164 N AVENUE 25 90031
Certificate Information: 164 N AVENUE 25 90031
- Application / Permit
- 25016-10000-18351
- Plan Check / Job No.
- B25LA23735
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- EPLAN: INTERIOR REMODEL; RELOCATE KITCHEN, REMODEL EXISTING BATH, NEW LAUNDRY, THREE NEW WALK IN CLOSETS, TWO NEW BATHROOMS, NO NEW SQUARE FEET. *** "COMPLY WITH DEPARTMENT ORDER effective date 04/30/2025. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE". CEIS Case Number is 1047562.***
- Permit Issued
- Issued on 7/23/2025
- Issuing Office
- Current Status
- Permit Finaled on 3/2/2026
Permit Application Status History
| Submitted | 6/9/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 6/11/2025 | JOHNPAUL ISIP |
| Corrections Issued | 6/12/2025 | JOHNPAUL ISIP |
| Applicant returned to address corrections | 7/8/2025 | AMY GUEVARRA |
| Plan Check Approved | 7/22/2025 | JOHNPAUL ISIP |
| Issued | 7/23/2025 | APPLICANT |
| Permit Finaled | 2/25/2026 | JACOB SEGURA |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Mcinc Construction Inc; Lic. No.: 1087192-B | , |
| Engineer | Beaudette,, Brandon Jay; Lic. No.: C91406 | 32003 54TH COURT S AUBURN, WA 98001 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 9/4/2025 | Corrections Issued | JACOB SEGURA |
| Rough-Elec/Plmb/HVAC | 9/4/2025 | Corrections Issued | JACOB SEGURA |
| ELECTRICAL-Rough | 9/16/2025 | Partial Approval | JACOB SEGURA |
| HVAC-Rough | 9/16/2025 | No Access for Inspection | JACOB SEGURA |
| PLUMBING-Rough | 9/16/2025 | Corrections Issued | JACOB SEGURA |
| Wood Frame | 9/16/2025 | Not Ready for Inspection | JACOB SEGURA |
| Footing/Foundation/Slab | 11/12/2025 | Partial Approval | JACOB SEGURA |
| BUILDING-Rough-Frame | 11/19/2025 | Corrections Issued | JACOB SEGURA |
| MERV13>=Rough | 11/19/2025 | No Access for Inspection | JACOB SEGURA |
| BUILDING-Rough-Frame | 11/24/2025 | Partial Approval | JACOB SEGURA |
| ELECTRICAL-Rough | 11/24/2025 | Partial Approval | JACOB SEGURA |
| HVAC-Rough | 11/24/2025 | Partial Approval | JACOB SEGURA |
| Insulation | 11/24/2025 | Partial Approval | JACOB SEGURA |
| Interior/Exterior Lathing | 11/24/2025 | Partial Approval | JACOB SEGURA |
| PLUMBING-Rough | 11/24/2025 | Partial Approval | JACOB SEGURA |
| Drywall Nailing | 12/2/2025 | Partial Approval | JACOB SEGURA |
| BUILDING-Rough-Frame | 1/28/2026 | Not Ready for Inspection | JACOB SEGURA |
| Final | 1/28/2026 | Corrections Issued | JACOB SEGURA |
| MERV13>=Final | 1/28/2026 | Not Ready for Inspection | JACOB SEGURA |
| MERV13>=Rough | 1/28/2026 | Not Ready for Inspection | JACOB SEGURA |
| SGSOV-Seismic Gas S/O Valve | 1/28/2026 | SGSOV Not Ready | JACOB SEGURA |
| Smoke Detectors | 1/28/2026 | Approved | JACOB SEGURA |
| BUILDING-Rough-Frame | 2/9/2026 | Not Ready for Inspection | JACOB SEGURA |
| Final | 2/9/2026 | Corrections Issued | JACOB SEGURA |
| MERV13>=Final | 2/9/2026 | Not Ready for Inspection | JACOB SEGURA |
| MERV13>=Rough | 2/9/2026 | Not Ready for Inspection | JACOB SEGURA |
| SGSOV-Seismic Gas S/O Valve | 2/9/2026 | SGSOV Not Ready | JACOB SEGURA |
| BUILDING-Rough-Frame | 2/17/2026 | Approved | JACOB SEGURA |
| Final | 2/17/2026 | Corrections Issued | JACOB SEGURA |
| MERV13>=Final | 2/17/2026 | Approved | JACOB SEGURA |
| MERV13>=Rough | 2/17/2026 | Approved | JACOB SEGURA |
| SGSOV-Seismic Gas S/O Valve | 2/17/2026 | SGSOV Approved | JACOB SEGURA |
| Final | 2/25/2026 | Permit Finaled | JACOB SEGURA |