4722 S LINCOLN BLVD 90292

Certificate Information: 4722 S LINCOLN BLVD 90292

Application / Permit
25016-10000-20560
Plan Check / Job No.
B25LA27131
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(13) Bath - Turkish or the like
Work Description
CHANGE OF USE FROM BEAUTY SALON TO SPA . THE SCOPE OF WORK INCLUDES AN INTERIOR TENANT IMPROVEMENT FOR AN EXISTING SPACE. WORK INCLUDES INSTALLATION OF NEW INTERIOR PARTITIONS, FINISHES, FIXTURES, FURNITURE, CASEWORK, MILLWORK, AND EQUIPMENT. WORK ALSO INCLUDES MECHANICAL, ELECTRICAL, AND PLUMBING UNDER SEPARATE PERMIT. NO STRUCTURAL BEARING OR SHEAR WALLS WILL BE REMOVED. NOT ADDING SQUARE FEET.
Permit Issued
Issued on 2/2/2026
Issuing Office
Current Status
CofO Issued on 5/15/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/1/2025 APPLICANT
Assigned to Plan Check Engineer 7/3/2025 KAVIAN REFAHI
Corrections Issued 7/3/2025 KAVIAN REFAHI
Applicant returned to address corrections 12/23/2025 KAVIAN REFAHI
Plan Check Approved 1/6/2026 KAVIAN REFAHI
Issued 2/2/2026 APPLICANT
CofO in Progress 5/14/2026 DANIEL ARMENTA
Permit Finaled 5/15/2026 VASIL MIHALEV
CofO Issued 5/15/2026 VASIL MIHALEV
Permit Finaled 5/15/2026 VASIL MIHALEV

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 9/30/2025 CINDY QI
Sewer availability Cleared 9/30/2025 CINDY QI
"Q" conditions Cleared 10/1/2025 JAZMIN ROQUE
Comm Cor/Mini-Mall Cleared 10/1/2025 JAZMIN ROQUE
Comm Cor/Mini-Mall Cleared 10/1/2025 JAZMIN ROQUE
Comm Cor/Mini-Mall Cleared 10/1/2025 JAZMIN ROQUE
ZA Case Cleared 10/1/2025 JAZMIN ROQUE
Coastal Zone Cleared 12/3/2025 JAZMIN ROQUE
Specific Plan Cleared 12/12/2025 PEDRO AYALA

Contact Information

Contractor Wcs-Williams Construction Services; Lic. No.: 360147-B       ,
Contractor Williams Patrick J; Lic. No.: 360147-B       ,
Engineer Phan,, Ben; Lic. No.: C57550 10822 WOODWARD LANE      GARDEN GROVE, CA 92840

Inspector Information

DANIEL ARMENTA, (310) 914-3925 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Light Gage Steel Frame 3/12/2026 Approved DANIEL ARMENTA
Pre-Inspection 3/12/2026 Partial Approval DANIEL ARMENTA
Insulation 3/16/2026 Approved DANIEL ARMENTA
Insulation 3/18/2026 Approved DANIEL VARNUM
Wood Frame 3/18/2026 Approved DANIEL VARNUM
Drywall Nailing 3/26/2026 Partial Approval DANIEL ARMENTA
Pre-Inspection 3/26/2026 Not Ready for Inspection DANIEL ARMENTA
Drywall Nailing 4/1/2026 Approved DANIEL ARMENTA
Partition/T-Bar Ceiling 4/20/2026 Partial Approval DANIEL ARMENTA
Partition/T-Bar Ceiling 4/21/2026 Approved DANIEL ARMENTA
Final 5/8/2026 Not Ready for Inspection DANIEL ARMENTA
METHANE-Final 5/8/2026 Approved DANIEL ARMENTA
METHANE-Rough 5/8/2026 Approved DANIEL ARMENTA
Pre-Inspection 5/8/2026 Not Ready for Inspection DANIEL ARMENTA
Reinforced Masonry Frame 5/8/2026 Not Ready for Inspection DANIEL ARMENTA
SGSOV-Seismic Gas S/O Valve 5/8/2026 SGSOV Approved DANIEL ARMENTA
Smoke Detectors 5/8/2026 Approved DANIEL ARMENTA
Final 5/11/2026 Not Ready for Inspection DANIEL ARMENTA
Masonry Wall/Backfill 5/11/2026 Approved DANIEL ARMENTA
Final 5/12/2026 OK to Issue CofO DANIEL ARMENTA