6329 S 10TH AVE 90043
Certificate Information: 6329 S 10TH AVE 90043
- Application / Permit
- 25016-10000-21133
- Plan Check / Job No.
- B25LA28080
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- Eplan: Soft-Story seismic retrofit per LABC Chapter 93: RETROFIT SOFT STORY OPEN FRONT PARKING GARAGE WITH LIVING UNITS ABOVE AT THIS COMPLEX IN ACCORDANCE WITH THE NEW SOFT STORY (DIV. '93) ORDINANCE - 183893 - RETROFIT ( ADD (N)-(2) SPECIAL CANTILEVERED COLUMNS)
- Permit Issued
- Issued on 10/21/2025
- Issuing Office
- Current Status
- Issued on 10/21/2025
Permit Application Status History
| Submitted | 7/8/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 7/16/2025 | VARAND SARKISIAN |
| Corrections Issued | 7/23/2025 | VARAND SARKISIAN |
| Quality Review Completed | 8/5/2025 | HANS SANTIAGO |
| Plan Check Approved | 8/20/2025 | VARAND SARKISIAN |
| Issued | 10/21/2025 | APPLICANT |
Permit Application Clearance Information
| Tenant Habitability Plan | Cleared | 9/16/2025 | KORNEL LELEA |
Contact Information
| Contractor | Titan Contracting Services Inc; Lic. No.: 976552-B | 13434 RAYMER STREET NORTH HOLLYWOOD, CA 91605 |
| Engineer | Ding,, Wenzhuo; Lic. No.: C82891 | 5205 SUNNY POINT PL RANCHO PALOS VERDES, CA 90275 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 10/31/2025 | Corrections Issued | DARRYL ARNOLD |
| Pre-Inspection | 10/31/2025 | Approved | DARRYL ARNOLD |
| Structural Steel Frame | 10/31/2025 | Conditional Approval | DARRYL ARNOLD |
| Wood Frame | 10/31/2025 | Conditional Approval | DARRYL ARNOLD |
| Interior/Exterior Lathing | 11/5/2025 | Approved | DARRYL ARNOLD |
| Final | 11/13/2025 | Not Ready for Inspection | DARRYL ARNOLD |
| SGSOV-Seismic Gas S/O Valve | 11/13/2025 | SGSOV Not Ready | DARRYL ARNOLD |
| Smoke Detectors | 11/13/2025 | Corrections Issued | DARRYL ARNOLD |
| Final | 11/20/2025 | Not Ready for Inspection | DARRYL ARNOLD |
| SGSOV-Seismic Gas S/O Valve | 11/20/2025 | SGSOV Not Ready | DARRYL ARNOLD |
| Smoke Detectors | 11/20/2025 | Corrections Issued | DARRYL ARNOLD |
| Special/Order Compliance | 1/16/2026 | Conditional Approval | DARRYL ARNOLD |