9126 N VAN NUYS BLVD 91402
Certificate Information: 9126 N VAN NUYS BLVD 91402
- Application / Permit
- 25016-10000-19907
- Plan Check / Job No.
- B25LA26055
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (17) Restaurant - Take Out
- Work Description
- CHANGE OF USE FROM RETAIL TO TAKE-OUT RESTAURANT. NO DINING AREA PROPOSED.
- Permit Issued
- Issued on 11/18/2025
- Issuing Office
- Metro
- Current Status
- Issued on 11/18/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 6/24/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 6/27/2025 | LUKE GONZALES |
| Corrections Issued | 6/28/2025 | LUKE GONZALES |
| Building Plans Picked Up | 6/30/2025 | APPLICANT |
| Plan Check Approved | 9/18/2025 | ZAW HAN |
| Issued | 11/18/2025 | APPLICANT |
Permit Application Clearance Information
| "Q" conditions | Cleared | 7/11/2025 | DAVID URITA |
| ZA Case | Cleared | 7/11/2025 | DAVID URITA |
| ZA Case | Cleared | 7/11/2025 | DAVID URITA |
| Public Works-Highway Ded. | Cleared | 7/13/2025 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 7/15/2025 | LEE GUILBEAUX |
| Sewer availability | Cleared | 7/15/2025 | LEE GUILBEAUX |
| Food Service Establishment | Cleared | 8/28/2025 | CRYSTOL BRANDT |
| ZA Case | Cleared | 8/29/2025 | ALEX VELA |
| ZA Case | Cleared | 8/29/2025 | ALEX VELA |
| Food establishment approval | Cleared | 9/12/2025 | LACDHS APPROVED |
Contact Information
| Contractor | Btb Construction Inc; Lic. No.: 1122168-B | 16040 SUGARPINE LN CERRITOS, CA 90703 |
| Engineer | Kim,, Hong Kook; Lic. No.: C64529 | 3600 WILSHIRE BLVD STE 1903 LOS ANGELES, CA 90010 |
Inspector Information
| ANDREW DORSO, (818) 374-7520 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 12/22/2025 | Approved | DEANDRE HOFFMAN |
| Light Gage Steel Frame | 2/13/2026 | Partial Approval | JEFFREY DURAN |
| Drywall Nailing | 2/27/2026 | Not Ready for Inspection | ANDREW DORSO |
| Light Gage Steel Frame | 2/27/2026 | Not Ready for Inspection | ANDREW DORSO |
| Light Gage Steel Frame | 3/5/2026 | Partial Approval | JOHN KITCKO |
| Drywall Nailing | 3/11/2026 | Approved | ANDREW DORSO |
| Light Gage Steel Frame | 3/11/2026 | Approved | ANDREW DORSO |
| T-Bar Ceiling | 7/2/2026 | No Access for Inspection | RAFAEL CORTES |
| T-Bar Ceiling | 7/8/2026 | Partial Inspection | DEANDRE HOFFMAN |