14959 W GREENLEAF ST 91403

Certificate Information: 14959 W GREENLEAF ST 91403

Application / Permit
25016-10000-18406
Plan Check / Job No.
B25LA23796
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan: CONVERT (E) GARAGE AND STORAGE TO ACCESSORY DWELLING UNIT WITH PATIO COVER PER ORDINANCE
Permit Issued
Issued on 7/19/2025
Issuing Office
Current Status
CofO Issued on 5/28/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/9/2025 APPLICANT
Assigned to Plan Check Engineer 6/12/2025 DANIEL YIP
Corrections Issued 6/13/2025 DANIEL YIP
Applicant returned to address corrections 6/24/2025 DANIEL SMILEY
Applicant returned to address corrections 7/16/2025 NGHI SU
Plan Check Approved 7/17/2025 CARLOS MONTES
Issued 7/19/2025 APPLICANT
CofO in Progress 5/7/2026 MICHAEL CORTEZ
CofO Issued 5/28/2026 RUBEN SALAS
Permit Finaled 5/28/2026 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 6/17/2025 JESUS LUNA
Eng Process Fee Ord 176,300 Cleared 6/18/2025 JESUS LUNA
Sewer availability Cleared 6/18/2025 JESUS LUNA

Contact Information

Contractor Owner-Builder       ,
Engineer Warling,, Jeffrey Paul; Lic. No.: C43743 1792 PEREGRINE CT      SIMI VALLEY, CA 93065

Inspector Information

RAUL OLAGI, (818) 374-1166 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 7/24/2025 Partial Approval JACK KARGODORIAN
BUILDING-Rough-Frame 10/10/2025 Approved JACK KARGODORIAN
ELECTRICAL-Rough 10/10/2025 Approved JACK KARGODORIAN
Green Building Rough 10/10/2025 Approved JACK KARGODORIAN
PLUMBING-Rough 10/10/2025 Approved JACK KARGODORIAN
Drywall Nailing 10/20/2025 Approved JACK KARGODORIAN
Insulation 10/20/2025 Approved JACK KARGODORIAN
Shower Pan 10/20/2025 Corrections Issued JACK KARGODORIAN
Shower Pan 10/22/2025 Approved JACK KARGODORIAN
ELECTRICAL-Final 4/9/2026 Approved JAVIER RAMOS JR
Final 4/9/2026 Corrections Issued JAVIER RAMOS JR
Green Building Final 4/9/2026 Not Ready for Inspection JAVIER RAMOS JR
HVAC-Final 4/9/2026 Approved JAVIER RAMOS JR
PLUMBING-Final 4/9/2026 Approved JAVIER RAMOS JR
SGSOV-Seismic Gas S/O Valve 4/9/2026 SGSOV Approved JAVIER RAMOS JR
Smoke Detectors 4/9/2026 Approved JAVIER RAMOS JR
Final 4/29/2026 Corrections Issued MICHAEL CORTEZ
Green Building Final 4/29/2026 Approved MICHAEL CORTEZ
Final 5/6/2026 OK to Issue CofO MICHAEL CORTEZ