164 N AVENUE 25 90031

Certificate Information: 164 N AVENUE 25 90031

Application / Permit
25016-10000-18351
Plan Check / Job No.
B25LA23735
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
EPLAN: INTERIOR REMODEL; RELOCATE KITCHEN, REMODEL EXISTING BATH, NEW LAUNDRY, THREE NEW WALK IN CLOSETS, TWO NEW BATHROOMS, NO NEW SQUARE FEET. *** "COMPLY WITH DEPARTMENT ORDER effective date 04/30/2025. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE". CEIS Case Number is 1047562.***
Permit Issued
Issued on 7/23/2025
Issuing Office
Current Status
Permit Finaled on 3/2/2026

Permit Application Status History

Submitted 6/9/2025 APPLICANT
Assigned to Plan Check Engineer 6/11/2025 JOHNPAUL ISIP
Corrections Issued 6/12/2025 JOHNPAUL ISIP
Applicant returned to address corrections 7/8/2025 AMY GUEVARRA
Plan Check Approved 7/22/2025 JOHNPAUL ISIP
Issued 7/23/2025 APPLICANT
Permit Finaled 2/25/2026 JACOB SEGURA

Permit Application Clearance Information

No Data Available.

Contact Information

Contractor Mcinc Construction Inc; Lic. No.: 1087192-B       ,
Engineer Beaudette,, Brandon Jay; Lic. No.: C91406 32003 54TH COURT S      AUBURN, WA 98001

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 9/4/2025 Corrections Issued JACOB SEGURA
Rough-Elec/Plmb/HVAC 9/4/2025 Corrections Issued JACOB SEGURA
ELECTRICAL-Rough 9/16/2025 Partial Approval JACOB SEGURA
HVAC-Rough 9/16/2025 No Access for Inspection JACOB SEGURA
PLUMBING-Rough 9/16/2025 Corrections Issued JACOB SEGURA
Wood Frame 9/16/2025 Not Ready for Inspection JACOB SEGURA
Footing/Foundation/Slab 11/12/2025 Partial Approval JACOB SEGURA
BUILDING-Rough-Frame 11/19/2025 Corrections Issued JACOB SEGURA
MERV13>=Rough 11/19/2025 No Access for Inspection JACOB SEGURA
BUILDING-Rough-Frame 11/24/2025 Partial Approval JACOB SEGURA
ELECTRICAL-Rough 11/24/2025 Partial Approval JACOB SEGURA
HVAC-Rough 11/24/2025 Partial Approval JACOB SEGURA
Insulation 11/24/2025 Partial Approval JACOB SEGURA
Interior/Exterior Lathing 11/24/2025 Partial Approval JACOB SEGURA
PLUMBING-Rough 11/24/2025 Partial Approval JACOB SEGURA
Drywall Nailing 12/2/2025 Partial Approval JACOB SEGURA
BUILDING-Rough-Frame 1/28/2026 Not Ready for Inspection JACOB SEGURA
Final 1/28/2026 Corrections Issued JACOB SEGURA
MERV13>=Final 1/28/2026 Not Ready for Inspection JACOB SEGURA
MERV13>=Rough 1/28/2026 Not Ready for Inspection JACOB SEGURA
SGSOV-Seismic Gas S/O Valve 1/28/2026 SGSOV Not Ready JACOB SEGURA
Smoke Detectors 1/28/2026 Approved JACOB SEGURA
BUILDING-Rough-Frame 2/9/2026 Not Ready for Inspection JACOB SEGURA
Final 2/9/2026 Corrections Issued JACOB SEGURA
MERV13>=Final 2/9/2026 Not Ready for Inspection JACOB SEGURA
MERV13>=Rough 2/9/2026 Not Ready for Inspection JACOB SEGURA
SGSOV-Seismic Gas S/O Valve 2/9/2026 SGSOV Not Ready JACOB SEGURA
BUILDING-Rough-Frame 2/17/2026 Approved JACOB SEGURA
Final 2/17/2026 Corrections Issued JACOB SEGURA
MERV13>=Final 2/17/2026 Approved JACOB SEGURA
MERV13>=Rough 2/17/2026 Approved JACOB SEGURA
SGSOV-Seismic Gas S/O Valve 2/17/2026 SGSOV Approved JACOB SEGURA
Final 2/25/2026 Permit Finaled JACOB SEGURA