8072 S COWAN AVE 90045

Certificate Information: 8072 S COWAN AVE 90045

Application / Permit
25016-10000-18021
Plan Check / Job No.
B25LA23222
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
REMODEL (E) SFD INCLUDING KITCHEN, BEDROOMS, BATHROOMS, AND REPLACE WINDOWS
Permit Issued
Issued on 6/11/2025
Issuing Office
Current Status
Permit Finaled on 9/2/2025

Permit Application Status History

Submitted 6/4/2025 APPLICANT
Assigned to Plan Check Engineer 6/4/2025 NEHEMIAS RAMOS
Corrections Issued 6/4/2025 NEHEMIAS RAMOS
Plan Check Approved 6/11/2025 MINA HABILI
Issued 6/11/2025 APPLICANT
Permit Finaled 8/29/2025 RUBEN RIVAS

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 6/9/2025 MICHAEL BROWN
Sewer availability Cleared 6/9/2025 MICHAEL BROWN

Contact Information

Contractor Construction Masters; Lic. No.: 762655-B 18075 VENTURA BLVD STE 135      ENCINO, CA 91316
Engineer Khazra,, Afshin; Lic. No.: C50250 22855 PAUL REVERE DR      CALABASAS, CA 91302

Inspector Information

MORRIS JACKSON, (310) 914-3885 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 6/17/2025 Partial Approval RUBEN RIVAS
Footing/Foundation/Slab 6/17/2025 Partial Approval RUBEN RIVAS
BUILDING-Rough-Frame 6/18/2025 Partial Approval RUBEN RIVAS
ELECTRICAL-Rough 6/18/2025 Partial Approval RUBEN RIVAS
Floor/Roof Diaphrgm/Shear Wall 6/18/2025 Corrections Issued RUBEN RIVAS
Floor/Roof Diaphrgm/Shear Wall 6/20/2025 Partial Approval RUBEN RIVAS
Interior/Exterior Lathing 6/20/2025 Partial Approval RUBEN RIVAS
Wood Frame 6/20/2025 Partial Approval RUBEN RIVAS
Interior/Exterior Lathing 6/23/2025 Not Ready for Inspection JAYLIN GRAVITTE
Interior/Exterior Lathing 6/25/2025 Approved RUBEN RIVAS
Insulation 6/26/2025 Approved RUBEN RIVAS
Drywall Nailing 6/30/2025 Approved RUBEN RIVAS
Final 8/26/2025 Corrections Issued RUBEN RIVAS
SGSOV-Seismic Gas S/O Valve 8/26/2025 SGSOV Approved RUBEN RIVAS
Smoke Detectors 8/26/2025 Approved RUBEN RIVAS
Final 8/29/2025 Permit Finaled RUBEN RIVAS
PLUMBING-Final 8/29/2025 Approved RUBEN RIVAS