1038 N EL MEDIO AVE 90272
Certificate Information: 1038 N EL MEDIO AVE 90272
- Application / Permit
- 25016-10000-18644
- Plan Check / Job No.
- B25LA24194
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- **2025 Wildfire Eligible Project*** 1ST FLOOR AND 2ND REMODEL. KITCHEN, BATHROOM REMODELS, STAIR, WINDOWS AND DOORS REPLACEMENT TO (E) SFD.
- Permit Issued
- Issued on 4/14/2026
- Issuing Office
- Current Status
- Issued on 4/14/2026
Permit Application Status History
| Submitted | 6/10/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 6/11/2025 | FERNANDO FLORES |
| Corrections Issued | 6/11/2025 | FERNANDO FLORES |
| Plan Check Approved | 7/5/2025 | FERNANDO FLORES |
| No Progress | 1/28/2026 | LUKE GONZALES |
| Plan Check Approved | 2/20/2026 | LUKE GONZALES |
| Issued | 4/14/2026 | APPLICANT |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Baldwin Builders; Lic. No.: 992380-B | , |
| Contractor | Baldwin Plumbing Inc; Lic. No.: 992380-B | , |
| Engineer | Arakelyan,, Aram; Lic. No.: C82796 | 145 S GLENOAKS BI 328 BURBANK, CA 91502 |
Inspector Information
| DANIEL VERA, (213) 577-9924 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 4/16/2026 | Conditional Approval | JUAN VALENZUELA |
| Footing/Foundation/Slab | 4/16/2026 | Corrections Issued | BOBBY KEY |
| BUILDING-Rough-Frame | 6/25/2026 | Corrections Issued | MICHAEL ALLEN |
| ELECTRICAL-Rough | 6/25/2026 | Corrections Issued | MICHAEL ALLEN |
| Gas Test | 6/25/2026 | Approved | MICHAEL ALLEN |
| Interior/Exterior Lathing | 6/25/2026 | Approved | MICHAEL ALLEN |
| PLUMBING-Rough | 6/25/2026 | Corrections Issued | MICHAEL ALLEN |
| Insulation | 7/13/2026 | Not Ready for Inspection | DANIEL VERA |
| ELECTRICAL-Rough | 7/14/2026 | Approved | ARAM AVEDISIAN |
| PLUMBING-Rough | 7/14/2026 | Approved | ARAM AVEDISIAN |
| Deputy Drilled-In Anchors | 7/20/2026 | No Result Entered | JUAN VALENZUELA |
| Deputy Wood Construction | 7/20/2026 | No Result Entered | JUAN VALENZUELA |
| Drywall Nailing | 7/20/2026 | Approved | DANIEL VERA |
| Insulation | 7/20/2026 | Approved | DANIEL VERA |