12180 W VENTURA BLVD 91604
Certificate Information: 12180 W VENTURA BLVD 91604
- Application / Permit
- 25016-10000-18663
- Plan Check / Job No.
- B25LA24235
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (17) Coffee Shop
- Work Description
- ePlan. Change of use from retail to cookie shop with T.I. to include new service counter, new accessible rest-room and kitchen equipment. (1,096 sf)
- Permit Issued
- Issued on 10/14/2025
- Issuing Office
- Current Status
- CofO Issued on 2/25/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/12/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 6/17/2025 | REZA HAGHIGHAT |
| Corrections Issued | 6/18/2025 | REZA HAGHIGHAT |
| Applicant returned to address corrections | 7/28/2025 | REZA HAGHIGHAT |
| Plan Check Approved | 9/29/2025 | REZA HAGHIGHAT |
| Issued | 10/14/2025 | APPLICANT |
| CofO in Progress | 2/25/2026 | DEANDRE HOFFMAN |
| Permit Finaled | 2/25/2026 | JEFFREY DURAN |
| CofO Issued | 2/25/2026 | JEFFREY DURAN |
| Permit Finaled | 2/25/2026 | JEFFREY DURAN |
Permit Application Clearance Information
| Comm Cor/Mini-Mall | Cleared | 7/23/2025 | ASHLEY RODARTE |
| Miscellaneous | Cleared | 7/23/2025 | STEVEN WECHSLER |
| ZA Case | Cleared | 7/23/2025 | ASHLEY RODARTE |
| Eng Process Fee Ord 176,300 | Cleared | 7/28/2025 | MICHAEL BROWN |
| Food establishment approval | Cleared | 7/28/2025 | LACDHS APPROVED |
| Sewer availability | Cleared | 7/28/2025 | MICHAEL BROWN |
| Specific Plan | Cleared | 7/28/2025 | JOANNA MARROQUIN |
| Specific Plan | Cleared | 7/29/2025 | MIGUEL CRISOSTOMO |
Contact Information
| Contractor | M&D Construction Inc; Lic. No.: 1127450-B | , |
Inspector Information
| JEFFREY FULTON, (818) 374-1132 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Light Gage Steel Frame | 12/1/2025 | Partial Approval | RAFAEL CORTES |
| Drywall Nailing | 12/4/2025 | Approved | KENNETH ROBERTS |
| Special/Order Compliance | 12/4/2025 | Partial Inspection | REGINA MENDEZ |
| Final | 2/11/2026 | Not Ready for Inspection | JEFFREY FULTON |
| SGSOV-Seismic Gas S/O Valve | 2/11/2026 | SGSOV Not Ready | JEFFREY FULTON |
| Smoke Detectors | 2/11/2026 | Not Ready for Inspection | JEFFREY FULTON |
| Wood Frame | 2/11/2026 | Not Ready for Inspection | JEFFREY FULTON |
| Final | 2/12/2026 | OK to Issue CofO | JEFFREY FULTON |
| SGSOV-Seismic Gas S/O Valve | 2/12/2026 | SGSOV Approved | JEFFREY FULTON |
| Smoke Detectors | 2/12/2026 | Approved | JEFFREY FULTON |
| Wood Frame | 2/12/2026 | Approved | JEFFREY FULTON |
| Pre-Inspection | 2/13/2026 | Partial Inspection | DEANDRE HOFFMAN |