADEH |
| Issued | 10/6/2025 | APPLICANT |
| CofO in Progress | 4/28/2026 | EVAN COOPER |
| Permit Finaled | 5/6/2026 | RICHARD STEINBACH |
| CofO Issued | 5/6/2026 | RICHARD STEINBACH |
| Permit Finaled | 5/6/2026 | RICHARD STEINBACH |
Permit Application Clearance Information
| Address approval | Cleared | 7/18/2025 | BIAINA HARITUNIAN |
| Sewer availability | Cleared | 7/18/2025 | BIAINA HARITUNIAN |
| Hold | Cleared | 8/27/2025 | MARIA VENDIVIL |
| Eng Process Fee Ord 176,300 | Cleared | 9/9/2025 | JEREMY CHOK |
Contact Information
| Architect | Winslow,, David Stephen; Lic. No.: C21932 | 253 WALLER SAN FRANCISCO, CA 94102 |
| Contractor | Owner-Builder | , |
| Engineer | Garcia,, Ramon; Lic. No.: S4595 | 732 HOLBERTSON COURT SIMI VALLEY, CA 93065 |
Inspector Information
| KIRK SANDERS, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARAM AVEDISIAN, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 10/9/2025 | Corrections Issued | KIRK SANDERS |
| Pre-Inspection | 10/16/2025 | No Access for Inspection | KIRK SANDERS |
| Pre-Inspection | 10/17/2025 | Corrections Issued | KIRK SANDERS |
| BUILDING-Rough-Frame | 11/17/2025 | No Access for Inspection | KIRK SANDERS |
| ELECTRICAL-Rough | 11/17/2025 | No Access for Inspection | KIRK SANDERS |
| Green Building Rough | 11/17/2025 | No Access for Inspection | KIRK SANDERS |
| PLUMBING-Rough | 11/17/2025 | No Access for Inspection | KIRK SANDERS |
| Pre-Inspection | 11/17/2025 | No Access for Inspection | KIRK SANDERS |
| ELECTRICAL-Rough | 11/20/2025 | Corrections Issued | MICHAEL ALLEN |
| HVAC-Rough | 11/20/2025 | Corrections Issued | MICHAEL ALLEN |
| PLUMBING-Rough | 11/20/2025 | Corrections Issued | MICHAEL ALLEN |
| Pre-Inspection | 11/20/2025 | Corrections Issued | MICHAEL ALLEN |
| ELECTRICAL-Rough | 12/16/2025 | Corrections Issued | KIRK SANDERS |
| HVAC-Rough | 12/16/2025 | Partial Approval | KIRK SANDERS |
| PLUMBING-Final | 12/16/2025 | Corrections Issued | KIRK SANDERS |
| PLUMBING-Rough | 12/16/2025 | Corrections Issued | KIRK SANDERS |
| ELECTRICAL-Rough | 12/24/2025 | Approved | KIRK SANDERS |
| Gas Test | 12/24/2025 | Approved | KIRK SANDERS |
| HVAC-Rough | 12/24/2025 | Approved | KIRK SANDERS |
| PLUMBING-Rough | 12/24/2025 | Approved | KIRK SANDERS |
| Insulation | 2/10/2026 | Not Ready for Inspection | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 2/17/2026 | Partial Approval | RUBEN RIVAS |
| Green Building Rough | 2/17/2026 | Not Ready for Inspection | RUBEN RIVAS |
| Interior/Exterior Lathing | 2/17/2026 | Corrections Issued | RUBEN RIVAS |
| Insulation | 2/20/2026 | Approved | ARAM AVEDISIAN |
| Interior/Exterior Lathing | 2/20/2026 | Partial Approval | ARAM AVEDISIAN |
| Drywall Nailing | 2/24/2026 | Approved | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 3/12/2026 | Approved | ARAM AVEDISIAN |
| ELECTRICAL-Final | 3/12/2026 | Not Ready for Inspection | ARAM AVEDISIAN |
| Final | 3/12/2026 | Corrections Issued | ARAM AVEDISIAN |
| Green Building Final | 3/12/2026 | Approved | ARAM AVEDISIAN |
| Green Building Rough | 3/12/2026 | Approved | ARAM AVEDISIAN |
| HVAC-Final | 3/12/2026 | Not Ready for Inspection | ARAM AVEDISIAN |
| PLUMBING-Final | 3/12/2026 | Not Ready for Inspection | ARAM AVEDISIAN |
| Smoke Detectors | 3/12/2026 | Approved | ARAM AVEDISIAN |
| ELECTRICAL-Final | 4/16/2026 | Not Ready for Inspection | EUGENE CASSIDY |
| Final | 4/16/2026 | Corrections Issued | EUGENE CASSIDY |
| HVAC-Final | 4/16/2026 | Not Ready for Inspection | EUGENE CASSIDY |
| PLUMBING-Final | 4/16/2026 | Not Ready for Inspection | EUGENE CASSIDY |
| ELECTRICAL-Final | 4/28/2026 | Approved | EVAN COOPER |
| Final | 4/28/2026 | OK to Issue CofO | EVAN COOPER |
| HVAC-Final | 4/28/2026 | Approved | EVAN COOPER |
| PLUMBING-Final | 4/28/2026 | Approved | EVAN COOPER |
| Service/Power Release | 4/28/2026 | Approved | EVAN COOPER |