15350 W SHERMAN WAY 91406

Certificate Information: 15350 W SHERMAN WAY 91406

Application / Permit
25016-10000-19205
Plan Check / Job No.
B25LA25060
Group
Building
Type
Bldg-Addition
Sub-Type
Commercial
Primary Use
(22) Storage Building
Work Description
CHANGE OF USE FROM EXISTING 4 STORY RETAIL AND OFFICE TO SELF STORAGE WITH ACCESSORY RETAIL USES WITH ADDITION
Permit Issued
Issued on 3/16/2026
Issuing Office
Current Status
Issued on 3/16/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 6/16/2025 APPLICANT
Assigned to Plan Check Engineer 6/18/2025 SINA KHOSRAVI
Assigned to Zoning Architect 6/20/2025 KRISTEL MARQUEZ
Corrections Issued 6/23/2025 SINA KHOSRAVI
Disabled Access Plans Picked Up 6/27/2025 APPLICANT
Quality Review Completed 6/30/2025 KEN GILL
Building Plans Picked Up 7/7/2025 APPLICANT
Applicant returned to address corrections 3/2/2026 SINA KHOSRAVI
Plan Check Approved 3/4/2026 SINA KHOSRAVI
Issued 3/16/2026 APPLICANT

Permit Application Clearance Information

Sewer availability Cleared 9/5/2025 JOHN LIN
Eng Process Fee Ord 176,300 Cleared 9/9/2025 JOHN LIN
CPC Cleared 9/17/2025 ROSALINDA MEZA
Miscellaneous Cleared 9/17/2025 ROSALINDA MEZA
Miscellaneous Cleared 9/17/2025 ROSALINDA MEZA
Miscellaneous Cleared 9/17/2025 ROSALINDA MEZA
Miscellaneous Cleared 9/17/2025 ROSALINDA MEZA
ZA Case Cleared 9/17/2025 ROSALINDA MEZA
ZA Case Cleared 9/17/2025 ROSALINDA MEZA
ZA Case Cleared 9/17/2025 ROSALINDA MEZA
ZA Case Cleared 9/17/2025 ROSALINDA MEZA
ZA Case Cleared 9/17/2025 ROSALINDA MEZA
ZA Case Cleared 9/17/2025 ROSALINDA MEZA
Low Impact Development (LID) Cleared 10/23/2025 MARTIN FRAGOSO
DAS Clearance Cleared 12/9/2025 SHINE LIN
Green Code Cleared 1/7/2026 MICHAEL MARTINEZ
"Q" conditions Cleared 1/16/2026 ROSALINDA MEZA
Miscellaneous Cleared 1/16/2026 ROSALINDA MEZA
ZA Case Cleared 1/16/2026 ROSALINDA MEZA
Zoning Plan Check Cleared 2/17/2026 SINA KHOSRAVI

Contact Information

Architect Kubicek,, Robert Warren; Lic. No.: C20245 2233 E THOMAS RD      PHOENIX, AZ 85015
Contractor R C I Builders Inc; Lic. No.: 835114-B 2985 E HILLCREST DR #107      THOUSAND OAKS, CA 91362
Engineer Blunck,, Jerome Jon; Lic. No.: GE151 3595 OLD CONEJO ROAD      THOUSAND OAKS, CA 91320
Engineer Elder,, John; Lic. No.: S6534 5181 S EMERALD PL      CHANDLER, AZ 85249

Inspector Information

BRIAN KELLY, (818) 374-1127 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

Deputy Steel/Welding 7/24/2026   
Deputy Reinf. Concrete 7/27/2026   
Deputy Reinf. Concrete 7/27/2026   

Inspection Request History

Pre-Inspection 3/25/2026 Corrections Issued BRIAN KELLY
Pre-Inspection 4/6/2026 Corrections Issued BRIAN KELLY
Footing/Foundation/Slab 4/24/2026 Partial Approval BRIAN KELLY
Grading Pre-Inspection 4/27/2026 Partial Inspection BRIAN KELLY
Footing/Foundation/Slab 5/6/2026 Partial Inspection JOHN KITCKO
Deputy Drilled-In Anchors 5/15/2026 Conditional Approval BRIAN KELLY
Footing/Foundation/Slab 5/19/2026 Conditional Approval JEFFREY DURAN
Excavation/Setback/Form/Re-Bar 5/21/2026 Partial Approval BRIAN KELLY
Deputy Reinf. Concrete 5/22/2026 Conditional Approval BRIAN KELLY
Deputy Drilled-In Anchors 5/27/2026 Conditional Approval JEFFREY DURAN
Footing/Foundation/Slab 5/28/2026 Partial Approval JEFFREY DURAN
Deputy Reinf. Concrete 5/29/2026 Conditional Approval BRIAN KELLY
Footing/Foundation/Slab 6/1/2026 Partial Approval BRIAN KELLY
Deputy Drilled-In Anchors 6/9/2026 Conditional Approval BRIAN KELLY
Deputy Reinf. Concrete 6/11/2026 Conditional Approval BRIAN KELLY
Footing/Foundation/Slab 6/12/2026 Partial Approval BRIAN KELLY
Deputy Other (see comments) 6/16/2026 Conditional Approval BRIAN KELLY
Deputy Reinf. Concrete 6/16/2026 Conditional Approval BRIAN KELLY
Footing/Foundation/Slab 6/24/2026 Partial Approval BRIAN KELLY
Deputy Reinf. Concrete 6/25/2026 Conditional Approval BRIAN KELLY
Deputy Steel/Welding 6/25/2026 Conditional Approval BRIAN KELLY
Deputy Drilled-In Anchors 6/29/2026 Conditional Approval BRIAN KELLY
Deputy Steel/Welding 6/29/2026 Conditional Approval BRIAN KELLY
Deputy Steel/Welding 6/30/2026 Conditional Approval BRIAN KELLY
Footing/Foundation/Slab 6/30/2026 Partial Approval BRIAN KELLY
Deputy Reinf. Concrete 7/1/2026 Conditional Approval BRIAN KELLY
Deputy Steel/Welding 7/6/2026 Conditional Approval BRIAN KELLY
Structural Steel Frame 7/14/2026 Partial Inspection DEANDRE HOFFMAN
Deputy Wood Construction 7/16/2026 Conditional Approval BRIAN KELLY
Deputy Steel/Welding 7/22/2026 Conditional Approval BRIAN KELLY
Light Gage Steel Frame 7/22/2026 Not Ready for Inspection BRIAN KELLY
Deputy Steel/Welding 7/23/2026 Conditional Approval BRIAN KELLY
Footing/Foundation/Slab 7/23/2026 Partial Inspection BRIAN KELLY