1046 W 37TH ST 90731
Certificate Information: 1046 W 37TH ST 90731
- Application / Permit
- 25016-10000-18359
- Plan Check / Job No.
- B25LA23745
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- Eplan: Soft-Story Seismic Retrofit per LABC Chapter 93: Install of one (1) Ordinary Steel Moment Frame
- Permit Issued
- Issued on 8/29/2025
- Issuing Office
- Current Status
- Issued on 8/29/2025
Permit Application Status History
| Submitted | 6/6/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 6/12/2025 | BIDYUT RATH |
| Corrections Issued | 6/18/2025 | BIDYUT RATH |
| Quality Review Completed | 6/26/2025 | HANS SANTIAGO |
| Applicant returned to address corrections | 7/22/2025 | BIDYUT RATH |
| Applicant returned to address corrections | 7/23/2025 | BIDYUT RATH |
| Plan Check Approved | 7/25/2025 | BIDYUT RATH |
| Issued | 8/29/2025 | APPLICANT |
Permit Application Clearance Information
| Tenant Habitability Plan | Cleared | 8/26/2025 | ARIC DEFUSCO |
Contact Information
| Contractor | R G Builders Inc; Lic. No.: 1106018-B | 7558 MIDFIELD AVE LOS ANGELES, CA 90045 |
| Engineer | Labib,, Youhanna T.; Lic. No.: NA4549 | 319 MAIN ST EL SEGUNDO, CA 90245 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 12/15/2025 | Approved | DARRYL ARNOLD |
| Structural Steel Frame | 1/28/2026 | Not Ready for Inspection | ALFREDO LOPEZ |
| Wood Frame | 1/28/2026 | Not Ready for Inspection | ALFREDO LOPEZ |
| Structural Steel Frame | 1/30/2026 | Corrections Issued | JOEY BUCHANAN |
| Wood Frame | 1/30/2026 | Approved | JOEY BUCHANAN |
| Structural Steel Frame | 2/18/2026 | Approved | DAVID TSAU |
| Wood Frame | 2/18/2026 | Approved | DAVID TSAU |
| Interior/Exterior Lathing | 3/4/2026 | Approved | DAVID TSAU |
| Drywall Nailing | 3/26/2026 | Approved | DAVID TSAU |
| Final | 4/14/2026 | Not Ready for Inspection | DARRYL ARNOLD |
| SGSOV-Seismic Gas S/O Valve | 4/14/2026 | SGSOV Not Ready | DARRYL ARNOLD |
| Smoke Detectors | 4/14/2026 | Not Ready for Inspection | DARRYL ARNOLD |
| Final | 4/15/2026 | Not Ready for Inspection | DARRYL ARNOLD |
| SGSOV-Seismic Gas S/O Valve | 4/15/2026 | SGSOV Not Ready | DARRYL ARNOLD |
| Smoke Detectors | 4/15/2026 | Corrections Issued | DARRYL ARNOLD |