5541-5541 1/2 E TEMPLETON ST 90032

Certificate Information: 5541-5541 1/2 E TEMPLETON ST 90032

Application / Permit
25016-10000-20828
Plan Check / Job No.
B25LA27525
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
EPLAN: CONVERT PORTION OF (E) DWELLING TO JADU PER GC 66323(a)(1) and 66333
Permit Issued
Issued on 11/6/2025
Issuing Office
Current Status
Permit Finaled on 5/26/2026

Permit Application Status History

Submitted 8/8/2025 APPLICANT
Assigned to Plan Check Engineer 8/12/2025 NGHI SU
Corrections Issued 8/13/2025 NGHI SU
Applicant returned to address corrections 10/23/2025 NGHI SU
Plan Check Approved 10/24/2025 NGHI SU
Issued 11/6/2025 APPLICANT
Permit Finaled 5/22/2026 LILIANA PORTILLO

Permit Application Clearance Information

Address approval Cleared 9/17/2025 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 9/17/2025 LEE GUILBEAUX
Sewer availability Cleared 9/17/2025 LEE GUILBEAUX
Grading Pre-Inspection Cleared 10/6/2025 MICHAEL TEMPLE

Contact Information

Contractor Jorgensen - Reeve Builders Inc; Lic. No.: 876216-B       ,

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 1/8/2026 Approved LILIANA PORTILLO
ELECTRICAL-Rough 1/8/2026 Approved LILIANA PORTILLO
HVAC-Rough 1/8/2026 Approved LILIANA PORTILLO
PLUMBING-Rough 1/8/2026 Approved LILIANA PORTILLO
Insulation 1/15/2026 Approved LILIANA PORTILLO
Drywall Nailing 1/16/2026 Approved GEM DE OCAMPO
Shower Pan 1/16/2026 Approved GEM DE OCAMPO
Interior/Exterior Lathing 1/21/2026 Approved LILIANA PORTILLO
ELECTRICAL-Final 2/18/2026 Not Ready for Inspection LILIANA PORTILLO
Final 2/18/2026 Corrections Issued LILIANA PORTILLO
HVAC-Final 2/18/2026 Not Ready for Inspection LILIANA PORTILLO
PLUMBING-Final 2/18/2026 Not Ready for Inspection LILIANA PORTILLO
SGSOV-Seismic Gas S/O Valve 2/18/2026 SGSOV Not Ready LILIANA PORTILLO
Smoke Detectors 2/18/2026 Approved LILIANA PORTILLO
ELECTRICAL-Final 2/20/2026 Approved LILIANA PORTILLO
Final 2/20/2026 Not Ready for Inspection LILIANA PORTILLO
HVAC-Final 2/20/2026 Approved LILIANA PORTILLO
PLUMBING-Final 2/20/2026 Approved LILIANA PORTILLO
SGSOV-Seismic Gas S/O Valve 2/20/2026 SGSOV Approved LILIANA PORTILLO
Service/Power Release 2/20/2026 Approved LILIANA PORTILLO
Final 2/26/2026 Corrections Issued LILIANA PORTILLO
Final 5/14/2026 Not Ready for Inspection LILIANA PORTILLO
Final 5/22/2026 Permit Finaled LILIANA PORTILLO