1726 S WESTERN AVE 90006

Certificate Information: 1726 S WESTERN AVE 90006

Application / Permit
25016-10000-19007
Plan Check / Job No.
B25LA24791
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(13) Medical Office
Work Description
TENANT IMPROVEMENT AND CHANGE OF USE FROM (E) TAKE-OUT RESTAURANT TO DENTAL OFFICE.
Permit Issued
Issued on 9/10/2025
Issuing Office
Metro
Current Status
CofO Issued on 4/8/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/13/2025 APPLICANT
Assigned to Plan Check Engineer 6/18/2025 MINA HABILI
Corrections Issued 6/19/2025 MINA HABILI
Building Plans Picked Up 6/25/2025 APPLICANT
Applicant returned to address corrections 7/22/2025 CARLOS MONTES
Plan Check Approved 9/8/2025 DANIEL YIP
Issued 9/10/2025 APPLICANT
CofO in Progress 4/7/2026 JEROME BLACKWOOD
Permit Finaled 4/8/2026 ERNESTO CORRAL
CofO Issued 4/8/2026 ERNESTO CORRAL
Permit Finaled 4/8/2026 ERNESTO CORRAL

Permit Application Clearance Information

CPC Cleared 7/7/2025 DORIAN AGUILAR
HPOZ Cleared 7/7/2025 DORIAN AGUILAR
Community Plan Implem. Overlay Cleared 7/15/2025 MANERI ROMAN
Eng Process Fee Ord 176,300 Cleared 7/22/2025 TREVOR QUAN
Sewer availability Cleared 7/22/2025 TREVOR QUAN
Miscellaneous approval Cleared 9/8/2025 LACDHS APPROVED

Contact Information

Contractor Buffalo T J Construction Inc; Lic. No.: 1053384-B 8162 4TH STREET #42      BUENA PARK, CA 90621
Engineer Yu,, Kunyoung; Lic. No.: C66880 22812 ERIEL AVE      TORRANCE, CA 90505

Inspector Information

JEROME BLACKWOOD, (213) 213-5353 Office Hours: 7:00-8:00 AM MON-FRI
REGINA MENDEZ, (213) 213-5353 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 10/24/2025 Approved CHRISTOPHER BLACKWOOD
Light Gage Steel Frame 12/8/2025 Not Ready for Inspection JEROME BLACKWOOD
Light Gage Steel Frame 12/15/2025 Partial Approval JEROME BLACKWOOD
Drywall Nailing 12/18/2025 Partial Approval ALFREDO LOPEZ
T-Bar Ceiling 1/8/2026 Partial Approval CHRISTOPHER BLACKWOOD
Final 4/2/2026 Not Ready for Inspection JEROME BLACKWOOD
Light Gage Steel Frame 4/2/2026 Approved JEROME BLACKWOOD
METHANE-Final 4/2/2026 Approved JEROME BLACKWOOD
METHANE-Rough 4/2/2026 Approved JEROME BLACKWOOD
SGSOV-Seismic Gas S/O Valve 4/2/2026 SGSOV Approved JEROME BLACKWOOD
Smoke Detectors 4/2/2026 Approved JEROME BLACKWOOD
Final 4/6/2026 OK to Issue CofO JEROME BLACKWOOD
SGSOV-Seismic Gas S/O Valve 4/6/2026 SGSOV Approved JEROME BLACKWOOD
Wood Frame 4/6/2026 Approved JEROME BLACKWOOD