8072 S COWAN AVE 90045
Certificate Information: 8072 S COWAN AVE 90045
- Application / Permit
- 25016-10000-18021
- Plan Check / Job No.
- B25LA23222
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- REMODEL (E) SFD INCLUDING KITCHEN, BEDROOMS, BATHROOMS, AND REPLACE WINDOWS
- Permit Issued
- Issued on 6/11/2025
- Issuing Office
- Current Status
- Permit Finaled on 9/2/2025
Permit Application Status History
| Submitted | 6/4/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 6/4/2025 | NEHEMIAS RAMOS |
| Corrections Issued | 6/4/2025 | NEHEMIAS RAMOS |
| Plan Check Approved | 6/11/2025 | MINA HABILI |
| Issued | 6/11/2025 | APPLICANT |
| Permit Finaled | 8/29/2025 | RUBEN RIVAS |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 6/9/2025 | MICHAEL BROWN |
| Sewer availability | Cleared | 6/9/2025 | MICHAEL BROWN |
Contact Information
| Contractor | Construction Masters; Lic. No.: 762655-B | 18075 VENTURA BLVD STE 135 ENCINO, CA 91316 |
| Engineer | Khazra,, Afshin; Lic. No.: C50250 | 22855 PAUL REVERE DR CALABASAS, CA 91302 |
Inspector Information
| MORRIS JACKSON, (310) 914-3885 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 6/17/2025 | Partial Approval | RUBEN RIVAS |
| Footing/Foundation/Slab | 6/17/2025 | Partial Approval | RUBEN RIVAS |
| BUILDING-Rough-Frame | 6/18/2025 | Partial Approval | RUBEN RIVAS |
| ELECTRICAL-Rough | 6/18/2025 | Partial Approval | RUBEN RIVAS |
| Floor/Roof Diaphrgm/Shear Wall | 6/18/2025 | Corrections Issued | RUBEN RIVAS |
| Floor/Roof Diaphrgm/Shear Wall | 6/20/2025 | Partial Approval | RUBEN RIVAS |
| Interior/Exterior Lathing | 6/20/2025 | Partial Approval | RUBEN RIVAS |
| Wood Frame | 6/20/2025 | Partial Approval | RUBEN RIVAS |
| Interior/Exterior Lathing | 6/23/2025 | Not Ready for Inspection | JAYLIN GRAVITTE |
| Interior/Exterior Lathing | 6/25/2025 | Approved | RUBEN RIVAS |
| Insulation | 6/26/2025 | Approved | RUBEN RIVAS |
| Drywall Nailing | 6/30/2025 | Approved | RUBEN RIVAS |
| Final | 8/26/2025 | Corrections Issued | RUBEN RIVAS |
| SGSOV-Seismic Gas S/O Valve | 8/26/2025 | SGSOV Approved | RUBEN RIVAS |
| Smoke Detectors | 8/26/2025 | Approved | RUBEN RIVAS |
| Final | 8/29/2025 | Permit Finaled | RUBEN RIVAS |
| PLUMBING-Final | 8/29/2025 | Approved | RUBEN RIVAS |