4979 W WASHINGTON BLVD 90016
Certificate Information: 4979 W WASHINGTON BLVD 90016
- Application / Permit
- 25016-10000-18591
- Plan Check / Job No.
- B25LA24124
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (16) Grocery Store
- Work Description
- CHANGE OF USE FROM RETAIL TO GROCERY MARKET
- Permit Issued
- Issued on 4/1/2026
- Issuing Office
- Current Status
- Issued on 4/1/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 6/12/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 6/12/2025 | HERNAN ARREOLA |
| Corrections Issued | 6/17/2025 | HERNAN ARREOLA |
| Assigned to Zoning Architect | 6/20/2025 | BENNY WONG |
| Quality Review Completed | 6/24/2025 | GARO TELMI |
| Plan Check Approved | 3/25/2026 | HERNAN ARREOLA |
| Issued | 4/1/2026 | APPLICANT |
Permit Application Clearance Information
| DAS Clearance | Cleared | 6/30/2025 | Samuel Gonzalez |
| "D" conditions | Cleared | 8/5/2025 | ASHLEY RODARTE |
| Miscellaneous | Cleared | 8/5/2025 | ASHLEY RODARTE |
| ZA Case | Cleared | 8/5/2025 | ASHLEY RODARTE |
| ZA Case | Cleared | 8/5/2025 | ASHLEY RODARTE |
| Eng Process Fee Ord 176,300 | Cleared | 9/8/2025 | JEREMY CHOK |
| Sewer availability | Cleared | 9/8/2025 | JEREMY CHOK |
| Historic Resource Verification | Cleared | 9/18/2025 | RAFAEL FONTES |
| Community Plan Implem. Overlay | Cleared | 12/4/2025 | ISAIAH ROSS |
| Redevelopment Project Area | Cleared | 12/8/2025 | YASMINE BASHIRI |
| Zoning Plan Check | Cleared | 2/19/2026 | BENNY WONG |
| Food establishment approval | Cleared | 3/25/2026 | LACDHS APPROVED |
Contact Information
| Contractor | Nemo & Rami Inc; Lic. No.: 1011948-B | 1930 W HOLT AVENUE POMONA, CA 91768 |
| Engineer | Tagudar,, Fred; Lic. No.: NA33612 | , |
Inspector Information
| IAN BLINN, (213) 482-7361 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRISTOPHER BLACKWOOD, (213) 482-7361 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 5/19/2026 | Partial Inspection | CHRISTOPHER BLACKWOOD |
| Drywall Nailing | 5/28/2026 | Approved | DARRYL ARNOLD |
| Drywall Nailing | 5/29/2026 | Conditional Approval | DARRYL ARNOLD |