5541-5541 1/2 E TEMPLETON ST 90032
Certificate Information: 5541-5541 1/2 E TEMPLETON ST 90032
- Application / Permit
- 25016-10000-20828
- Plan Check / Job No.
- B25LA27525
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- EPLAN: CONVERT PORTION OF (E) DWELLING TO JADU PER GC 66323(a)(1) and 66333
- Permit Issued
- Issued on 11/6/2025
- Issuing Office
- Current Status
- Permit Finaled on 5/26/2026
Permit Application Status History
| Submitted | 8/8/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 8/12/2025 | NGHI SU |
| Corrections Issued | 8/13/2025 | NGHI SU |
| Applicant returned to address corrections | 10/23/2025 | NGHI SU |
| Plan Check Approved | 10/24/2025 | NGHI SU |
| Issued | 11/6/2025 | APPLICANT |
| Permit Finaled | 5/22/2026 | LILIANA PORTILLO |
Permit Application Clearance Information
| Address approval | Cleared | 9/17/2025 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 9/17/2025 | LEE GUILBEAUX |
| Sewer availability | Cleared | 9/17/2025 | LEE GUILBEAUX |
| Grading Pre-Inspection | Cleared | 10/6/2025 | MICHAEL TEMPLE |
Contact Information
| Contractor | Jorgensen - Reeve Builders Inc; Lic. No.: 876216-B | , |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 1/8/2026 | Approved | LILIANA PORTILLO |
| ELECTRICAL-Rough | 1/8/2026 | Approved | LILIANA PORTILLO |
| HVAC-Rough | 1/8/2026 | Approved | LILIANA PORTILLO |
| PLUMBING-Rough | 1/8/2026 | Approved | LILIANA PORTILLO |
| Insulation | 1/15/2026 | Approved | LILIANA PORTILLO |
| Drywall Nailing | 1/16/2026 | Approved | GEM DE OCAMPO |
| Shower Pan | 1/16/2026 | Approved | GEM DE OCAMPO |
| Interior/Exterior Lathing | 1/21/2026 | Approved | LILIANA PORTILLO |
| ELECTRICAL-Final | 2/18/2026 | Not Ready for Inspection | LILIANA PORTILLO |
| Final | 2/18/2026 | Corrections Issued | LILIANA PORTILLO |
| HVAC-Final | 2/18/2026 | Not Ready for Inspection | LILIANA PORTILLO |
| PLUMBING-Final | 2/18/2026 | Not Ready for Inspection | LILIANA PORTILLO |
| SGSOV-Seismic Gas S/O Valve | 2/18/2026 | SGSOV Not Ready | LILIANA PORTILLO |
| Smoke Detectors | 2/18/2026 | Approved | LILIANA PORTILLO |
| ELECTRICAL-Final | 2/20/2026 | Approved | LILIANA PORTILLO |
| Final | 2/20/2026 | Not Ready for Inspection | LILIANA PORTILLO |
| HVAC-Final | 2/20/2026 | Approved | LILIANA PORTILLO |
| PLUMBING-Final | 2/20/2026 | Approved | LILIANA PORTILLO |
| SGSOV-Seismic Gas S/O Valve | 2/20/2026 | SGSOV Approved | LILIANA PORTILLO |
| Service/Power Release | 2/20/2026 | Approved | LILIANA PORTILLO |
| Final | 2/26/2026 | Corrections Issued | LILIANA PORTILLO |
| Final | 5/14/2026 | Not Ready for Inspection | LILIANA PORTILLO |
| Final | 5/22/2026 | Permit Finaled | LILIANA PORTILLO |