3828 W SUNSET BLVD 100-110 90026
Certificate Information: 3828 W SUNSET BLVD 100-110 90026
- Application / Permit
- 25016-10000-19421
- Plan Check / Job No.
- B25LA25368
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (16) Secondhand Store
- Work Description
- EPLAN. TENANT IMPROVEMENT FOR EXISTING SECONDHAND STORE (UNIT 110) EXPANDING INTO ADJACENT TENANT SPACE (UNIT 100). CHANGE OF USE FROM RETAIL TO SECONDHAND STORE.
- Permit Issued
- Issued on 7/31/2025
- Issuing Office
- Current Status
- CofO Issued on 1/21/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/17/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 6/23/2025 | ADAM HEGAZI |
| Corrections Issued | 6/24/2025 | ADAM HEGAZI |
| Applicant returned to address corrections | 7/17/2025 | ZAW HAN |
| Plan Check Approved | 7/30/2025 | ADAM HEGAZI |
| Issued | 7/31/2025 | APPLICANT |
| CofO in Progress | 1/2/2026 | JEROME BLACKWOOD |
| CofO in Progress | 1/21/2026 | LUIS CCAMACHO |
| Permit Finaled | 1/21/2026 | ERNESTO CORRAL |
| CofO Issued | 1/21/2026 | ERNESTO CORRAL |
| Permit Finaled | 1/21/2026 | ERNESTO CORRAL |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 7/15/2025 | DAVID LOPEZ |
| Sewer availability | Cleared | 7/15/2025 | DAVID LOPEZ |
| "Q" conditions | Cleared | 7/16/2025 | FIPE LEILUA |
| ZA Case | Cleared | 7/16/2025 | FIPE LEILUA |
Contact Information
| Architect | Wick,, David Sochu; Lic. No.: NA29199 | , |
| Contractor | Ramirez Ricky; Lic. No.: 800586-B | , |
Inspector Information
| TIMOTHY POWELL, (213) 482-0360 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 10/14/2025 | Partial Inspection | LUIS CCAMACHO |
| Light Gage Steel Frame | 10/24/2025 | Partial Approval | LUIS CCAMACHO |
| Structural Steel Frame | 10/24/2025 | Not Ready for Inspection | LUIS CCAMACHO |
| Drywall Nailing | 11/7/2025 | Partial Approval | LUIS CCAMACHO |
| Final | 12/17/2025 | Partial Inspection | LUIS CCAMACHO |
| SGSOV-Seismic Gas S/O Valve | 12/17/2025 | SGSOV Approved | LUIS CCAMACHO |
| Smoke Detectors | 12/17/2025 | Approved | LUIS CCAMACHO |
| Wood Frame | 12/17/2025 | Approved | LUIS CCAMACHO |
| Final | 12/23/2025 | OK to Issue CofO | JEROME BLACKWOOD |
| Final | 12/26/2025 | Partial Approval | LUIS CCAMACHO |