4035 W LEEWARD AVE 90005
Certificate Information: 4035 W LEEWARD AVE 90005
- Application / Permit
- 25016-10000-21490
- Plan Check / Job No.
- B25LA28672
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT EXISTING DETACHED GARAGE TO AN ADU. INTERIOR ALTERATION INCLUDING FINISHES AT HABITABLE ATTIC. STRUCTURAL ALTERATIONS TO (E) FRAMING AND FOUNDATION PER GC 66323(a)(1
- Permit Issued
- Issued on 2/27/2026
- Issuing Office
- Metro
- Current Status
- Issued on 2/27/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 7/11/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 7/15/2025 | NEHEMIAS RAMOS |
| Corrections Issued | 7/16/2025 | NEHEMIAS RAMOS |
| Applicant returned to address corrections | 12/15/2025 | SHANGQIN XIE |
| Plan Check Approved | 2/10/2026 | JOHN MESIAS |
| Issued | 2/27/2026 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 8/2/2025 | DERRICK MAGEE |
| Sewer availability | Cleared | 8/2/2025 | DERRICK MAGEE |
| Eng Process Fee Ord 176,300 | Cleared | 8/4/2025 | DERRICK MAGEE |
| HPOZ | Cleared | 8/13/2025 | MICAELA TORRES-GIL |
| Miscellaneous | Cleared | 8/13/2025 | MICAELA TORRES-GIL |
| Specific Plan | Cleared | 8/28/2025 | NEHEMIAS RAMOS |
| Construction near power lines | Cleared | 9/26/2025 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JEFFREY MEAD, (213) 202-3240 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 3/3/2026 | Approved | JEFFREY MEAD |
| Footing/Foundation/Slab | 3/26/2026 | Approved | JEFFREY MEAD |
| Footing/Foundation/Slab | 4/14/2026 | Approved | RONNIE MINDANAO |
| ELECTRICAL-Rough | 5/27/2026 | Approved | JEFFREY MEAD |
| PLUMBING-Rough | 5/27/2026 | Approved | JEFFREY MEAD |
| BUILDING-Rough-Frame | 5/29/2026 | Approved | JEFFREY MEAD |
| Green Building Rough | 5/29/2026 | Approved | JEFFREY MEAD |
| HVAC-Rough | 5/29/2026 | Approved | JEFFREY MEAD |